Corporate Risk Strategy

Approved Executive 3 papers

AI summaryCabinet approved an updated Risk Management Framework, cutting corporate risks from 13 to 10 and adding new risks covering local government reorganisation and compliance.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAdoption of amended Risk Management Framework
MoneyNoneNo direct financial implications from the report
What happens nextImplement the updated frameworkCorporate Risk Board to merge with Budget and Performance Board
Who it affectsCouncil risk management and governanceAudit Committee to monitor through 4-monthly reporting

What was decided

Cabinet approved the amended Risk Management Framework at Appendix 1, following a recommendation from the Audit Committee. Report P2, 2.1

Corporate risks are reduced from 13 to 10, with new risks added for local government reorganisation and compliance, the capacity risk removed, and environment risk expanded to cover climate, emergencies and external events. Report 1.5, P8, P9, P10, P11

The Corporate Risk Board will merge with the Council's Budget and Performance Board, and reporting will move to a 4-monthly cycle aligned with budget reporting. Report 1.3

Why

An internal audit in August 2025 gave substantial assurance for framework design but moderate assurance for effectiveness, prompting a further review completed in December 2025. Report 1.1

The framework needed updating to reflect the Gedling Legacy Plan for 2026-28 and the risks from Local Government Reorganisation, as recommended by the Audit Committee. Report 1.2, 1.4, 10.1

Senior Leadership Team and risk board members were consulted and supported the changes. Report 1.3, 3.1

What happens next

The Audit Committee will continue to receive reports on risk against the Council's stated risk appetite of 'Moderate, tending always towards exposure to only modest risks'. Report 1.6

The merged Corporate Risk and Budget and Performance Board will operate with 4-monthly reporting aligned to the budget cycle. Report 1.3

Options considered

  • Chosen: Approve the amended Risk Management Framework. Considered necessary to keep the framework fit for purpose and reflective of current arrangements and risks. Report 3.1
  • Rejected: Do not approve the amendments. Would leave the framework not reflecting current risk management arrangements or key risks facing the organisation. Report 3.1

Implications

  • Financial: No direct financial implications arising from the report. Report 4.1
  • Legal: Supports the Council's duty under the Accounts and Audit Regulations 2015 to have a sound system of internal control including risk management. Report 5.1, 1.2
  • Equalities: An Equality Impact Assessment is included at Appendix 2. Report 6.1, P22
  • Climate: No carbon reduction or environmental sustainability implications, although the environment corporate risk has been expanded to cover climate change, emergency planning and war. Report 7.1, P11
  • Risk: Corporate risk appetite remains at Moderate, and new or expanded risks cover Local Government Reorganisation, compliance, and external or socio-economic risks. Report 1.6, P9, P11

Who and where

  • Audit Committee, which will continue to scrutinise risk reporting Report 1.6, 2.1
  • Senior Leadership Team and risk board members involved in the revised governance Report 1.3
  • Council officers and risk owners across the organisation Report 3.1

Timeline

  • March 2024: Cabinet approved the previous Risk Management Framework. Report 1.1
  • August 2025: Internal audit of risk management gave substantial design assurance and moderate effectiveness assurance. Report 1.1
  • December 2025: Further review of the framework was completed. Report 1.1
  • 23rd June: Audit Committee reviewed the proposed changes and recommended approval to Cabinet. Report 2.1
  • 2026-28: Gedling Legacy Plan sets the Council's priorities to which the revised framework aligns. Report 1.2

Plain English for the jargon

  • LGR: Local Government Reorganisation
  • Risk Appetite: The level of risk an organisation is willing to accept to achieve its objectives, here set at Moderate.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item136

Resolved

That Cabinet: 1) Following recommendation from the Audit Committee, approved the adoption of the amended Risk Management Framework at Appendix 1 to this report.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Cabinet

Recommendation

That Members:

1) Following recommendation from the Audit Committee, approve the adoption of the amended Risk Management Framework at Appendix 1 to this report.

