The Director (Environment & Operations) in consultation with the Assistant Director (Governance & Law) and the Director (Corporate Services) be given delegated authority to a) conduct the procurement process and award the contracts for planned major refurbishment and equipment servicing work using the South East Consortium (SEC) procurement framework by way of direct award or mini tender as outlined in the report. b) grant extensions for planned major refurbishment and equipment servicing work contracts on a yearly basis up to a maximum of three extended years as outlined and subject to satisfactory contractor performance. 2. The Leader and Lead member be consulted in respect of use of the allocated budget for 2016/17 and setting a budget for maintaining the decent homes standard in future years, taking into account the results of the recent stock condition survey.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
1.1As a landlord, Gravesham Borough Council has a statutory duty to ensure its housing stock is regularly maintained, that equipment is serviced and that any responsive repairs are completed within a timely manner and therefore it is essential that required external service providers are in place to assist with the delivery of required works.
1.2The DSO Building Management operation controls this function with the in-house DSO team and term contractors completing responsive repair works and the Contracts team managing the external contractors that carry out planned and major works together with the servicing of equipment, such as lifts and door-entry systems. 1.3 In April 2010, the Council entered into a gas partnership contract with Swale Heating to carry out the servicing of existing equipment and the installation of new equipment for a five year period with five one-year extensions to be granted annually.
1.4With the exception of the gas partnership contract which was awarded in 2010, using the OJEU procurement process, contracts for the other areas above were awarded in 2012. The process took 16 months to compete and required outside consultants and a project group to deliver a compliant procurement process.
1.5Contracts awarded to term contractors that support the DSO were done so separately from the four-year contracts awarded in respect of the planned major refurbishment works and equipment servicing contracts. Whilst all of the contracts commenced around the same time, the term contracts were agreed for a longer period which will expire on 31 March 2017. A separate report will be submitted to Cabinet at a future date to outline the procurement process for the term contracts.
2. Current Position
2.1In April 2012, the Council entered into a number of contracts to cover the following work areas:
2.1.1 Major and planned works – this includes works such as new roofs, replacement doors and windows, external repairs, cyclical decorations, electrical updates and asbestos removal. The estimated full-term value of these contracts is £11,300,000
2.1.2 Equipment servicing and repairs – this includes the regular maintenance and planned works for warden call services, asbestos surveys, fire and emergency lighting, door-entry systems and lifts. The estimated full-term value of these contracts is £364,000
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.