Resolved
To note the information.
Audit Committee noted this item on Tuesday 10 December 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the information.
Arrangements to Secure Value for Money - Progress Gedling Borough Council – years ended 31 March 2022 and 31 March 2023
November 2024 Introduction
Our work on VFM arrangements is substantially well progressed and this report was produced at a point in time to meet the Audit Committee date. Under the current guidance, the Auditor’s Annual Report, which finalises the VFM commentary is to be issued within 3 months of the date of issuing the audit report. We are on track to meet that deadline. This report, therefore, represents our findings to date, with some residual work to complete through our quality control arrangements. We shall issue a final report once our work is fully complete.
Our reports are prepared in the context of the ‘Statement of responsibilities of auditors and audited bodies’ issued by Public Sector Audit Appointments Ltd. Reports and letters prepared by appointed auditors and addressed to members or officers are prepared for the sole use of the Council. No responsibility is accepted to any member or officer in their individual capacity or to any third party. Forvis Mazars LLP is the UK firm of Forvis Mazars Global, a leading global professional services network. Forvis Mazars LLP is a limited liability partnership registered in England and Wales with registered number OC308299 and with its registered office at 30 Old Bailey, London, EC4M 7AU. Registered to carry on audit work in the UK by the Institute of Chartered Accountants in England and Wales. Details about our audit registration can be viewed at www.auditregister.org.uk under reference number C001139861. VAT number: GB 839 8356 73 2 VFM arrangements
Overall Summary VFM arrangements – Overall summary
Approach to Value for Money arrangements work Although we describe this work as planning work, we keep our understanding of arrangements under review and update our risk assessment throughout the audit to reflect emerging issues that may suggest there are We are required to consider whether the Council has made proper arrangements for securing economy, further risks of significant weaknesses. efficiency and effectiveness in its use of resources. The NAO issues guidance to auditors that underpins the work we are required to carry out and sets out the reporting criteria that we are required to consider. The reporting criteria are: Phase 2 - Additional risk-based procedures and evaluation Where we identify risks of significant weaknesses in arrangements, we design a programme of work to enable us to decide whether there are actual significant weaknesses in arrangements. We use our professional Financial sustainability - How the Council plans and manages its resources to ensure it can judgement and have regard to guidance issued by the NAO in determining the extent to which an identified continue to deliver its services. weakness is significant.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Mazars: 21-22 and 22-23 VFM Progress Report: DraftReport | 647 KB | DownloadRead as text |
Follow Audit Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 20 Oct 2026 | BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... | Noted | Open |
| 20 Oct 2026 | Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... | Noted | Open |
| 20 Oct 2026 | Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... | Noted | Open |
| 20 Oct 2026 | Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.