That Members (i) authorise the Director of Place to make an order under s257(1A) of the Town and Country Planning Act 1990 (as amended) to divert Arnold Footpath No. 3 for a distance of approx. 230m as per drawing ref 2326-03-01 Rev V, to carry out the procedure under Schedule 14 of the Town and Country Planning Act 1990 for confirmation of the order and, (ii) following consultation and publication, to confirm the order if there are no outstanding objections to the order. However, if there are outstanding objections, the matter be referred to the Secretary of State for determination.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
1.1The application is before Planning Committee to seek authorisation to make an order to divert Arnold Footpath No. 3, between Crawford Rise and Mapperley Plains, Arnold, for a distance of approx. 230m. The application is made pursuant to Section 257(1A) of the Town and Country Planning Act 1990 (as amended), which allows for a footpath to be diverted provided it is necessary to enable development to be carried out in accordance with a valid planning permission.
2.0Site description
2.1The application site currently a field and the public right of way links Mapperley Plains to the north-east of the field to Crawford Rise to the south- west of the site.
3.0Relevant planning history
3.12023/0926 Full planning permission was granted in January 2025 for “Erection of 54 dwellings (38 open market and 16 affordable dwellings), along with the provision of associated public open space and infrastructure.”
4.0Proposed development
4.1Arnold Footpath No. 3 crosses the development site subject to planning permission 2023/0926. To facilitate the erection of a number of the approved dwellings, Arnold Footpath 3 would need to be diverted.
4.2Currently the footpath runs in a straight line diagonally across the site from the north-east corner of the field to the south west corner of the field. The current footpath is approx. 230 metres in length. 4.3 The footpath’s entrance and exit to and from the field is proposed to remain unaltered. However, it is proposed that from the entrance from Mapperely Plains, the footpath will run in straight line along the northern boundary of the field before traversing south along Street 2 then west along Main Street and the larger public open space before turning south along the smaller area of public open space and then west onto Crawford Rise. The proposed route is shown on drawing no. 2326-03-01 Rev V.
5.0Consultations
5.1Nottinghamshire County Council Rights of Way Officer;- No objection
5.2Neighbours;- A site notice has been displayed at both ends of the section of footpath that is to be diverted. No neighbour letters have been received.
6.0Planning considerations
Legal framework
6.1Section 257(1) of the Town and Country Planning Act 1990 as amended states that a competent authority may by Order authorise the stopping up or diversion of any footpath if they are satisfied that it is necessary to do so in order to allow a development to be carried out in accordance with a planning permission and is not yet substantially complete, as is the case here.
Section 257 - Footpaths, bridleways and restricted byways affected by development: orders by other authorities
(1) Subject to section 259, a competent authority may by order authorise the stopping up or diversion of any footpath, bridleway or restricted byway if they are satisfied that it is necessary to do so in order to enable development to be carried out -
(a) in accordance with planning permission granted under Part III or section 293A, or
(b) by a government department
(1A) Subject to section 259, a competent authority may by order authorise the stopping up or diversion of any footpath, bridleway or restricted byway if they are satisfied that –
(a) an application for planning permission in respect of development has been made under Part 3, and
(b) if the application were granted it would be necessary to authorise the stopping up or diversion in order to enable the development to be carried out
(2) An order under this section may, if the competent authority are satisfied that it should do so, provide— (a) for the creation of an alternative highway for use as a replacement for the one authorised by the order to be stopped up or diverted, or for the improvement of an existing highway for such use;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.