Internal Drainage Districts – East & West of Gravesend

Agreed Executive 1 paper

Cabinet agreed this item on Monday 30 June 2014. Below is the council's own wording, with the papers it was decided on.

Item14

Resolved

(i) Note that the Environment Agency’s Internal Drainage Boards for the Internal Drainage Districts to the East and West of Gravesend will be disbanded on 31 March 2015; (ii) Agrees to the principle that no Internal Drainage Board be established covering the area to the West of Gravesend, for the reasons set out in Section Three of this report; (iii) Agrees to the principle of the establishment of a new Internal Drainage Board for the Internal Drainage District to the East of Gravesend, for the reasons set out in Sector Four of this report. Furthermore, delegated authority be given to the Director (Housing & Regeneration), Assistant Director (Corporate Performance) and Assistant Director (Governance & Law), in consultation with the Leader of the Council to take all necessary steps, including entering into any relevant legal commitments, in the establishment of a new Internal Drainage Board covering the area to the East of Gravesend.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Background

1.1Internal Drainage Districts (IDD’s) are statutorily defined as “such areas within the areas of regional flood defence committees as will derive benefit or avoid danger as a result of drainage operation” (Section 1, Land Drainage Act 1991).

Cabinet – Internal Drainage Districts – East & West of Gravesend 1.2 IDDs are managed by Internal Drainage Boards (IDB’s), which are local public authorities with permissive powers to manage water levels within their respective drainage districts. IDB’s undertake works to reduce flood risk to people and property, and manage water levels to meet local needs. In lowland England, 120 IDBs currently manage the IDDs.

1.3Today, their work is controlled by the Land Drainage Act 1991 and the Flood and Water Management Act (FWMA) 2010. They are part of a combination of organisations, collectively known as Risk Management Authorities including local authorities and water companies, that each have a part to play in managing water levels and flood risk.

1.4IDD’s, and specifically the IDB’s which oversee such areas are concerned with land drainage and not tidal flood defence – with the latter dealt with by the Environment Agency through its Thames Estuary 2100 Plan. There is however overlap between responsibilities for flood defences, main rivers, IDB drainage ditches and ordinary watercourses, and responsibility will depend upon the exact nature of each flooding issue.

1.5There are currently two IDDs which cover land within the boundary administered by Gravesham Borough Council – one historically referred to as being “West of Gravesend”, covering an area of the Swanscombe Peninsular, part of Dartford Borough Council’s administrative area and an area of land within the London Borough of Bexley’s control, and one historically referred to as “East of Gravesend”, which covers land falling both within Gravesham’s boundary, and that of Medway Unitary Authority. Appendix Two to this report, shows a map of the two current IDDs.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Internal Drainage Districts: East & West of GravesendReport 697 KB DownloadRead as text

At this meeting

Whole meeting

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies