Report of the Head of Planning and Regeneration

Refused Licensing 1 paper

Regulatory Board refused this item on Wednesday 5 December 2018. Below is the council's own wording, with the papers it was decided on.

Item21

Resolved

That a decision be taken on each application for planning consent as detailed below: 22. 18/00305/FULL - DEMOLITION OF EXISTING LIGHT INDUSTRIAL UNIT (CLASS B1) AND ERECTION OF 4 THREE BEDROOM HOUSES WITH ASSOCIATED PARKING, CYCLE AND BIN STORAGE (as amended by plans received 17.09.2018) Unit 3 - 4 Camden Street Gosport Hampshire PO12 3LU Councillor Hylands left the room and took no part in the discussion or voting thereon. Consideration was given to the report of the Head of Planning and Regeneration requesting that consideration be given to planning application 18/00305/FULL. The Board was updated that Members had undertaken a site visit. [name removed] was invited to address the Board. He advised that his deputation was a response to the site visit that had taken place and to reiterate concerns raised at the previous meeting and offer more detail. He also advised that he was offering an alternative concept to aid Members to see what was possible and on the site and what was seen by the local community as the answer to addressing a number of the issues presented by the current application. He advised that his proposal offered a contemporary design, without compromising or excluding the historic surrounds completely, that had an overall positive solution to the parking issues and that did not unduly ignore the planning guidance documents. He advised that minimum separation distances of 10.5 metres and a maximum distance of 15.5 metres were more favourable and with conjoined breaks within the buildings reduced the loss of outlook and privacy. He advised that the height of the proposal was far more of a justification for non-compliance than ‘it is better than the existing building’ and would give additional living space that would increase from 76m2 to 109m2. He advised that the rear amenity space for the properties would be improved as well as equal. In addition, the refuse collection point would be more aptly adjacent to the homes they served and as a result, more likely to be cared for by them. [name removed] advised the Board that most importantly, the issue of onsite parking would be addressed, without detriment to the SPD or the concerns of the existing neighbourhood and further leant itself to emergency vehicle access. He concluded that he hoped Members had had the opportunity to view the area as a whole, including the junction between Donnelly Street and Camden Street, where visually, similar homes, recent rebuilds, had been allowed by the authority, He advised that there was deliberately no detail offered as it was proposed that the details would be given, without prejudice to the applicant as an offer to gaining what would be seen by all as a positive, harmonious result. Hr advised that further to the points made previously by Councillor Hylands a new proposal could lend itself to opening up the site, with neither ‘side’ needing to build ... view the full minutes text for item 21.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Regulatory Board

Regulatory Board Agenda : 5th December 2018

GOSPORT BOROUGH COUNCIL – REGULATORY BOARD

5th December 2018

ITEMS WITH RECOMMENDATIONS

1. Copies of drawings and accompanying planning applications referred to in this schedule will be made available for inspection by Members from 5.00 pm immediately prior to the meeting. Unless otherwise advised, these plans will be displayed in the room in which the Regulatory Board is to be held.

2. The number of objections and representations indicated in the schedule are correct at the time the recommendations were formulated. Should any representations be made after this date, these will be notified to the Regulatory Board during the officer presentation.

3. Copies of all representations received from the public will be made available for inspection by Members in the same way as drawings will be made available, referred to in Note 1 above.

4. An index of planning applications within this schedule can be found overleaf, together with a summary of each recommendation.

DC-AGENDA-EN-26.11.18 Page 1 of 50 DC/UNI-form Template Regulatory Board : 5th December 2018

INDEX Item Page Appl. No. Address Recommendation No

01. 03-10/1 18/00305/FULL Unit 3 - 4 Camden Street Grant Permission Gosport Hampshire PO12 subject to Conditions 3LU

02. 11- 18/00085/FULL Gosport Leisure Park Forest Grant Permission 22/1 Way Gosport Hampshire subject to Conditions

03. 23- 18/00071/FULL 95 Bury Road Gosport Refuse 32/1 Hampshire PO12 3PR

04. 33- 18/00104/FULL Anglesey Lodge Anglesey Grant Permission 40/1 Road Gosport Hampshire subject to Conditions PO12 2DX

