Resolved
Resolved that the proposal illustrated at Appendix A of the report be endorsed. Note: [name removed], Meopham Parish Council, spoke under the terms of the agreement.
Gravesham Joint Transportation Board agreed this item on Wednesday 24 March 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that the proposal illustrated at Appendix A of the report be endorsed. Note: [name removed], Meopham Parish Council, spoke under the terms of the agreement.
Gravesham Borough Council
Report to: Joint Transportation Board
Date: 23 March 2010
Reporting officer: Head of Countywide Improvements, Kent Highway Services Subject: Sole Street – Pedestrian Facilities Across the Railway Bridge Purpose and summary of report: This report advises Members of measures proposed to remedy the lack of a pedestrian facility across the railway bridge in Sole Street
Recommendation: Members are recommended to endorse the proposal illustrated as Appendix A to this report
1. Background and Discussion.
1.1For many years, the lack of footway over the railway bridge in Sole Street has been a cause of concern for some train passengers, pedestrians, residents and local Members. Several years ago a workable compromise was reached, whereby white hatched road-markings were painted on the station-side of the carriageway across the bridge for pedestrians to walk on in order to stay out of the path of traffic. To provide further guidance to drivers, double white centre-lines were painted on, and on both approaches to, the bridge.
1.2A routine road safety assessment by Kent Police carried out in the autumn of 2009 revealed some concerns with regards to the legitimacy and enforceability of these road markings. Kent Highway Services (KHS) considered that the changes sought by the Police (which were necessary to comply with legislation) could not be implemented without removing the hatched area.
1.3Because these changes were considered necessary to comply with legislation, no consultation was undertaken and unfortunately the work was carried out without notifying local Members or the Parish Council. The changes were immediately unpopular and an agreement was quickly reached whereby a further compromise road marking scheme would be reinstated across the bridge. These remedial works were completed in November but current design standards means that the resultant hatched area for pedestrians to walk along is noticeably narrower than it had been. 1.4 In view of this, officers have developed a more formal, permanent, solution to the difficulty faced by pedestrians and train passengers. The proposed scheme comprises a proper footway (illustrated as Appendix A to this report) that was submitted for funding as part of the Local Transport Plan (LTP) 2006-11. Under KHS’s Scheme Prioritisation System that is used to compare one scheme’s benefits against another’s, the scheme scored 50.6, some 5 points below the LTP funding threshold for the 2010-11. As such, it was ineligible for funding. However, recognising the problems that KHS’s actions had caused and that the outcome was not satisfactory, the £22,000 funding needed to implement this scheme has been secured from KHS’s repair and renewal budget.
1.5Whilst funding is secure, there does remain the technical challenge of installing a new footway without compromising the bridge’s strength, waterproofing or integrity. KHS engineers are working with Network Rail to refine the scheme’s design in order to minimise the proposed footway’s effect on the bridge’s structure and are confident that a workable solution can be reached in time to allow the footway to be installed this summer.
1.6Members are asked to endorse the scheme illustrated as Appendix A to this report.
BACKGROUND DOCUMENTS: The background papers pertaining to this report are held on the Kent Highway Services’ files.
All requests to inspect the above documents MUST be directed in the first instance to the Committee Section of the Democratic Services Department
Contact Officers: Kerry Prescott (KHS Transportation Engineer)
Andrew Burton (KHS Highway Schemes Manager)
Tel 08458 247 800).
2 Appendix A: Sole Street – Proposed Footway
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Sole Street: Pedestrian Facilities across the Railway BridgeReport | 159 KB | DownloadRead as text |
Follow Gravesham Joint Transportation Board at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Mar 2021 | Bath Street - Fastrack Infrastructure SchemeResolved that the report be noted. | Noted | Open |
| 10 Mar 2021 | Highway Forward Works Programme - 2019/20 onwardsResolved the report be noted. | Noted | Open |
| 10 Mar 2021 | Issues raised by Councillors with the approval of the ChairIt was agreed that the results of the ATC be shared with Cllr Rana. It was noted that the officer had previously disc... | Agreed | Open |
| 14 Mar 2018 | Gravesham Highway Works Programme 2017/18Resolved that the Board noted the information contained within the report and agreed the following: · The Gravesham D... | Noted | Open |
| 14 Mar 2018 | Petitions from residents at the JTB (KCC Petition Scheme)Resolved that the Board look at the original JTB Legal Agreement between KCC and GBC with the view to amending it to ... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.