It was agreed: That Cabinet hereby authorises the Director (Communities), in consultation with the Leader of the Executive, Head of Legal and the Director (Corporate Services), subject to consideration of all due diligence, legal, financial, procurement and contractual issues to take all necessary actions in relation to; Advertise the sport and leisure facility opportunity to perspective external organisations via appropriate advertising publications. Develop an evaluation framework for assessing any expressions of interest made. Award a long term lease to preferred partner organisation, subject to Planning. To continue negotiations with GCLL on a contract extension period up to 2025 for the leisure centres.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
To update Cabinet on the future re-development of the site formerly known as Fleet Leisure and to seek authority to advertise for external organisations to invest, develop and manage the site as a sports and leisure facility linked to a long term lease.
Recommendations
1. That Cabinet hereby authorises the Director (Communities), in consultation with the Leader of the Executive, Head of Legal and the Director (Corporate Services), subject to consideration of all due diligence, legal, financial, procurement and contractual issues to take all necessary actions in relation to;
Advertise the sport and leisure facility opportunity to perspective external organisations via appropriate advertising publications. Develop an evaluation framework for assessing any expressions of interest made. Award a long term lease to preferred partner organisation, subject to Planning. To continue negotiations with GCLL on a contract extension period up to 2025 for the leisure centres.
1. Introduction
1.1At the Cabinet meeting of 30 March 2015 it was agreed to;
Extend the leisure centre contract with GCLL to 2025 and include Fleet Leisure.
Agree final amendments to the proposals outlined in this report.
A loan of approximately £2.6 million being made to GCLL by the council, making use of Prudential Borrowing powers as necessary.
The submission of any necessary planning application. Letting of the contracts for the development of the site.
2. Updated Position
2.1Following on from the previous Cabinet report, the VEAT notice did not illicit any expressions of interest from alternative facility providers and so the council has been working in partnership with Gravesham Community Leisure Limited (GCLL) to negotiate the financial and contractual arrangements to manage the Fleet Leisure site in tandem with an extension of the main leisure centre contract up to 2025.
2.2On top of these contract negotiations, also in partnership with GCLL, a series of feasibility studies, structural and building surveys, and detailed designs of the Fleet Leisure site have been carried out.
2.3Following some further soft market testing and further detailed design of the layout by GCLL through specialist leisure facility developers, it was anticipated that the original £2.6 million projected costs for the works would be difficult to achieve and the figure was estimated to be closer to £2.9 million, although at this stage it was still viable as a project.
2.4Around this time, Ebbsfleet United Football Club (EUFC) also decided not to be a major partner and long term hirer of the facility from GCLL, which meant that they would not require access to the planned highly spec’d grass pitches or use of the extensive catering facilities. The impact of this change on the proposed business plan and facility model impacted heavily on the projected income of the project, although a solution to this was to increase the amount of 3G provision on site.
2.5Once detailed feasibility work was commissioned, the structural surveys highlighted a high level of asbestos across the site, especially within the under-croft area of the main building. In order to meet the council’s duty of care responsibilities as owners and to remove some of the uncertainty around the proposed refurbishment phase, the asbestos was removed or encapsulated where necessary and a soft strip of the internals was completed. This enabled completion of all the necessary structural surveys. This took away a series of ‘unknowns’ from the refurbishment phase of the building in order to reduce the risk of future exaggerated costs once a building developer was appointed and on site.
2.6However, once the structural surveys were completed, it did become clear that the site was in very poor condition and although the development was yet to go out to tender, it was advised that due to;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.