The Cabinet: approved the updated Risk Management Strategy; approved the updated Corporate Risk Register 2009-10; agreed to the continued publication of the Risk Management Strategy and the Corporate Risk Register 2009-10 on the council’s website.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Gravesham Borough Council Corporate Risk Register 2009-10 Gravesham’s Corporate Risk Register outlines the key strategic risks facing the council and the controls currently in place to respond to these risks – the register also highlights any further action required by the council to properly manage these risks.
The Corporate Risk Register is the result of an annual strategic risk management exercise conducted to identify, analyse and prioritise those risks that may affect the ability of the council to achieve its corporate objectives. The key risks facing the council were identified through a combination of workshops and interviews with Cabinet Members, Directors, Assistant Directors, Service Managers and other senior managers. The process also identified the council’s risk ‘tolerance’ level and risks were plotted above and below this level based on the likelihood and impact of each risk. Where risks were identified as being above the acceptable tolerance line, an assessment was made to establish whether existing actions would properly manage the risk or whether further management action was required to bring the risk below the line. Identified risks were considered by Cabinet Members to ensure all that all appropriate risks were properly considered.
Given that the council works in an ever-changing environment it will be necessary to conduct similar strategic risk management exercises on a periodic basis. Progress against management actions recorded in the register will be reported to Cabinet on a quarterly basis and the register will be reviewed on a six-monthly basis.
As a contribution to good corporate governance, risk management also forms a part of the annual business planning process – each departmental business plan has a specific service risk register to identify the key risks facing that service. This reinforces the corporate risk management approach through each Service Manager giving proper formal consideration to strategic and operational risks.
Overall Risk Scores 2009-10:
Likelihood: L A 5 1,2,3 A – Very high, B – High, C – Significant, D – Low, i B 14 4 E – Very low F- Almost impossible
k 6,7,8, e C 9,10, 11,12 Impacts: 1 – Catastrophic 2 – Critical, 3 – Marginal, 4 – Negligible li 13
D h o E o F d 4 3 2 1
Impact Gravesham Borough Council Corporate Risk Register 2009-10
The Risk Challenging financial position Risk no. 1 Assessment January 2009 Target for year-end review (March 2010) Likelihood A Impact 2 Likelihood A Impact 2 Cabinet Portfolio Leader and Regeneration Portfolio (Cllr Mike Snelling) and risk The grant settlement resulting from the Comprehensive Spending Review (CSR07) was background significantly lower than in previous years resulting in challenges in relation to the council’s finances. Whilst the council is expecting to make some significant financial savings over the medium term to meet these challenges, further work is still required to mitigate this risk. In addition, the council's major income streams such as planning application fees and land charges have reduced as a consequence of the current economic climate. • Financial savings not achieved • Cuts in services and drop in quality of Consequences • Budgets exceeded delivery possible and impact on strategic • Problems stored up for the future • Reserves depleted objective (i.e. if the • Some services not managing their • Value for money damaged risk is not spending parameters. • Audit and inspection concern managed) • Minimum reserve position of • Damage to Council’s reputation £1million is not maintained
Early warning Tough decisions around savings are not made in a timely manner (council not robust signs about monitoring and controlling budgets). Key corporate Medium-term financial strategy 2009-10 – 2011-12 documents and Treasury Management Strategy processes Budget monitoring processes – monthly basis Risk Owner (s) Director (Transformation and Finance) Last Review Date January 2009 Review Quarterly Frequency
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.