Risk Underwriting for the Construction of the Flood Defence Scheme at Alverstoke

Approved Committee 1 paper

Community Board approved this item on Wednesday 7 July 2021. Below is the council's own wording, with the papers it was decided on.

Item82

Resolved

That the Board gave formal support of the risk underwriting by the Council for costs in excess of the current approved funding, allocated to the Council by the Environment Agency (EA) and other contributors, for the scheme. That the Board referred the report to Policy and Organisation Board for the provision of financial allocation of the risk underwriting for the Alverstoke Coastal Defence Scheme at the recommended 30% contingency level (£212,269), with a minimum of 20% contingency level (£108,600), should costs be in excess of the current approved funding.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Community Board

Board/Committee: Community Board Date of meeting: 7th July 2021 Title: Risk Underwriting for the Construction of the Flood defence scheme at Alverstoke Author: Head of Streetscene Status: FOR DECISION AND RECOMMENDATION TO POLICY AND ORGANSIATION BOARD

Purpose This report sets out the background information for the risk underwriting required by the Council as part of responsible project management of the contract for the Construction works. Recommendation That the Board gives formal support of the risk underwriting by the Council for costs in excess of the current approved funding, allocated to the Council by the Environment Agency (EA) and other contributors, for the scheme. The Board refers the report to Policy and Organisation Board for the provision of financial allocation of the risk underwriting for the Alverstoke Coastal Defence Scheme at the recommended 30% contingency level (£212,269), with a minimum of 20% contingency level (£108,600), should costs be in excess of the current approved funding. 1.0 Background

1.1This report provides information on the Alverstoke Coastal Defence Scheme. Work on the project is being undertaken by Coastal Partners (formerly known as ‘Eastern Solent Coastal Partnership’) on behalf of Streetscene.

This proposed scheme will provide tidal flood defence to a 1-in-100-year event (1% Annual Exceedance Probability) in 2060 to both areas. The Alverstoke scheme will reduce flood risk to 132 residential and 10 commercial properties.

Planning permission for the scheme was granted at the Regulatory Board meeting on the 2nd December 2020, with approval given for the award of the construction contract by the Community Board on 10th February 2021.

The scheme received formal approval for the full allocation of funding possible from the Environment Agency (EA), through Flood Defence Grant in Aid on 26th May 2021.

1.2This report recommendation is for the Council to underwrite the remaining risk funding for the scheme. This underwriting cannot be insured against, so funds need to be allocated from the Council. The risk underwriting is required so the scheme has the provision for the risk costs, if required, prior to works commencing on site.

2.0Report

2.1Scheme drivers

The need for the scheme is derived from key documents adopted by the Council, including:

 Shoreline Management Plan (SMP). This is a high-level policy document setting out a framework for future management of the coastline. It was adopted by the Council in 2010 and recommends a ‘Hold the line’ policy to maintain or upgrade to the level of protection required by the coastal defences in the Alverstoke area.

 The River Hamble to Portchester Strategy (RHPS). This strategy looked at how the SMP policy can be implemented at a more local level and identifies areas where work may be required over the next 100 years. The strategy recommended three priority schemes in Gosport. These are situated at Forton, Seafield and Alverstoke. The strategy identified these locations as “vulnerable areas”, in which there is significant risk of tidal flooding.

In order to deliver the SMP and RHPS policy of ‘Hold the Line’ for Alverstoke, considerable effort was invested into selecting the preferred scheme design option. A feasibility study was carried out in 2016, which looked at all technically feasible options that could deliver the Alverstoke scheme. The feasibility study combined detailed site surveys with constraints and opportunities mapping to identify and evaluate potential alignments for the schemes.

2.2Scheme Design

The proposed works at Alverstoke includes a reinforced concrete flood wall located at the western end of the lake, with a floodgate across Little Anglesey Road.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Risk Underwriting for the Construction of the Flood Defence Scheme at AlverstokeReport 148 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

14 of 14 attended
PB
Councillor Piers BatemanCommittee Member, present
JB
Councillor John Beavis MBECommittee Member, present
SB
Councillor Sean BlackmanCommittee Member, present
GB
Councillor Graham Burgessex-Officio, present
CC
Councillor Christopher CarterCommittee Member, present
PC
Councillor Peter ChegwynCommittee Member, present as substitute
RE
Councillor Richard EarleCommittee Member, present
MD
Councillor Mrs Diane FurlongCommittee Member, present
SH
Councillor Stephen HammondCommittee Member, present
JH
Councillor Jamie HutchisonCommittee Member, present
MD
Councillor Miss Dawn KellyCommittee Member, present
LM
Councillor Lesley MeenaghanCommittee Member, present

All 14 on the meeting page

On this subject at Gosport

Search all
  1. Risk Underwriting for the Construction of the Flood Defence Scheme at AlverstokeThis decision
  2. Cross Reference from the Community Board -Risk Underwriting for the Construction of the Flood defence scheme at AlverstokeApproved

More from Gosport Community Board

All decisions
MeetingDecisionOutcome
8 Mar 2022 Minutes of the previous meeting of the Community Board held on 5 January 2022That the minutes of the meeting held on 5 January 2022 be signed as a true and correct record. Decided Open
5 Jan 2022 Minutes of the previous meeting of the Community Board held 3 November 2021that the minutes of the meeting held on 3 November 2021 be signed as a true and correct record. Decided Open
5 Jan 2022 Joint Municipal Waste Management StrategyThat the Board approved the Joint Municipal Waste Management Strategy (JMWMS) Approved Open
3 Nov 2021 Minutes of the previous meeting of the Community Board held on 8 September 2021that the minutes of the meeting held on 8 September 2021 be signed as a true and correct record. Decided Open
3 Nov 2021 Commemorative Bench Seat PolicyThat the Board approved the Commemorative Bench Seat Policy and provided delegated authority to the Head of Streetsce... Approved Open