AI summaryGedling Borough Council Cabinet approves 10-year Regeneration Plan and 4-year Investment Plan for Greater Carlton, acting as accountable body for government neighbourhood funding.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet approved both plans as the accountable body
MoneyNo sums in the reportCapacity funding received; main grant agreement pending
What happens nextSubmit plans to MHCLG by 28 November 2025Formal grant agreement expected by January 2026
Who it affectsGreater Carlton neighbourhood areaResidents, businesses and stakeholders in the area

What was decided

Cabinet approved the 10-year Regeneration Plan and 4-year Investment Plan as the accountable body for the Greater Carlton Plan for Neighbourhoods. Report 11.1

Cabinet noted the findings of the public and stakeholder consultation that informed the proposals.

Why

The Council is the accountable body and must confirm the Board and ensure the programme meets its internal standing orders and the funding conditions set by MHCLG. Report 11.1, 6.1, 6.2

Officers oversaw the plans to make sure they comply with funding conditions and standing orders, and failure to approve could put the funding at risk or delay delivery. Report 4.1, 11.1

What happens next

The plans must be submitted to MHCLG for approval by 28th November 2025, in line with the Plan for Neighbourhoods Guidance. Report 6.3

A formal grant agreement for the Initial 4 Year Investment Plan is expected by January 2026; the Council will not commit any delivery expenditure until it is received. Report 5.2, 5.3

The Equalities Impact Assessment and Carbon Reduction Impact Assessment that sit with the plans will be formally approved by both the Board and the Council. Report 7.1, 8.1

Options considered

  • Chosen: Approve the Regeneration Plan and 4-year Investment Plan as the accountable body. Ensures the Council meets its obligations and protects allocated funding Report 11.1, 4.1
  • Rejected: Do not approve the plans. Could jeopardise the funding or cause delays in delivery Report 4.1

Implications

  • Legal: The Council, as accountable body, must follow its Standing Orders, Financial Regulations and Contract and Procurement Rules, with Section 151 officer duties for the funding. Report 6.1, 6.2
  • Financial: Capacity funding has been received; further expenditure for delivery is on hold until a formal grant agreement is received. Report 5.1, 5.3
  • Equalities: The plans include an Equalities Impact Assessment to be formally approved by the Board and the Council. Report 7.1
  • Climate: The plans include a Carbon Reduction Impact Assessment and consider carbon reduction and sustainability interventions, though none arise directly from this report. Report 8.1
  • Risk: MHCLG has given verbal assurance that grant funding is secured, but no formal grant agreement has yet been received. Report 5.2

Who and where

  • Residents, businesses and stakeholders in the Greater Carlton neighbourhood area Report 9.1
  • The Greater Nottingham Neighbourhood Board (working in partnership with the accountable body) Report 6.1, 5.2
  • Gedling Borough Council as the accountable body and its Section 151 officer Report 6.1, 6.2

Timeline

  • 7 March 2025: Government issued the Plan for Neighbourhoods prospectus setting out funding requirements Report 6.1
  • November 2025: Deputy Chief Financial Officer and Monitoring Officer approved the report Report P16, P17, P18, P19, P20
  • 28th November 2025: Deadline to submit the Regeneration Plan and Investment Plan to MHCLG for approval Report 6.3
  • January 2026: Formal grant agreement for the Initial 4 Year Investment Plan expected, in time for year one preparation Report 5.2

Plain English for the jargon

  • MHCLG: Ministry of Housing, Communities and Local Government, the government department providing the funding
  • GCPfN: Greater Carlton Plan for Neighbourhoods, the 10-year regeneration programme covered by the decision
  • Accountable body: The local authority (Gedling Borough Council) that holds legal responsibility for spending the grant and supporting the Board
  • EIA: Equalities Impact Assessment, required as part of the plan approval
  • CIA: Carbon Reduction Impact Assessment, required as part of the plan approval
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item50

Resolved

THAT CABINET: 1. Approves the 10-year Regeneration Plan and 4 year Investment Plan, as the accountable body. 2. Notes the findings of the public and stakeholder consultation that have informed the development of the proposals.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Cabinet

Report to Cabinet

Subject: Greater Carlton Plan for Neighbourhoods

Date: 19 November 2025

Author: Assistant Director for Economic Growth & Regeneration

Wards Affected Carlton, Carlton Hill, Cavendish, Porchester, Pheonix, Gedling, Netherfield, Colwick and Trent Valley

Purpose To seek approval, as the accountable body, of the ‘10 year Regeneration Plan’ and ‘4 year Investment Plan’ which outlines the Greater Carlton Neighbourhood Board’s longer term strategic vision for Greater Carlton through the Plan for Neighbourhoods programme.

