The Cabinet agreed: (1) final approval of the new Local Development Scheme to be delegated to the Lead Member for Business and the LDF and the Director (Business). (2) the amended LDS be submitted to GOSE for approval. (3) Delegate to the Lead Member for Business and the LDF and the Director (Business ) the ability to make minor changes to the LDS following comments from GOSE prior to the LDS coming into force.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Gravesham Borough Council Local Development Scheme 2008-11
Gravesham Borough Council
Report to: Cabinet
Date: 17th November 2008
Reporting officer: Director Business
Subject: Gravesham Local Development Scheme (LDS)
Purpose and summary of report: To seek Member approval for the revised Gravesham Local Development Scheme 2008- 2011 Recommendations: 1. Final approval of the new Local Development Scheme to be delegated to the Lead Member for the LDF and the Director (Business). 2. The amended LDS be submitted to GOSE for approval. 3. Delegate to the Lead Member for the LDF and the Director (Business) the ability to make minor changes to the LDS following comments form GOSE prior to the LDS coming into force.
1. Introduction
1.1Following the meeting of the Local Development Framework Working Group on the 3rd June, all members were given a copy of the draft LDF timetable for delivering the Core Strategy. The timetable circulated then is very similar to that now proposed in the revised LDS. The draft Gravesham Local Development Scheme 2008-2011 is attached as appendix C of this report.
1.2We have been supported by Mott MacDonald, on behalf of PAS, in setting out a management programme for delivering the Core Strategy and Generic Development Control Policies DPD. Part of this work focused on translating the stages into a Gantt chart in MS Project.
1.3The value of clear and robust project management has been highlighted by a number of organisations and in a range of fora. We are purchasing the MS Project software so that amendments can be made as appropriate to the project plan and we are intending to use it to help work programming.
1.4To continue this project management approach, we have produced a Project Initiation Document (PID) for this Core Strategy and Generic Development Control Policies DPD. This has taken a little time but has formed the basis of the LDS. A couple of more detailed project plans have also been produced for Infrastructure Planning and production of the SHLAA. In combination these plans have allowed us to consider the project’s risks and the contingencies that need to be put in place.
2. What is the Local Development Scheme?
2.1The Planning and Compulsory Purchase Act 2004 requires local planning authorities to prepare and keep under review a LDS for their area. The primary objective of the LDS is to set out the programme of work for the preparation of the Council’s Local Development Framework (LDF) for 3 years ahead (i.e. for the period 2008-2011). It is therefore both a key management tool and an important vehicle for explaining the council’s plan-making intentions to key stakeholders and the general public.
3. Recent changes to the LDF system
3.1The changes to the LDF system have been in introduced by way of the Town and Country Planning (Local Development)(England) (Amendment) Regulations 2008. These changes are designed to streamline the system and the Regulations came into force on 27th June 2008. In addition, the Government has produced new Planning Policy Statement 12 (Local Spatial Planning).
3.2The changes which have been made which directly influence the timetable and procedures to be set out in the LDS include:
3.2.1 Merging the Issues and Options and Preferred Options stage with a single requirement to engage the public and stakeholders. This is being known as the regulation 25 consultation stage.
3.2.2 Bringing forward the time for formal representations on the particular plan before it is submitted to the Secretary of State (previously these both took place at the same time and thus did not allow for any possible changes to be made to the plan). This regulation 27 stage is being described as the publication stage consultation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.