Resolved
The Cabinet agreed that the Assistant Director (Business and Law) be given authority to make changes to the Council’s scheme of delegation as set out in the report.
Cabinet agreed this item on Monday 13 September 2010. Below is the council's own wording, with the papers it was decided on.
Resolved
The Cabinet agreed that the Assistant Director (Business and Law) be given authority to make changes to the Council’s scheme of delegation as set out in the report.
Gravesham Borough Council
Report to: Cabinet
Date: 13 September 2010
Reporting officer: Director (Business)
Subject: Amendment of the Scheme of Delegations in relation to the 2008 Planning Act Purpose and summary of report: The 2008 Planning Act created a new body and process to deal with major infrastructure projects, and it is necessary to amend the scheme of delegations in relation to this. Members need to be aware that the process is significantly different to that which they are used to. Recommendations: That the Assistant Director (Business and Law) be given authority to makes changes to the Council’s scheme of delegation as set out in this report.
1. Introduction
1.1The 2008 Planning Act set up the Infrastructure Planning Commission (IPC) to handle nationally significant infrastructure projects (NSIP’s), with a new application process to be followed. The Borough Council’s Scheme of Delegations needs to be amended to allow delegated powers to the Director (Business) to deal with some matters where appropriate.
1.2The process involves “front loading” the consultation which means that the Council will need to make its concerns and emerging views known early in the process and not wait until a formal application is made to the IPC. It is therefore significantly different from the processes the Council is used to dealing with.
1.3The coalition Government is proposing to alter the decision making mechanism from the Commissioners to Ministers, and merge the organisation into the Planning Inspectorate, as the Major Infrastructure Planning Unit. This is unlikely to happen before early 2012 as it requires primary legislation, so the IPC will continue to operate as now. The change in final decision maker will not affect the administrative process which is expected to remain the same
1.4Currently there are at least one potential application’s in which the Borough Council is involved though not located within Gravesham, the Tilbury C Power Station proposal. This is currently being consulted upon, and will be used as an example below. 2. Infrastructure Planning Commission process
2.1For the purpose of this report reference will be made to the IPC as an abbreviation for the process. The diagram at the end of the report summarises the process and what is set out below is an overall guide.
2.2A number of key stages for a Local Authority can be identified (see diagram):
• Statement of Community Consultation (SOCC - just produced for Tilbury)
• Environmental Impact Scoping Report (assuming project requires one and most will by definition – being carried for Tilbury)
• Local Impact Report
• Pre submission consultation
• Discussion on Development Consent Order and any s.106 agreement
• Submission of the proposal to the IPC (for Tilbury currently expected in late November/early December 2010)
• Validation by IPC (includes taking a view whether the consultation process has been adequate)
• Examination, with an emphasis on written submissions
• If permission is granted there is then a consent process for minor details if required
2.3Long serving Members will recognise some obvious parallels with the procedures followed for the CTRL (now HS1) under the 1996 Channel Tunnel Rail Link Act, as well as some differences. The process assumes that the application is for a fully worked up scheme with most of the details fixed, not an outline application with the details to be sorted out at a later date. This places a major cost burden on the applicant up front. In particular they have to prepare the draft Development Consent Order, in effect the planning permission notice but it is a statutory instrument when modified and approved.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Scheme of Delegations in relation to the 2008 Planning ActReport | 370 KB | DownloadRead as text |
Follow Cabinet at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... | Refused | Open |
| 28 Sep 2026 | Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. | Agreed | Open |
| 28 Sep 2026 | Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... | Noted | Open |
| 28 Sep 2026 | Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... | Decided | Open |
| 28 Sep 2026 | LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.