That the Sub Board noted i) the update from the Head of IT including progress on specific projects, updates on staffing and skills whilst highlighting on-going challenges. ii) Noted the recommendation that a further update is provided at the January 2026 meeting once the new IT manager has been in post for a number of months.
Word for word from the decision Gosport published for this meeting.Source: democracy.gosport.gov.uk
1.1There have been several challenges within the IT provision at Gosport Borough Council over a prolonged period and this has been highlighted through a number of limited assurance audits and then subsequently a lack of information provided in follow-up reviews.
1.2The previous Head of IT retired earlier in 2025 and subsequently support has been provided by the Gavin Muncaster, Head of IT, on a part time basis through a service level agreement with Southampton City Council. As well as providing a level of management support for the team there has been focus on IT Strategic level priorities to deliver improvements in the delivery of IT service and to set a direction for the service moving forwards. Additionally, a full time IT Operations manager has been recruited, joining the organisation on 01/09/2025.
2.0Report
2.1The challenges relating to IT Service delivery within Gosport have been well documented through Internal audit reports and the recent corporate peer challenge and are well understood by this Board. Rather than repeat specific detail of the issues this report focusses actions being taken or are planned whilst highlighting where risks and challenges remain.
2.2It is noted that as a small organisation there are some specific challenges that the IT service will face. In particular the core platforms to support services such as NEC (Revenues and Benefits), IDOX (Planning and Regulatory services), require the same level or management and upgrades as much larger organisations with much greater levels of resource. This has definitely been a contributing factor into the progress of system upgrades and improvements.
2.3IT Service updates and improvements are detailed below, split into three key areas, Resourcing (staffing and skills), Technology (software systems and hardware) and Service Improvements (process and practices).
2.4Resourcing – staffing and skills. Much of the IT service have been long-standing employees of Gosport Borough Council and collectively they have a significant knowledge of the IT systems and hardware in use within the authority. However, with a relatively small team it is well understood there are areas where knowledge and experience sit with individuals as well as a small number of people that are heavily relied onto to keep systems running.
2.4.1 Gavin Muncaster had been providing support for a short period prior to the retirement of the current Head of IT and has continued to do so. Working with senior colleagues in the authority small immediate changes have made to the structure of the IT service. Rather than a direct replacement of the Head of IT Role a new IT Manager has been recruited who will be focussed on IT Operational management. The new IT Manager starts on 1st September 2025. Additionally extra capacity has been recruited with a new IT Technician added to the team with a focus on networking and hardware, starting in August 2025.
2.4.2 It is expected that the current arrangements on strategic level support will remain in place, allowing the IT manager to focus on managing and improving IT service delivery and operational IT services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.