The Cabinet agreed that the Assistant Director (Business and Law), in consultation with the Leader, be authorised to take all necessary steps, on such terms and conditions as he thinks fit to amend the Development Agreement to enable: (1) the introduction of a new milestone and the date of 1 May 2011 to submit the planning application for the alternative to the tower, with a second milestone that reasonable endeavours be used to submit the application for Council approval by the 1 March 2011; (2) the postponement of the Termination Date to 2 May 2014.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
It is recommended that the Assistant Director (Business and Law), in consultation with the Leader, be authorised to take all necessary steps, on such terms and conditions as he thinks fit to amend the Development Agreement to enable:-
(1) the introduction of new milestones as referred to in paragraph 3.4 of this report;
(2) the postponement of the Termination Date to 2nd May 2014.
1. Introduction
1.1Members will recall that in January 2009 a joint press conference was held by Gravesham Borough Council and Edinburgh House Estates Limited (EHE) at which it was announced that the planning application that had been submitted for the Heritage Quarter scheme would proceed without the tower.
1.2There is consensus between the Council and EHE that without the tower the overall scheme is not viable and therefore will not be built.
1.3It follows that in order for the scheme to proceed EHE would have to work up some alternative solution in order to make the scheme viable once again. For technical legal reasons the tower has not yet been removed from the current application that is before the Council. EHE have indicated however that they are prepared to remove the tower from the scheme in return for additional time to work up an alternative solution. As a result of these developments, EHE have re-appraised their ‘target programme’ for the completion of the scheme and the time needed to work up a new scheme and submit appropriate planning applications will result in an overall delay to the project of 27 months. 2. The Development Agreement
2.1The Development Agreement provides that if it has not become unconditional 5 years from the date on which it was exchanged, i.e. by 2 February 2012, either the Council or the developer may determine the Agreement. This is known as the Termination Date.
2.2The outstanding conditions that have not been met and still need to be satisfied in order for the agreement to become unconditional • viability • funding • the Church (on the western phase only)
Once the conditions have been satisfied/waived by the Developer the agreement becomes unconditional.
2.3The next stage is for the building contract to be let when a third party contractor will become involved and have a vested and enforceable interest in the development being built out. At that stage it is worth noting that the Council also receives the Capital Receipt for its land and the Developer can draw down the leases for the site.
2.4The Development Agreement also specifies ‘milestone dates’ in order to ensure that EHE maintains progress in accordance with the ‘target programme’ for delivery of the project. Again, if those milestone dates are missed, then the Agreement can be terminated by either party. The original milestone dates for the Development Agreement have all been achieved. However, the need to work up some viable alternative solution for the scheme has led to EHE being concerned that the current delays have considerably increased their risk of not achieving unconditionality before February 2012. Hence the reason that EHE have requested an extension of the termination date to avoid the risk of the Agreement being terminated without them having sufficient time to reach the unconditional date.
2.5The plan is for EHE to progress the current planning application without the tower. This will take some two months from Cabinet approval for the amended/additional paperwork to be drawn up by EHE and there will then be a need for a 13 week consultation period for the revised scheme with the matter coming before the Regulatory Board probably in October 2009.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.