The Cabinet agreed that Dartford Borough Council is advised that the Borough Council will provide up to a maximum of £10,000 from the General Fund reserve to prepare the case in the forthcoming planning appeal involving the Tariff. The contribution is conditional on the provision of reciprocal support in the event of this council receiving equivalent appeals or judicial review, and on the condition that this council is not party to the proceedings.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Review of the Kent Thameside Delivery Board (6th draft 13.6.08)
1. Introduction 1.1 With the recent departure of the Chief Executive of the Kent Thameside Delivery Board (KTDB) team and the decision by Lord Bruce-Lockhart to relinquish the Chairmanship of the Board, it has been agreed that the time is right for a short review of the partnership arrangements in Kent Thameside.
1.2The rationale for a review at this stage relates to factors at both regional and national levels, including the following:
When the Delivery Board was established in 2003, the focus was upon planning for delivery in Kent Thameside. With the opening of Ebbsfleet International Station, the granting of planning permission for Eastern Quarry and the successful implementation of the Fastrack network, delivery is undeniably happening in Kent Thameside. The review will ascertain whether the current structure is fit for purpose;
The Sub National Review of Economic Development and the proposed strengthening of the Local Authority role in Economic Development including a statutory economic assessment duty;
The new round of Local Area Agreements which will be shaping action on the ground across the Gateway;
Joint working across Thames Gateway Kent leading to a potential Multi Area Agreement covering the North Kent districts and Medway.
The changing structure of partnership working across Kent in general.
1.3There is a momentum in the delivery of significant proposals in the Kent Thameside area. Ebbsfleet Valley, as one of the four spatial transformers across the whole Gateway is critical to the success of the Thames Gateway initiative. DCLG has allocated £41.7m from the Thames Gateway programme to support growth in the period of 2008 – 11, plus a further indicative allocation of £10m for community infrastructure in Kent Thameside. It is therefore essential that the review is carried out in a timely and efficient manner and does not impede progress on delivery.
2 Overview 2.1 There are a number of arrangements in place to co-ordinate and drive forward the delivery of activities in the Thames Gateway 2.1.1 Thames Gateway Strategic Partnership provides the high level co-ordination across the Gateway and is chaired by the Minister for Housing & Planning.
2.1.2 The Thames Gateway Kent Partnership is one of the three Area Partnerships in the Gateway. The TGKP brings together representatives of the three Kent and Medway Delivery vehicles (Kent Thameside, Medway Renaissance and Swale Forward), together with the local authorities and private sector representatives.
2.1.3 The Kent Thameside Delivery Board which was established to facilitate delivery in Kent Thameside.
2.2The KTDB was established in 2003 and was a requirement for the acceptance of funding from the former Office of the Deputy Prime Minister.
1 2.3 Various sub-groups and activities are directly connected to the KTDB.
2.3.1 Fastrack Delivery Executive
2.3.2 Kent Thameside Economic Board.
2.3.3 The implementation group for Homes and Road.
2.3.4 Green grid arrangements.
3 Present position 3.1 Since discussions took place in 2001/02 leading up to the establishment of the KTDB in 2003 a lot of progress has been achieved. Delivery is an ongoing feature and must be the primary focus of any future arrangements.
3.2The reality is that such delivery takes place between the private sector and the relevant public sector agencies which is primarily the three Councils, SEEDA and English Partnerships. Funding from DCLG is invariably allocated to one of these public sector agencies with the responsibility to deliver specific proposals within agreed timescales.
3.3The concept of Ebbsfleet in 2001/02, when the arrangements for the KTDB were being developed, is now progressively being delivered. Besides the international station having opened the Springhead Quarter is being built and the first homes have been reserved. The final quarter master plans should be agreed in the near future.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.