05. 41- 18/00105/LBA Anglesey Lodge Anglesey Grant Listed Building 44/1 Road Gosport Hampshire Consent PO12 2DX subject to Conditions

06. 45- 18/00412/VOC 63 Linden Grove Gosport Grant Permission 48/1 Hampshire PO12 2ED

07. 49- 18/00373/FULL 4 Vadne Gardens Gosport Grant Permission 51/1 Hampshire PO12 4TB subject to Conditions

DC-AGENDA-EN-26.11.18 Page 2 of 50 DC/UNI-form Template Regulatory Board : 5th December 2018

ITEM NUMBER: 01. APPLICATION NUMBER: 18/00305/FULL APPLICANT: [name removed] Roofing Ltd DATE REGISTERED: 27.07.2018

DEMOLITION OF EXISTING LIGHT INDUSTRIAL UNIT (CLASS B1) AND ERECTION OF 4 THREE BEDROOM HOUSES WITH ASSOCIATED PARKING, CYCLE AND BIN STORAGE (as amended by plans received 17.09.2018) Unit 3 - 4 Camden Street Gosport Hampshire PO12 3LU

The Site and the proposal

1. This application was considered by the Regulatory Board on 17th October 2018 when Members resolved to defer it for a site visit prior to the application being reconsidered at the next meeting of the Board.

2. The application site is located on the eastern side of Camden Street and is approximately 0.07 hectares in area. The site contains a vacant single storey, pitched roof light industrial unit (last occupied by TecSew Ltd) together with a yard area to the north. The 6m high building is set back from the pavement of Camden Street by approximately 1.7m. The building is approximately 17.8m wide along Camden Street reducing to be approximately 15.7m wide at the rear of the site. It is constructed of red brick and has a roller shutter door in the western elevation. The yard area to the north is approximately 6.4m wide along Camden Street and is approximately 30m deep.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report of the Head of Planning and RegenerationAgenda 356 KB DownloadRead as text

At this meeting

Whole meeting
18Minutes of the meeting held on 17 October 2018Approved
21Report of the Head of Planning and RegenerationThis decision

Who was there

14 of 14 attended
PB
Councillor Piers BatemanCommittee Member, present
ML
Councillor Mrs Linda BattyCommittee Member, present
KC
Councillor Kevin CaseyCommittee Member, present
RE
Councillor Richard EarleCommittee Member, present
KF
Councillor Keith FarrCommittee Member, present
CF
Councillor Clive Foster-ReedCommittee Member, present
SH
Councillor Stephen HammondCommittee Member, apologies, sent representative
DK
Councillor David Keith HerridgeCommittee Member, present
ML
Councillor Mrs Lynn HookVice-Chair, present
RH
Councillor Robert HylandsCommittee Member, present as substitute
TJ
Councillor Tony JessopChairman, present
MD
Councillor Miss Dawn KellyCommittee Member, present

All 14 on the meeting page

On this subject at Gosport

Search all
  1. Report of the Head of Planning and RegenerationThis decision
  2. Report of the Head of Planning and RegenerationApproved
  3. Report of the Head of Planning and RegenerationAgreed
  4. Report of the Head of Planning and RegenerationApproved
  5. Report of the Head of Planning and RegenerationRefused
  6. Report of the Head of Planning and RegenerationDecided

More from Gosport Regulatory Board

All decisions
MeetingDecisionOutcome
29 Jul 2026 Minutes of the meeting held on 3 June 2026That the minutes of the meeting held on Wednesday 3 June 2026 be signed as a true and correct record. Decided Open
3 Jun 2026 Election of the ChairmanThat Councillor Carter be elected as the Chairman of the Regulatory Board for the Municipal Year 2026/27. Decided Open
3 Jun 2026 Election of the Vice ChairmanThat Councillor Jessop be elected as Vice Chairman for the Municipal Year 2026/27. Decided Open
3 Jun 2026 Minutes of the meeting held on 18 March 2026That the minutes of the meeting held on 18 March 2026 be signed as a true and correct record. Decided Open
3 Jun 2026 Report of the Head of Development ManagementThat application 26/00007/FULL be approved , subject to the conditions in the report of the Head of Development Manag... Approved Open