The Cabinet agreed that: (1) the award of £8 million grant funding from the Department for Communities and Local Government ( DCLG ) be welcomed; (2) the proposals set out in paragraph 3.3 be approved (3) Members and officers continue to make representations concerning the rules on the annuality of funding to the newly formed Homes & Communities Agency.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
1.1The purpose of the Transport Quarter project is to create a major gateway for Gravesend with a transport interchange that integrates the railway station, bus services, Fastrack, taxi access, parking, set-down and pick up and pedestrian linkages. (see draft plan attached).
1.2At its meeting on 12 March 2007, Cabinet was informed of progress and advised of the results of the public consultation on the masterplan. In addition it was reported that an interim grant had been secured from the DCLG for the year ending March, 2008 to develop the masterplan. Cabinet confirmed the appointment of external consultants to advise on the preparation of the scheme.
2. Progress
2.1A steering group comprised of the key stakeholders – Gravesham Borough Council, Kent County Council (Kent Highways), Network Rail and the train operator Southeastern - was established in August after a high level meeting chaired by a senior representative of DCLG and attended by the Leader of the Executive, KCC Lead Member (environment, highways and waste) and the Route Director (Kent) from Network Rail. 2.2 The steering group agreed a collaborative approach, the component parts to deliver the masterplan and identified sources of funding. It was originally envisaged that one developer would be selected to deliver the whole scheme but following advice from Network Rail it has proved necessary to consider an alternative approach whereby specialist developers may be used to procure component parts, particularly those elements that involve working on rail land.
2.3An estimated investment of circa £75m (at 2005 costs) is required to deliver the entire scheme with funding coming from the DCLG, enabling development and a number of rail industry sources.
2.4The original bid for funding from the DCLG was for £10M for the period 2008/11 but after a lengthy appraisal the DCLG confirmed a grant of £8M of which £2M has to be spent in the current financial year. The funding agreement was received on 18 November, 2009.
2.5Due to the transfer of functions of the DCLG to the Homes & Communities Agency (HCA) it was essential to sign the funding agreement and return it by 20 November. This was to enable the DCLG to transfer the commitment to the HCA and prevent re-appraisal and any subsequent delay that would occur from this.
2.6The Chief Executive, in consultation with the Leader of the Executive, accordingly signed and returned the documents on 19 November.
2.7The DCLG investment will be a catalysing contribution to the development. Some of which will be needed to produce a detailed masterplan and the rest to help deliver component parts. Key elements the funding will used to pump prime are the planning, management and execution of the project, delivery of the new railway bridge, road re-alignments, public realm improvements and enhancements to the pedestrian bridge. There is also provision for the appointment on a fixed term contract of a project co-ordinator to oversee the scheme and funding for the necessary survey and other work required to support an outline planning application for the project.
2.8In order to develop the masterplan in sufficient detail to the stage that an outline planning application can be lodged, it is necessary to:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.