That the Economic Development Board: · Approves the principles of the CIL Spending Protocol, as set out in this report. · Agrees that detailed measures relating to the spending of the CIL neighbourhood portion are worked up in discussion with the Gosport Voluntary Association (GVA) and are reported to the Board for approval at a later date.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1.1The Community Infrastructure Levy (CIL) was introduced by the Planning Act 2008 as a tool to simplify planning obligations and help local authorities deliver infrastructure to support development in their area. The Levy came into force on 6 April 2010 through the Community Infrastructure Levy Regulations 2010.
1.2The Council’s CIL Charging Schedule came into effect in February 2016, following a public examination in 2015 when the Inspector recommended that the Charging Schedule be adopted. The current Charging Schedule is included in Appendix 1.
1.3As of 1st October 2018, the Council had collected £117,182 in CIL funds, with further funds expected soon. A protocol therefore needs to be adopted for the spending of the levy, which is in line with government regulations and the Council’s priorities.
1.4According to the regulations, CIL should be spent to ‘support the development of the area’ through funding:
the provision, improvement, replacement, operation or maintenance of infrastructure; or anything else that is concerned with addressing the demands that development places on an area.1
1.5The government’s online guidance clarifies that the levy should not be used to remedy pre-existing infrastructure deficiencies, unless those deficiencies will be made more severe by new development.2
1.6According to the regulations and guidance, the spending of CIL monies should be split in the following way:
Up to 5% can be retained by the Council to cover administration costs.3 15-25% should be spent on infrastructure projects in consultation with the local community (the ‘neighbourhood portion’).4 The remainder is for the Council to spend on infrastructure projects.5
1.7The remainder, which this report will refer to as ‘strategic CIL’, must be spent on infrastructure projects which are within the scope of the Council’s Regulation ‘123 List’. The current 123 List was approved by the Council’s Economic Development Board on 17th September 2014 and formed part of the CIL Examination (Appendix 2). There are no regulations or guidance requiring a public consultation on the spending of strategic CIL, however amendments to a 123 List should be subject to a public consultation.6 Should the Council wish to review the contents of the 123 List, this can be carried out as part of the upcoming review of the Charging Schedule.
1.8The ‘neighbourhood portion’ equates to a minimum of 15% of all CIL receipts within an area where development occurs, up to a cap of £100 per household per year. This rises to 25% of CIL receipts with no household cap in areas with an adopted neighbourhood plan or a neighbourhood development order. The regulations state that the neighbourhood portion should be passed to a parish or town council every 6 months to spend in their area7. In unparished areas such as Gosport, the Council retains the monies for spending in consultation with the local community.
1.9DCLG’s online guidance states that the government ‘does not prescribe a specific process for agreeing how the neighbourhood portion should be spent’ however the use of neighbourhood funds
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.