Resolved that the recommendations made by the sub-group of the Overview Scrutiny Committee be implemented, which are as follows: · Continue to identify areas of repairs and maintenance work that can be carried out in house and increase staffing levels where appropriate to deliver this objective · Provide a further update of repairs and maintenance improvements to the Overview Scrutiny Committee within 12 months, with an initial update report in six months · Ensure regular liaison between the internal Repairs team and the Housing team to ensure that a good client/contractor relationship is maintained and that information is shared and acted upon · Provide further training to the Housing Officers to enable them to provide more comprehensive advice to tenants regarding tenant responsibilities and the council’s responsibilities in terms of repairs and maintenance issues · Review ‘repeat offenders’ who have the same or similar repair job carried out a number of times and recover repair costs where appropriate · Ensure regular monitoring of all planned work programmes is undertaken in order to identify on-going savings
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Following on from the previous Housing Repairs Topic review in April 2016, the Overview Scrutiny Committee wanted to expand their research into this area and chose to undertake a further review into Housing repairs, to focus on the cyclical repairs and maintenance plan and capital improvement works. There is a need to ensure that the council is using the finite resources it has available in the best way possible to ensure that the tenants are receiving a good service within these budget constraints.
This topic review has identified further potential improvements that can be made to the overall repairs and maintenance service for both the tenant and the council, building on the improvements that have already been made by officers.
We would like to take this opportunity to thank the officers involved in the review for their time and assistance in providing comprehensive information which has enabled Members to discuss, debate and identify potential improvements for consideration.
Cllr Sue Howes
Chair of the Sub-group
Page 3 1. Introduction and Summary of Recommendations 1.1 In June 2016, the Overview Scrutiny Committee selected the subject of Housing Repairs for a further topic review. The terms of reference for the review focused on:
• A review of the total amount spent on repairs and maintenance and the capital improvement works to the council’s housing stock • A review of the cyclical programmes that the council has in place with regards to roofs, kitchens, bathrooms, boilers, etc, to establish whether the council is replacing these items more frequently than is necessary, or more frequently relative to others.
1.2Throughout the review, Members of the sub-group have been provided with a significant amount of information to review and analyse, which prompted in-depth discussion on specific technical areas and also led to identifying some opportunity for improvements in areas not initially considered within the scope of the review.
Summary of Recommendations 1.3 In summary, the Scrutiny Topic review of Housing Repairs has identified six recommendations for Cabinet consideration:
RECOMMENDATION Report page
1. Continue to identify areas of repairs and maintenance work that -6- can be carried out in house and increase staffing levels where appropriate to deliver this objective. Timeframe for actions: • Areas of work to be carried out in-house identified - 6 months • Staffing levels increased and teams developed - 18 months
2. Provide a further update of repairs and maintenance -7- improvements to the Overview Scrutiny Committee within 12 months in response to the topic review recommendations. Timeframe for actions: • Progress update report - 6 months
Page 4 RECOMMENDATION Report page
3. Ensure regular liaison between the internal Repairs team and the -7- Housing team to ensure that a good client/contractor relationship is maintained and that information is shared and acted upon. Timeframe for actions: • Regular liaison meetings involving Directors and operational managers from repairs and housing - Already in place
4. Provide further training to Housing Officers to enable them to -7- provide more comprehensive advice to tenants regarding tenant responsibilities and the council’s responsibilities in terms of repairs and maintenance issues. Timeframe for actions: • 6 months
5. Review ‘repeat offenders’ who have the same or similar repair -8- job carried out a number of times and work with housing management to address this issue and to recover repair costs from the tenant where appropriate. Timeframe for actions: • 6 months
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.