Background

1.1In March 2024, Cabinet approved a new Risk Management Framework following recommendation from Audit Committee. This framework has driven the change to the risk management processes across the organisation. Since the adoption of the framework, significant work has been undertaken to improve the way the Council manages and reports risk and following an internal audit of the risk management process in August 2025 which resulted in a substantial assurance for design and moderate assurance for effectiveness, a further review of the framework was completed in December 2025.

1.2The Accounts and Audit Regulations 2015 require the Council to ensure that it has a sound system of internal controls which includes the effective management of risk. As the Council moves towards a period of change with Local Government Reorganisation, a more focused approach has been taken to the setting of Council priorities for 2026-28 through the approval of the Gedling Legacy Plan which sets out the Council’s priorities for the next 2 years.

1.3In order to support delivery of the Gedling Legacy Plan, a review of the Council’s current governance structures has been undertaken. In particular, consideration has been given to the effectiveness of the Council’s Corporate Risk Board and Budget and Performance Board which are officer boards established to ensure better and more effective management of risk and performance across the organisation. As a result of the review and following consultation with Senior Leadership Team and risk board members, it has been recommended that the Corporate Risk Board merge with the Council’s Budget and Performance Board. This will ensure better alignment in the review of performance, budget and risk. In addition, the reporting of all three has been aligned to mirror the budget reporting process of 4 monthly reporting. The Risk management Framework has been updated to reflect this change.

1.4Following recommendations from Audit Committee in relation to the current Corporate Risk Register and the need to reflect Local Government Reorganisation within it, a review of the Corporate Risk register has been undertaken by the Corporate Risk Board and Senior Leadership Team to ensure that corporate risks truly reflect the rising risks facing the organisation at the current time including LGR and other external impacts which present a risk to the organisation.

1.5The Corporate Risks have been amended and have reduced from 13 to 10 Corporate Risks they can be found at Appendix 2 of the Risk Framework. The key changes are:

 Some of the risk headings have been combined to ensure more effective tracking, for example, performance has been linked with projects and priorities, ICT and Data Security have been combined.

 A new risk has been added in relation to Local Government Reorganisation (LGR).

 The current corporate risk of capacity has been removed as it is recognised that this is in fact an outcome of a number of other risks including potentially LGR.

 A new risk of compliance has been added to ensure effective management of risks in relation to compliance with health and safety, procurement, data protection and a range of other legislative requirements.  Finally, the Environment risk has been expanded to cover any external environment or socio-economic risk which may impact the organisation including, climate change, emergency planning events and war. The new Corporate Risks are included at Appendix of the Risk Management Framework.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk StrategyReport 166 KB DownloadRead as text
PDF
EIA-form June 26Report 261 KB Download
PDF
Risk Management Framework Update June 2026Report 754 KB Download

At this meeting

Whole meeting

Who was there

6 of 16 attended
JC
Councillor John ClarkeChair, present
JH
Councillor Jenny HollingsworthVice-Chair, apologies
KF
Councillor Kathryn FoxCommittee Member, present
VM
Councillor Viv McCrossenCommittee Member, present
MP
Councillor Marje PalingCommittee Member, present
LP
Councillor Lynda PearsonCommittee Member, apologies
HW
Councillor Henry WheelerCommittee Member, present
KR
Councillor Kyle Robinson-PayneCommittee Member, present
MH
Mike HillOfficer, in attendance
FW
Francesca WhyleyOfficer, in attendance
MA
Mike AveryOfficer, in attendance
NO
Natalie OseiOfficer, in attendance

All 16 on the meeting page

On this subject at Gedling

Search all
  1. Corporate Risk StrategyThis decision
  2. Corporate Risk Management Review Period 1 April - July 2026Noted
  3. Corporate Risk Management Strategic FrameworkApproved
  4. Corporate Risk Management Review Quarter 4 2025/26Noted
  5. Corporate Risk Management Review - Quarter 3 2025/26Noted
  6. Corporate Risk Management Review - Quarter 3 2025/26Noted

More from Gedling Cabinet

All decisions
MeetingDecisionOutcome
16 Jul 2026 To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
16 Jul 2026 Forward Plan1) To note the report. Noted Open
16 Jul 2026 Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... Noted Open
16 Jul 2026 Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... Agreed Open
16 Jul 2026 Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies