Resolved
Resolved that the report be noted.
Gravesham Joint Transportation Board noted this item on Wednesday 9 September 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the report be noted.
Gravesham Borough Council
Report to: Joint Transportation Board
Date: 9th September 2009
Reporting officer: Head of Countywide Improvements
Subject: Highway and Transportation Schemes Progress Report – 2009/10 Purpose and summary of report: This report advises members of the progress of highway and transportation schemes in Gravesham.
Recommendations: For information and comment.
1. Background.
1.1For each highway improvement scheme in Gravesham, Appendix 1 summarises progress to date and anticipated progress prior to the next meeting of this Board.
1.2In June 2009 it became apparent that there was insufficient provision in the 2009-10 budget to meet those costs from the 2008-09 programme that had not been paid by 31 March. As a result, part of the budget allocated to 2009-10 schemes has had to be used to meet this shortfall. The consequence is that the delivery of some schemes that were due in 2009-10 has now been postponed until 2010-11. In Gravesham these are discussed as follows:
2. Discussion
2.1Hall Road / Colyer Road / Coldharbour Road Northfleet: Cycle Path. This scheme has been deferred as part of the required land has been reserved as an evacuation area for Northfleet Technology College during the school rebuilding work. The Council’s commitment to fund this scheme’s construction in financial year 2010-11 has therefore been withdrawn. Nonetheless, because this scheme remains a valid and worthwhile infrastructure improvement, design and enabling works will continue in the expectation that the scheme will be strong contender for construction being funded in 2011-12. This scheme will not be reported to this Board again until September 2010 2.2 High Street, Northfleet Conversion of southern footway to shared use cycle path. Works were due to start on site in December 2009, but due to the budget shortfall, this has now been postponed until Easter 2010.
2.3Wrotham Road, Gravesend: Phase 2 of Gravesend-to-Istead Rise Cycle Route (A2 to Chalky Bank). Works were scheduled to start in November 2009 but due to the budget shortfall, they have now been delayed until May 2010.
BACKGROUND DOCUMENTS: The background papers pertaining to this report are held on the Kent Highway Services files.
All requests to inspect the above documents MUST be directed in the first instance to the Committee Section of the Democratic Services Department
Contact Officers: See last column in Appendix 1 (tel 08458 247 800).
2 Highway and Transportation Scheme Progress Report – 2009/10: APPENDIX 1
Kent
Forecast Out- allocation KHS Location Description of Current Progress Anticipated Actions Highway
2009 – 10 2009 - 10 Original Ref Works for next 3 months Services
turn (Prior to next JTB) Contact 08458 247800 drainage Works is scheduled to 07-ITS- London Road improvements to Works have been Andy take place between £0K £8K GR-X1 Northfleet footway outside ordered Padgham 16-27 November Post Office Hall Road / Outline design has Colyer Road Cycle route & been progressed and 08-ITS- / See main text of this Peter pedestrian discussions regarding £20k £10k GR-02 Coldharbour report Slaughter improvements. purchase of 3rd party Road land continuing. Northfleet Every effort will be Wellington made to compel EdF Street / Reverse direction Disputes with EdF to complete their 08-ITS- Andrew Peacock of one-way traffic resolved but their works works this summer, £8K £11K GR-03 Burton Street, in both roads are still unprogrammed allowing the traffic Gravesend flows to be reversed in October Conversion of 09-ITS- High Street, southern footway As per March 2009 See main text of this Geoff £50K £0K GR-01 Northfleet to shared use report to this Board report Dance cycle path 09-ITS- Wrotham Phase 2 of See main text of this Andy £40K £0K GR-02 Road, Gravesend-to- report Padgham Gravesend Istead Rise Cycle Design underway Route (A2 to Chalky Bank) Kent
Forecast Out- allocation KHS Location Description of Current Progress Anticipated Actions Highway
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Improvement Schemes 2009/2010: report herewith.Report | 61 KB | DownloadRead as text |
Follow Gravesham Joint Transportation Board at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2021 | Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. | Noted | Open |
| 10 Mar 2021 | Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. | Noted | Open |
| 10 Mar 2021 | Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... | Agreed | Open |
| 14 Mar 2018 | Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham D... | Noted | Open |
| 14 Mar 2018 | Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.