That the Board approves the licence and dedication of the land referred to in the report for the proposed amended scheme (Eclipse Busway: Completion of Phase 1 – Retention of Rowner Road Bridge), and authorises the Borough Solicitor to enter into such legal documentation as is necessary to effect this decision on such terms and conditions as are appropriate.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
That the Board approves the licence and dedication of the land referred to in the report for the proposed amended scheme (Eclipse Busway: Completion of Phase 1 – Retention of Rowner Road Bridge), and authorises the Borough Solicitor to enter into such legal documentation as is necessary to effect this decision on such terms and conditions as are appropriate
Background
1.1In December 2008 the Council approved the transfer, sale and dedication of land to enable Phase 1 of the BRT Scheme to proceed. Subsequently the Council dedicated 1053 sqm of land as public highway, to enable HCC to construct facilities associated with the busway, via a Deed of Dedication dated 14 August 2009.
1.2HCC undertook a review of the route south with the bus operator in 2013. They decided that the operational benefits of extending the busway south of Rowner Road were questionable due to the need for buses to pick up passengers from the surrounding residential areas. They also concluded that the previously planned connection at Military Road did not form a logical part of existing or planned bus networks. As a result in October 2013 HCC applied for and granted planning permission to itself for a revised busway junction with Rowner Road that would require the demolition of Rowner Arch. The Council were consulted at the time and raised no objection to this planning application.
1.3However, in late 2013 HCC learnt that a bid for government funding for the revised scheme had been unsuccessful and informed the Council. The Council invited HCC to return to the issue of land transfer and dedication for the revised scheme when HCC had obtained appropriate funding.
1.4In October 2017 Hampshire County Council (HCC) secured £6.93m from the Department for Transport National Productivity Investment Fund for the construction of the southern extension to the Eclipse Busway in Gosport. As a result HCC approached the Council for the transfer and dedication of 504 sqm of land as previously envisaged.
1.5The scheme to demolish Rowner Arch is not without local concern and the Council subsequently asked HCC to provide, if possible, an alternative scheme that would not require the demolition of Rowner Arch. HCC now confirm that an alternative scheme has been drafted and will be presented formally to the Executive Member for Environment and Transport on 13 November 2018. If approved, HCC will then submit a new planning application, carry out detail design work, obtain the land required and seek additional funding before presenting the detailed scheme to the Executive Member for Environment and Transport for further approval.
2 Report
2.1The full HCC report on the scheme for the completion of Phase 1 is attached at Appendix A for background information. The proposed amended scheme will require additional land for highway dedication as shown in Appendices B and C. The proposed new busway will cross the shared-use footway/cycleway at-grade and then continue along a new ramped embankment to meet Rowner Road immediately to the east of the bridge. This proposal would remove the need for a three month road closure of Rowner Road, for the demolition of the bridge, and for the construction of the new junction, which were all required for the previously approved scheme, and the traffic implications will be significantly reduced.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.