That the Board gave formal support of the risk underwriting by the Council for costs in excess of the current approved funding, allocated to the Council by the Environment Agency (EA) and other contributors, for the scheme. That the Board referred the report to Policy and Organisation Board for the provision of financial allocation of the risk underwriting for the Alverstoke Coastal Defence Scheme at the recommended 30% contingency level (£212,269), with a minimum of 20% contingency level (£108,600), should costs be in excess of the current approved funding.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
Board/Committee: Community Board Date of meeting: 7th July 2021 Title: Risk Underwriting for the Construction of the Flood defence scheme at Alverstoke Author: Head of Streetscene Status: FOR DECISION AND RECOMMENDATION TO POLICY AND ORGANSIATION BOARD
Purpose This report sets out the background information for the risk underwriting required by the Council as part of responsible project management of the contract for the Construction works. Recommendation That the Board gives formal support of the risk underwriting by the Council for costs in excess of the current approved funding, allocated to the Council by the Environment Agency (EA) and other contributors, for the scheme. The Board refers the report to Policy and Organisation Board for the provision of financial allocation of the risk underwriting for the Alverstoke Coastal Defence Scheme at the recommended 30% contingency level (£212,269), with a minimum of 20% contingency level (£108,600), should costs be in excess of the current approved funding. 1.0 Background
1.1This report provides information on the Alverstoke Coastal Defence Scheme. Work on the project is being undertaken by Coastal Partners (formerly known as ‘Eastern Solent Coastal Partnership’) on behalf of Streetscene.
This proposed scheme will provide tidal flood defence to a 1-in-100-year event (1% Annual Exceedance Probability) in 2060 to both areas. The Alverstoke scheme will reduce flood risk to 132 residential and 10 commercial properties.
Planning permission for the scheme was granted at the Regulatory Board meeting on the 2nd December 2020, with approval given for the award of the construction contract by the Community Board on 10th February 2021.
The scheme received formal approval for the full allocation of funding possible from the Environment Agency (EA), through Flood Defence Grant in Aid on 26th May 2021.
1.2This report recommendation is for the Council to underwrite the remaining risk funding for the scheme. This underwriting cannot be insured against, so funds need to be allocated from the Council. The risk underwriting is required so the scheme has the provision for the risk costs, if required, prior to works commencing on site.
2.0Report
2.1Scheme drivers
The need for the scheme is derived from key documents adopted by the Council, including:
Shoreline Management Plan (SMP). This is a high-level policy document setting out a framework for future management of the coastline. It was adopted by the Council in 2010 and recommends a ‘Hold the line’ policy to maintain or upgrade to the level of protection required by the coastal defences in the Alverstoke area.
The River Hamble to Portchester Strategy (RHPS). This strategy looked at how the SMP policy can be implemented at a more local level and identifies areas where work may be required over the next 100 years. The strategy recommended three priority schemes in Gosport. These are situated at Forton, Seafield and Alverstoke. The strategy identified these locations as “vulnerable areas”, in which there is significant risk of tidal flooding.
In order to deliver the SMP and RHPS policy of ‘Hold the Line’ for Alverstoke, considerable effort was invested into selecting the preferred scheme design option. A feasibility study was carried out in 2016, which looked at all technically feasible options that could deliver the Alverstoke scheme. The feasibility study combined detailed site surveys with constraints and opportunities mapping to identify and evaluate potential alignments for the schemes.
2.2Scheme Design
The proposed works at Alverstoke includes a reinforced concrete flood wall located at the western end of the lake, with a floodgate across Little Anglesey Road.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Commemorative Bench Seat PolicyThat the Board approved the Commemorative Bench Seat Policy and provided delegated authority to the Head of Streetsce...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.