The Cabinet agreed that: (1) the attached draft Transport Quarter Consultation Report be approved for publication and the changes considered appropriate arising from the consultation listed in paragraph 2.12 be agreed for inclusion into the Masterplan ; (2) the Assistant Director (Special Projects) be authorised to submit applications for conservation area consent, outline and detailed planning permission subject to any changes agreed under 1 or arising from pre-application discussions; (3) the Assistant Director (Business & Law) be authorised to make the necessary compulsory purchase pursuant to the powers contained in Section 226 of the Town and Country Planning Act 1990 and all enabling powers to compulsorily acquire land shown edged black on Appendix 1 – Plan A; all cost to be underwritten by the grant funding from the Homes and Communities Agency.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Appendix 1 Materials Used in the Consultation Process 39
1.1Exhibition display panels 39 1.2 Photographs of the scale model 46 1.3 The Questionnaire 47 1.4 Promotional Flyer 49 1.5 Promotional Poster 50 1.6 Newspaper four-page wrap around 51 1.7 Street survey forms 55 1.8 Press coverage 62 1.9 Neighbourhood Forum newsletter 64 1.10 Web site material 65
Appendix 2 Consolidated comments from the Street Surveys 66
Contacts 71
2 1 Executive Summary
Consultation
The Transport Quarter was subject to a previous public consultation in 2005/6 which resulted in the omission of the Victoria Centre and the ‘Gala Bingo’ block from the original master plan. Revisions to the plan were included in the 2009 version of the plan which was the subject of this consultation.
The public exhibition on the Transport Quarter Master Plan consultation was held for a period of six weeks from 12th June - 24th July 2009 at both TOWNCENTRIC and the Civic Centre. It was widely publicized and attracted a wide range of comments, questions and suggestions from the public. Two hundred and twenty nine people completed the questionnaire devised for the consultation. Twelve letters, four e-mails and three phone calls were also received.
Public Perceptions of Proposals The detailed analysis of the rating of responses to the main statements provided in the questionnaire showed that the master plan was well received overall. These responses revealed that:
• the proposals for the transport quarter are supported • it is considered a good idea to integrate all transport modes • the new civic square and other public realm improvements are welcomed • removing all through traffic from Clive Road and barrack Row is supported • providing additional car parking is welcomed • improving pedestrian access and comfort is welcomed • the provision of additional housing is accepted
Changes to the Master Plan Resulting from the Consultation In light of the public view above no major changes to the master plan are considered necessary. The wealth of suggestions, questions and comments provided have been reviewed in detail at a workshop involving all of the project’s stakeholders. As a result of this process the following refinements to the plans are recommended, subject to detailed design: -
• Shared spaces should be designed to have kerbs. • cycle parking provision should be included at Key nodes • Day-lighting issues should be considered in the detailed design stages for all parts of the transport quarter development. • Principles of ‘Secure by Design’ should be considered for embodiment within the designs. • Taxis should be allowed to turn left into Darnley Road, provided that they exit Barrack Row from the south side lane. • Taxis should be allowed to use the south-bound bus lane in Darnley Road • The option of providing a taxi rank on the north side of Barrack Row is to be discussed with taxi operators. Such use would require the use of a call forward system.
Further refinements to the detailed aspects of the plan will be made utilizing the feedback and opinion gathered from the Street Survey exercise which pinpoints features of the area which should be retained as well as identifying areas where changes should be made. The totality of the input received should provide for a more comprehensive outline master plan and better detailing of individual elements of the scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.