Item118

Resolved

The Cabinet authorised contributions to the Thames Gateway Kent Partnership (subject to KCC funding being confirmed) and the Kent Thameside Economic Board for 2011/12 to be agreed by the Chief Executive, in consultation with the Leader of the Executive, subject to costs being contained within the available budgets as set out at paragraph 3.13.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Background

1.1For some years now the Council has operated at a number of levels within Thames Gateway. It has acted as a delivery body itself, worked in partnership across Kent Thameside within the Kent Thameside Regeneration Partnership and across north Kent as a member of the Thames Gateway Kent Partnership.

1.2These two partnership bodies, whilst receiving contributions from this Council, have also benefited from significant financial support from the Communities and Local Government (CLG) / Homes and Communities Agency (HCA) and the South East England Development Agency (SEEDA).

1.3With the imminent winding up of the regional development agencies, of which SEEDA is one, and removal of CLG / HCA funding, these structures have been reviewed and the purpose of this report is to update Members.

2. Kent Thameside

2.1With the loss of government and other funding, the decision has been taken to wind up the operation of the Kent Thameside Regeneration Partnership. This situation is replicated across north Kent with Medway Renaissance and Swale Forward being initially subsumed into their respective council organisations and, with loss of funding heavily downsized or removed. 2.2 Remaining staff, with the assistance of partners, are moving towards the close down date of 31 March 2011 with every effort being made to safeguard any remaining resources for the benefit of the area.

2.3The Fastrack project will continue under the management of Kent County Council.

2.4It should also be noted that, alongside the Regeneration Partnership sits the private sector-led Kent Thameside Economic Board. This will continue in a slightly changed form and could possibly take a lead on some of the issues / programmes previously overseen by the Regeneration Partnership, e.g. Employ Kent Thameside, Homes and Roads, etc. Thus it will be necessary for the Council to continue to make provision for potential contributions to this body, which is already contained within the Civic Budget (£2,500 in 2011/12).

3. North Kent

3.1In the light of the withdrawal of HCA funding for local delivery vehicles across the Thames Gateway (and indeed nationally), it was agreed to work up a proposal for funding a refocused TGKP Executive Team for the financial year 2011/12 onwards.

3.2A bid for HCA funding, matching contributions from the five North Kent local authorities, was prepared and submitted to the HCA Executive Director for the area in which North Kent now falls, but that request was unsuccessful.

3.3Given both the public sector funding restraint and the state of the property market in North Kent, an officers working group has considered the option of winding up the Partnership and / or providing a skeleton servicing and administration function via one of the local authorities. However, the group consider that there are a number of very good reasons for continuing to undertake the operation of a team at the north Kent level, not least of which being the reputational risk of not having one – and in a related sense the advantage handed to the other two Thames Gateway sub-regions that are both proposing to retain a secretariat team and will provide a critical link into the Minister-led Thames Gateway Strategic Group.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Regeneration PartnershipsReport 65 KB DownloadRead as text

At this meeting

Whole meeting

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies