Standards & Audit Sub Board, Thursday 26 March 2026 at 6.00pm

IT Update Report

Noted Finance 1 paper

AI summaryGosport Standards and Audit Sub Board notes progress on IT improvement programme but keeps limited assurance rating until changes embed during 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedProgress on projects, staffing, and Internal Audit follow-ups
MoneyNot stated
What happens nextEquipment refresh rolloutPlan by mid-April 2026, rollout Q1 26/27
Who it affectsGosport Borough Council IT usersCouncil staff and IT service delivery

What was decided

The Sub Board noted the update from the Head of IT covering project progress, staffing, skills and ongoing challenges.

The Sub Board noted continued progress through the IT Improvement Programme and the positive direction shown in the February 2026 Internal Audit follow-up reports.

Why

The IT service has had prolonged challenges highlighted by several limited assurance audits and weak follow-up information, prompting a coordinated IT Improvement Programme after permanent IT management was embedded in September 2025. Report 1.1, 1.2

Internal Audit follow-up work in February 2026 confirmed improvements, though overall assurance remains limited because the improvement programme is still at an early stage of implementation. Report 2.1, 3.1

What happens next

Complete the replacement of the VPN solution by the end of April 2026 to improve remote access security. Report P6

Finalise the initial project plan for the staff computer refresh by mid-April 2026, with rollout expected to start in Q1 of the 26/27 financial year. Report P6

Include IT audits in the 26/27 audit plan to review the latest position and agree any updated actions and timescales. Report 3.1

Implications

  • Risk: Limited assurance remains until changes embed; risks are now better understood and a risk-based approach is in place for hardware replacement. Report 3.1, P9
  • Other: Migration of several critical systems to cloud-hosted platforms has improved resilience and reduced dependency on legacy on-premise infrastructure, though formal disaster recovery documentation is still being updated with service areas. Report P6
  • Staffing: Day to day management by the permanent IT Manager has brought clearer prioritisation and more structured helpdesk staffing with in-person coverage. Report P5

Who and where

  • Gosport Borough Council staff using IT equipment and services Report P5, P6
  • GBC service areas whose business continuity plans are being aligned with updated IT disaster recovery plans Report P6

Timeline

  • September 2025: Previous IT update report and embedding of permanent IT management Report 1.2, 2.1
  • February 2026: Internal Audit follow-up reviews completed across Helpdesk, Disaster Recovery, Hardware and Asset Management, Licence Management and Microsoft Teams governance Report 2.1, 3.1
  • end of April 2026: Replacement of the VPN solution due to be completed Report P6
  • mid-April 2026: Initial project plan for the rollout of new end user equipment to be completed Report P6
  • Q1 26/27: Rollout of new end user equipment expected to start Report P6
  • 26/27: IT audits to be included in the audit plan to review latest position and agree updated actions Report 3.1

Plain English for the jargon

  • VPN: Virtual Private Network, used to provide secure remote access for users
  • M365 E5: The higher tier of Microsoft 365 licensing, giving greater tools for managing devices, software and accounts
  • KPI: Key Performance Indicator, a measure used to track service performance
  • LGR: Local Government Reorganisation, referenced in relation to avoiding short-term investment in new systems
  • HOI: Head of IT, the officer providing the update
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item47

Resolved

That the Sub Board: Noted the update from the HOI including progress on specific projects, updates on staffing and skills whilst highlighting on-going challenges. Noted the continued progress made through the IT Improvement Programme and the positive direction of travel reflected in the February 2026 Internal Audit follow-up reports.
Word for word from the decision Gosport published for this meeting. Source: democracy.gosport.gov.uk

Follow this further

Built from Gosport's papers

What the report saysPro

Report to Standards & Audit Sub Board

Background

1.1There have been several challenges within the IT provision at Gosport Borough Council over a prolonged period and this has been highlighted through a number of limited assurance audits and then subsequently a lack of information provided in follow-up reviews.

1.2Since September 2025, permanent IT management arrangements have been embedded and a coordinated IT Improvement Programme has been established to address historic audit findings in a structured and sustainable manner

2.0Report

2.1The challenges relating to IT Service delivery within Gosport have previously been reported on and this report is a follow-up to the September 2025 update. Recent peer challenge and internal audit progress reports have confirmed improvements and progress has been made but further on- going work is required to maintain this momentum. 2.2 Internal Audit follow-up work completed in February 2026 confirms that while overall assurance remains limited, this reflects the early stage of implementation of a new improvement programme rather than a lack of progress. 2.3 The report is structured around the individual internal audit reports. IT Service updates and improvements relating to each audit, in line with the February 2026 follow-up meetings, are detailed below. 2.4 IT Helpdesk and Service Management

Improvements are now in progress across incident categorisation, backlog management, escalation of high priority incidents and the introduction of clearer performance data and KPIs. These changes are recent and not yet fully embedded but represent a material improvement in control and oversight compared to September 2025. 2.4.1 With direct day to day management and prioritisation from the permanent IT Manager have ensure there is a clear focus and prioritisation of issues within the team. 2.4.2 There is a more structured approach to the staffing of the helpdesk with in- person coverage and regular communication as appropriate whether this is corporate wide for general issues or specific management updates on individual incidents. 2.4.3 The current IT Service Management System (the main tool used by the IT Helpdesk) remains basic in it’s functionality and therefore some actions such as KPI monitoring d backlog management remain a challenge but manual activity and development of the system, liaising with the supplier, is being worked on. 2.4.4 Disaster Recovery and Resilience

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IT Update ReportReport 110 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 7 attended
KC
Councillor Kirsty CoxCommittee Member, present
MZ
Councillor Mrs Zoe Huggins BEMCommittee Member, present
JH
Councillor Jamie HutchisonDeputy Chair, present
RH
Councillor Robert HylandsChairman, present
LM
Councillor Lesley MeenaghanCommittee Member, present
SP
Councillor Stephen PhilpottCommittee Member, apologies, sent representative
PR
Councillor Philip Raffaelli CB FRCPCommittee Member, present as substitute

More from Gosport Standards & Audit Sub Board

All decisions
MeetingDecisionOutcome
2 Jul 2026 Election Of ChairmanThat Councillor Dan Hayes is duly elected as Chairman for the municipal year 2026/27 Decided Open
2 Jul 2026 Election of Vice ChairmanThat Councillor Colin Towell is duly elected as Vice Chairman for the municipal year 2026/27 Decided Open
2 Jul 2026 Minutes of the Meeting of the Sub Board held on 26 March 2026That the minutes of the meeting held on 26 March 2026 were signed as a true and correct record. A Member queried the ... Agreed Open
2 Jul 2026 Local Government Ombudsman Review 2025/2026That the Sub Board noted the report Noted Open
2 Jul 2026 Gifts & Hospitality Return for Council StaffThat the Sub Board noted the report Noted Open