Gedling Borough Council
Cabinet, Wednesday 19 November 2025 at 2.00pm

Gedling Plan Quarter 2 Performance 2025/2026 report

Noted Executive 3 papers

AI summaryGedling Cabinet noted Q2 2025/26 performance: 33 of 69 planned milestones completed and 12 of 30 indicators met or exceeded target, with one milestone off track.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedQuarter 2 2025/26 progress against indicators and delivery plan actions was noted.
MoneyNo financial implications from this report.
What happens nextQuarterly monitoring continuesPerformance will be tracked in future quarters against the same plans.
Who it affectsBorough wideThe performance report covers all areas of the council.

What was decided

Cabinet noted progress against Improvement Performance Indicators for quarter 2 of 2025/26. Report P7

Cabinet noted progress against Annual Delivery Plan Actions. Report P8

Why

To keep members informed of progress against the Annual Delivery Plan and the Gedling Plan. Report 13.1

Performance reports offer an early warning system where targets may not be secured. Report 1.3

What happens next

A resourcing report will go to the senior leadership team in November to address delays in housing benefit and council tax reduction processing. Report P51, P52

The off track milestone on a digital inclusion approach will have corrective action implemented to meet the year end deadline. Report 2.5

Future reports will continue to track the 189 annual milestones and the 30 quarterly performance indicators. Report 2.3, P34

Options considered

  • Chosen: Present the quarterly performance update. Keeps Cabinet aware of progress against the delivery plan and indicators. Report 6.1
  • Rejected: Not to present an update. Cabinet would not be aware of Q2 2025/26 performance. Report 6.1

Implications

  • Financial: No financial implications arising from this report. Report 7.1
  • Legal: No legal implications arising from this report. Report 8.1
  • Equalities: No equalities implications arising from this report. Report 9.1
  • Climate: No carbon reduction or sustainability implications arising from this report. Report 10.1
  • Staffing: Loss of a team leader and one administrative team member is contributing to delays in housing benefit and council tax reduction processing. Report P51, P52
  • Risk: Sickness absence is 13.45 days against a 9 day target, driven by long term illness in Environmental Services. Report P58, P59

Who and where

  • All residents and businesses in the borough Report P1
  • Waste Services customers, who account for 75% of all complaints Report P65
  • Housing benefit and council tax reduction claimants, affected by processing delays Report P51, P52

Timeline

  • July to September 2025: Quarter 2 reporting period, with 33 of 69 planned milestones completed. Report 2.4
  • September 2025: Issues and Options consultation on the local plan concluded with over 1500 responses. Report P28
  • Quarter 3 2025/26: Demolition of the waste depot shed is due for completion. Report P30
  • November 2025: A resourcing report on housing benefit and council tax reduction processing is due at the senior leadership team. Report P51, P52

Plain English for the jargon

  • Annual Delivery Plan: A plan with 52 actions across 6 themes agreed by Cabinet in March 2025 to deliver council priorities.
  • Milestone: A measurable step under each Annual Delivery Plan action used to track progress, with 189 set for 2025/26.
  • Traffic light assessment: A red, amber and green system used to judge if a performance indicator is on track.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item51

Resolved

THAT: 1) The progress against Improvement Performance Indicators for quarter 2 of 2025/26 be noted. 2) The progress against Annual Delivery Plan Actions be noted.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Cabinet

Wards affected

Borough wide

Purpose

To inform Cabinet in summary of the position against Performance Indicators and Annual Delivery Plan Actions in Quarter 2 of 2025/26.

Key Decision

This is not a key decision.

Recommendation

THAT:

The progress against Improvement Performance Indicators for quarter 2 of 2025/26 be noted.

The progress against Annual Delivery Plan Actions be noted

Background

1.1The Council has made a commitment to closely align budget and performance management. This is in line with accepted good practice.

1.2To deliver this commitment, systems to monitor performance against revenue and capital budgets, improvement activity and performance indicators have all been brought together and are now embedded in the way the Council works.

