Resolved
That the minutes of the meeting held on 26 January 2025 were signed as a true and correct record.
Standards & Audit Sub Board decided this item on Thursday 27 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the minutes of the meeting held on 26 January 2025 were signed as a true and correct record.
Public Document Pack Standards & Audit Sub Board 16 January 2025
A MEETING OF THE STANDARDS & AUDIT SUB BOARD WAS HELD ON 16 JANUARY 2025
Councillors Cox, Hutchison, Hylands, Philpott and Raffaelli
34. APOLOGIES FOR NON ATTENDANCE
There were none
35. DECLARATIONS OF INTEREST
There were none
36. MINUTES OF THE MEETING OF THE SUB BOARD HELD ON 14 NOVEMBER 2024
RESOLVED: That the minutes of the meeting held on the 14 November 2024 were signed as a true and correct record.
37. DEPUTATIONS- STANDING ORDER 3.4
There were none
38. PUBLIC QUESTIONS - STANDING ORDER 3.5
There were none
39. DATA SECURITY BREACH REPORT
Consideration was given to a report by the Data Protection Officer (DPO)informing the Sub Board of any Data Security Breaches and actions agreed/taken since the last meeting.
The DPO introduced his report by pointing out that the number of breaches were almost the same as last time and all fairly minor with none to be reported to the ICO.
Members were understanding of how easy it is to make such mistakes when busy and were pleased to hear that CMT had discussed the issue and were to produce tips to help minimise errors.
Members were advised that all breaches of data, either of an individual or organisation, would be contained within the report.
RESOLVED: That the Sub Board noted a report including the breaches that have arisen and the action determined by the Information Governance Group (IGG)
40. INTERNAL AUDIT PROGRESS REPORT 1ST APRIL TO 13TH DECEMBER 2024
1 Standards & Audit Sub Board 16 January 2025
Consideration was given to a report by the Chief Internal Auditor (CIA) updating the Sub Board on the progress of the Audit Plan 2024/25.
The CIA introduced his report by advising members that although a couple of audits had been delayed due to sickness in the audit team, there were currently no concerns that the audit plan will not be completed to enable an audit opinion to be given in July 2025.
Members were advised that there are concerns in relation to the results of the IT audits contained in the report. This includes 1 full audit and 4 follow up audits where limited assurances opinions remain. No substantive testing could take place due to no information being provided by the service. In answer to a Member’s question regarding when those marked as High become Critical, the CIA advised focusing on completing the follow ups rather than the current colour.
The Head of IT advised members that the work had been progressed, but that the outcomes had not been updated on the audit tracker system.
Members were advised that the current situation, the resilience of the existing team and plans to strengthen in the future, have been discussed with the CEX and recruitment has begun to address the concerns voiced by the Sub Board at the last meeting.
The Chairman requested that the Head of IT brings a report to the next Sub Board meeting with an update and evidence that the follow ups requested have been completed. This will not be verified by internal audit, however, further follow ups on these areas will be scheduled for quarter 1 of the 2025/26 audit plan. If the issues are not resolved, the CIA noted that the risks could be raised to critical.
Members were advised that Hayley McKay had been appointed as Acting Head of Housing and recruitment of an Interim Asset Manager had been agreed. Further consideration of all roles within the service will be carried out to inform job descriptions.
RESOLVED: That the Standards and Audit Sub Board noted the progress of the Audit Plan 2024/25 from 1st April to 13th December 2024 as set out in appendix A.
41. STRATEGIC RISK REGISTER UPDATE
Consideration was given to a report by the Chief Internal Auditor (CIA) presenting the strategic risk register for noting as at December 2024 in line with the Risk Management Policy.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Minutes of the Meeting of the Sub Board held on 16 January 2025Reports_pack | 205 KB | DownloadRead as text |
Follow Standards & Audit Sub Board at Gosport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Jul 2026 | Election Of ChairmanThat Councillor Dan Hayes is duly elected as Chairman for the municipal year 2026/27 | Decided | Open |
| 2 Jul 2026 | Election of Vice ChairmanThat Councillor Colin Towell is duly elected as Vice Chairman for the municipal year 2026/27 | Decided | Open |
| 2 Jul 2026 | Minutes of the Meeting of the Sub Board held on 26 March 2026That the minutes of the meeting held on 26 March 2026 were signed as a true and correct record. A Member queried the ... | Agreed | Open |
| 2 Jul 2026 | Local Government Ombudsman Review 2025/2026That the Sub Board noted the report | Noted | Open |
| 2 Jul 2026 | Gifts & Hospitality Return for Council StaffThat the Sub Board noted the report | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.