That the Board approved an additional £155,000 funding be allocated for an enhanced refurbishment and upgrade of the Stokes bay Splash Park. That the Board agreed to forward the report to the Policy and Organisation Board to approve the additional funding.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1. That an additional £155,000 funding be allocated for an enhanced refurbishment and upgrade of the Stokes Bay Splash Park. 2. That this report is forwarded to the Policy & Organisation Board to approve the additional funding as laid out in this report.
Background
1.1The Council has allocated £275,000 to the Stokes Bay Splash Park to be delivered within the Capital Programme for 2021/2022. The total fund allocated comprised of £250,000 for the Splash Park and another £25,000 for the Stokes Bay Wet and Dry scheme.
1.2Following a review analysis of the works programme and the commission of an outline design specification, a number of additional requirements to the original scope of works have been identified.
1.3The additional requirements include demolition of the existing pump room and providing it with additional ancillary facilities including a new water treatment room with extra capacity, which meets current industry guidelines and will reduce the risk of systematic failure of the treatment plant, plus a chemical store delivering a modern purpose- built facility.
1.4These additional items are required to ensure compliance with both statutory and regulatory requirements and will also result in life cycle cost savings and lower maintenance costs. 1.5 It should be noted that the budget of £275,000 for the scheme was within the estimated range for delivering the original scope of works.
2 Report
2.1The Capital Programme manager commissioned an outline design scope of works review of the Stokes bay Splash Park project.
2.2The design contractors reviewed the proposed work scope and inspected the existing pump room equipment to ascertain reuse potential and compliance with current operating standards and to ensure all design risks were mitigated while ensuring value for money.
2.3Following a detailed analysis of the design recommendations it was agreed that there was a need to replace the water treatment plant and that in order to do so, a new pump house would be necessary which would also provide space for a chemical treatment store in line with industry standards.
2.4The proposed design will promote the use of modular methods of construction which is a sustainable form of construction ensuring that the delivery of this scheme aligns with the Council’s broader climate change objectives. Further benefits include added cost savings on life cycle maintenance.
2.5The works programme is planned for 24 weeks commencing after the September shut down of the Splash Park facility with a handover date planned for March 2022 to enable re-opening of the facility in time for the new season.
2.6The costs of the required additional works required is £155,000
2.7The Community Board project review has identified the funded projects at Elmore lake and Parham Road as suitable projects which could be removed from the capital Programme which would provide £70,000 and £25,000 towards the required £155,000 with the remainder coming from the S.106 Open Space and the Strategic CIL funding allocations.
2.8Agreement of these proposed financial transfers (virements) requires approval by the Policy and Organisation Board.
The virement request is as follows:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Commemorative Bench Seat PolicyThat the Board approved the Commemorative Bench Seat Policy and provided delegated authority to the Head of Streetsce...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.