1.3In addition, performance reports focus directly on the Council’s priorities and offer an “early warning” system of instances where targets may not be secured.

1.4The assessment criteria used for indicators is based on red, amber and green traffic light symbols. To be assessed as green, performance indicators must be in line with their expected performance at that stage of the year determined within the performance management system.

1.5This report reflects a change to the usual format in that progress against the Annual Delivery Plan is now reported and replaces the previous section on the Gedling Plan actions.

2 Proposal

2.1It is proposed that Cabinet note the current performance information for Quarter 2 of 2025/26 as set out below –

2.2Annual Delivery Plan Actions

In March 2025 Cabinet agreed to the annual delivery plan with 52 actions spanning 6 themes -

 Customer Experience and Communities Programme  Smarter Working Programme  Depot Modernisation Programme  Gedling Growth  Leisure Transformation  Governance Control Framework

2.3Milestones have been identified under each action to assist the monitoring of progress against the delivery plan, of which there are a total of 189 covering all themes for 2025/26.

2.4For Q2 there were originally 69 milestones recorded as planned for delivery during July to September. 33 have been completed (please see appendix A for more details) and 36 were realigned to Q3 or Q4 as more information on these projects were made available and dependencies became known.

2.5Of the 36 milestones that have been realigned, 34 are ‘on track’ (signifying that milestones are progressing as planned – status green) and 2 milestones are being closely monitored, 1 has been identified as ‘at risk’ where there are issues or concerns that could impact delivery but are being addressed or mitigated. 1 has been identified as ‘off track’ where issues do exist that are impacting progress, and corrective action is being implemented to meet the year-end deadline. The milestone ‘off-track’ is ‘Create an action plan to drive delivery’ and is related to the Annual Delivery Plan action – ‘Created a digital inclusion approach to support customers and employees’.

2.6There were 30 milestones completed in Quarter 1 and 33 completed in quarter 2 against 189 due for the whole year. This represents a cumulative completion rate of milestones of 33.33% (the number of completed and expected milestones below). The completion rate is expected to significantly increase in quarter 3 as the milestones tracking ‘Green’ are completed.

Quarter 1 Quarter 2 Quarter 3 Quarter 4 Completed Completed Expected Expected 30 33 73 53

2.7

3 Achievements

3.1Focussed on deliverables from the Annual Delivery Plan, key achievements identified for particular attention during quarter 2 include:

 Between July and August 2025, our programme consultants, Mutual Ventures led a targeted engagement and consultation campaign with key stakeholders to support the development of themes, proposals and interventions for our 4-year investment plan.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Q2 202526 Completed MilestonesAppendix A 148 KB Download
PDF
Q2 20252026 Performance IndicatorsAppendix B 345 KB Download
PDF
Gedling Plan Quarter 2 Performance 2025/2026 reportReport 406 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 17 attended
JC
Councillor John ClarkeChair, present
JH
Councillor Jenny HollingsworthVice-Chair, present
DE
Councillor David EllisCommittee Member, present
KF
Councillor Kathryn FoxCommittee Member, present
VM
Councillor Viv McCrossenCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, present
HW
Councillor Henry WheelerCommittee Member, present
MH
Mike HillOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Mike AveryOfficer, in attendance
TA
Tina AdamsOfficer, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. Gedling Plan Quarter 2 Performance 2025/2026 reportThis decision
  2. Gedling BC Asset Management Plan 2026-2028Agreed
  3. The Gedling Visitor Economy Destination Management PlanApproved
  4. Gedling Plan Q4 Performance 2025/2026 ReportNoted
  5. Gedling Plan Annual Report 2025/2026Approved
  6. Gedling Local Development Plan - publication draftApproved

More from Gedling Cabinet

All decisions
MeetingDecisionOutcome
16 Jul 2026 To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
16 Jul 2026 Forward Plan1) To note the report. Noted Open
16 Jul 2026 Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... Noted Open
16 Jul 2026 Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... Agreed Open
16 Jul 2026 Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... Approved Open