Resolved
That the Board noted the process to procure a construction contractor using the National Framework Partnership.
Housing Board noted this item on Wednesday 27 September 2023. Below is the council's own wording, with the papers it was decided on.
Resolved
That the Board noted the process to procure a construction contractor using the National Framework Partnership.
Board/Committee: HOUSING BOARD Date of meeting: 27 SEPTEMBER 2023 Title: HOUSING DEVELOPMENT UPDATE Author: HEAD OF HOUSING Status: FOR NOTING
Purpose This report sets out the tender process to procure a construction contractor to deliver the new social housing on sites at Stoners Close, Wheelers Close and Glebe Drive. Recommendation That the Board notes the process to procure a construction contractor using the National Framework Partnership. 1.0 Background
1.1The Council entered into a contract with ECD Architects Ltd on 7 December 2021 to deliver a multi-disciplinary lead consultancy service to design and oversee the delivery the of 15 new council housing dwellings.
1.2The dwellings will be a mix of two, three and four bed family homes, as well as one bedroomed accessible bungalows, located across three brownfield infill sites at Stoners Close, Wheeler Close and Glebe Drive.
1.3The dwellings have been designed to low energy Passivhaus principles taking advantage of orientation, technology and fabric design to provide comfortable living environments for future residents, and with reduced running costs.
1.4These principles include a simplified building form reducing heat loss through its fabric, orientation to ensure dual aspect facades and a higher proportion of glazing to the southern elevations to maximise solar gain in the winter months, increased insulation and the incorporation of low carbon technologies such as air source heat pumps, and solar panels if required.
Each dwelling will benefit from a good degree of natural light and outlook, with south-facing rear gardens
1.5Planning applications for all three sites were submitted on 12 December 2022 and permission was granted at Regulatory Board on 26 April 2023 for:
The construction of seven dwellings with associated parking and landscaping at Stoners Close, The construction of five dwellings, in two separate blocks, with associated parking and landscaping at Wheeler Close, and The construction of three dwellings with associated parking and landscaping at Glebe Drive.
2.0Report
2.1A construction contractor will be procured to deliver all three sites. Procurement for a project of this size can be a lengthy and resource- intensive process; therefore, a construction contractor will be procured under the National Framework Partnership (NFP).
2.2By using an existing framework regulated by the Public Contracts Regulations 2015, the council can award an individual contract without going through a full ‘above threshold’ procurement process.
2.3NFP is backed by Hyde, one of the largest housing associations in the UK, and has live contracts with a total value of £2.25bn. NFP has more than fifty frameworks, with a network of two hundred trusted partners, and works with a number of public sector organisations, including local authorities.
2.4NFP provides a framework for finding construction contractors in the south of England for projects up to £10m, offering:
Local expertise and understanding - Construction contractors in the south have an understanding of the local market dynamics, regulations, and specific challenges in the region. They are well versed in the local construction practices, suppliers, and sub-contractors. Partnering with local contractors ensures the project is handled by professionals with a strong grasp of the local context, allowing for efficient project management and seamless collaboration.
Project efficiency and Flexibility - Construction contractors in the south specialise in projects up to £10m, enabling them to focus their resources, expertise, and attention on delivering projects of this scale. They have the capacity to efficiently manage and execute smaller-scale projects, ensuring attention to detail and adherence to timelines and budgetary constraints. Their flexibility allows for customised solutions while maintaining high-quality standards.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Housing Development UpdateReport | 236 KB | DownloadRead as text |
Follow Housing Board at Gosport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Jun 2026 | Election of ChairmanThat Councillor Meenaghan was elected as Chairman for the municipal year 2026-2027 | Decided | Open |
| 10 Jun 2026 | Election of Vice ChairmanThat Councillor Figgins was elected as Vice Chairman for the municipal year 2026-2027 | Decided | Open |
| 10 Jun 2026 | MINUTES OF THE PREVIOUS MEETING OF THE HOUSING BOARD HELD on 10 March 2026That the minutes of the meeting held on 10 March 2026 were signed as a true and correct record. | Decided | Open |
| 10 Mar 2026 | MINUTES OF THE PREVIOUS MEETING OF THE HOUSING BOARD HELD on 20 January 2026That the minutes of the meeting held on 20 January were signed as a true and correct record. | Decided | Open |
| 20 Jan 2026 | MINUTES OF THE PREVIOUS MEETING OF THE HOUSING BOARD HELD 19 November 2025That the minutes of the meeting held on 19 November 2025 were signed as a true and correct record. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.