To also note the outcome of the Greater Carlton Long Term Plan for Towns public consultation and Greater Carlton Plan for Neighbourhoods targeted engagement that have been considered as part of the proposals.

Key Decision This is a Key Decision as it is likely to result in expenditure through grant funding in excess of £500,000 through the lifecycle of the programme and is likely to have an impact on residents and communities working in more than two wards.

Recommendation(s)

THAT CABINET:

1. Approves the 10 year Regeneration Plan and 4 year Investment Plan, as the accountable body.

2. Notes the findings of the public and stakeholder consultation that have informed the development of the proposals. 1. Background

1.1On 6 March 2024, the Council was notified by the former Government that the Long Term Plan for Towns funding programme that had been originally announced in September 2023 had been extended from 55 to 75 towns and would now include Carlton. The former Government Minister confirmed that each town will receive “endowment-style” funding and support worth up to £20m over a 10 year period.

1.2Gedling Borough Council, as the accountable body for the programme, subsequently established a Town Board (’the Board’) and appointed Sir John Peace to the role of interim independent Chair.

1.3In full consultation with the local community, the Board developed a draft 10 year vision for Carlton including a 3-year investment plan outlining how funds would to be allocated. The draft plan included interventions to address the needs and priorities of Greater Carlton and refers to the themes of the former guidance.

1.4The work of the Board was stopped in December 2024 as the programme was paused by the Labour Government. In this period, the Board awaited the publication of a new prospectus and technical guidance by MHCLG. A transition from the Plan for Towns was driven by the need to address the disparities in funding and support for different areas across the UK. The Plan for Towns had been deemed restrictive and further flexibility was desired for its allocation of funding. A shift would also allow the programme to reflect a broader government initiative to focus on community-led change.

1.5The new Plan for Neighbourhoods guidance and prospectus was published on 7 March 2025 as part of the government’s plan to ensure that nowhere is left behind. The Plan for Neighbourhoods aims for Neighbourhood Boards to drive growth locally by improving the physical and social infrastructure of their community, delivering tangible improvements to the everyday lives of these communities by targeting three strategic priorities: thriving places, stronger communities, and taking back control. The three priorities identify a range of measures under the themes of:

• Regeneration, high streets and heritage • Housing • Work, productivity and skills • Cohesion • Health and wellbeing • Transport • Safety and security • Education and opportunity 1.6 Further information and guidance for the Plan for Neighbourhoods prospectus can be found through the following link: Plan for Neighbourhoods: prospectus - GOV.UK

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GCPfN Boundary changeAppendix 1 551 KB Download
PDF
GCLTPfT Round 1 consultation: Overview 2024Appendix 2 442 KB Download
PDF
GCLTPfT Round 1 consultation: Report 2024Appendix 3 950 KB Download
PDF
GCLTPfT Round 2 consultation: Report 2024Appendix 4 281 KB Download
PDF
GCPfN Engagement Overview 2025Appendix 5 177 KB Download
PDF
Greater Carlton Long Term Plan for NeighbourhoodsReport 236 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
JC
Councillor John ClarkeChair, present
JH
Councillor Jenny HollingsworthVice-Chair, present
DE
Councillor David EllisCommittee Member, present
KF
Councillor Kathryn FoxCommittee Member, present
VM
Councillor Viv McCrossenCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, present
HW
Councillor Henry WheelerCommittee Member, present
MH
Mike HillOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Mike AveryOfficer, in attendance
TA
Tina AdamsOfficer, in attendance

All 17 on the meeting page

More from Gedling Cabinet

All decisions
MeetingDecisionOutcome
16 Jul 2026 To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
16 Jul 2026 Forward Plan1) To note the report. Noted Open
16 Jul 2026 Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... Noted Open
16 Jul 2026 Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... Agreed Open
16 Jul 2026 Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies