Resolved
Resolved that Members were in agreement with the inclusion of the above seven risks for the Corporate Risk Register 2018-2019.
Finance and Audit Committee agreed this item on Monday 19 February 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that Members were in agreement with the inclusion of the above seven risks for the Corporate Risk Register 2018-2019.
Classification: Public Key Decision: No
Gravesham Borough Council
Report to: Finance & Audit Committee
Date: 19 February 2018
Reporting officer: Assistant Director (Corporate Services)
Subject: Corporate Risk Register for 2018-2019
Purpose and summary of report: This report informs Finance and Audit Committee of the outcomes from Gravesham Borough Council's annual risk identification and analysis exercise and presents a draft copy of the Corporate Risk Register for 2018-2019. The report also confirms that there are no material changes required to the Corporate Risk Management Strategy. Recommendations: 1. Members are requested to review the draft copy of the Corporate Risk Register for 2018-2019 which can be found at Appendix 2 of this report, prior to presentation to Cabinet for approval
1. Introduction and Background
1.1Gravesham Borough Council pursues a forward-looking and dynamic approach to delivering services to the local community and in doing so, the council is exposed to risk both in terms of threats and loss of opportunities. The council recognises that risks are inevitable and in practice, cannot be entirely avoided. Resultantly, the council will tolerate a certain degree of risk when pursuing objectives, executing strategies and delivering services.
1.2Responsibility for risk management runs throughout the council and specific roles and responsibilities have been identified so that risk management is embedded in the culture of the council. Finance & Audit Committee have responsibility for monitoring the effective development and operation of risk management through: Reviewing any changes that have been made to the Risk Management Strategy, prior to presentation to Cabinet for approval. Reviewing the annual Corporate Risk Register, prior to presentation to Cabinet for approval. Considering progress made during the year, in managing or mitigating risks contained within the Corporate Risk Register. Identifying potential risks for inclusion in the annual Corporate Risk Register. 2. Risk Management Strategy 2018-2019
2.1The Risk Management Strategy sets out the approach that has been adopted by the council for identifying, evaluating, managing and recording risks to which it is exposed. The primary intention of the risk management strategy is to ensure that risk management is embedded into the daily operations of the council. The strategy recognises that good risk management will lead to good management, good performance, good stewardship of public money, good public engagement and, ultimately, good outcomes for citizens and service users.
2.2A review of the strategy is carried out annually and, where necessary, it is updated to reflect any changes to the council’s approach to managing strategic risk.
2.3In March 2011, it was agreed by Cabinet that the Risk Management Strategy would only be presented to Members for approval if it was subject to updates and amendments resulting in material changes to the Strategy. The review has found that there have been no changes in the councils approach to managing strategic risks, therefore no material updates or amendments to the Strategy have been necessary.
3. Draft Corporate Risk Register 2018-2019
3.1In preparing the draft copy of the Corporate Risk Register for 2018-19, Management Team and Senior Officers were requested to:
Assess the existing risks recorded in the 2017-18 Corporate Risk Register, to confirm those which continue to generate a risk score above the council’s risk tolerance threshold and therefore be carried forward into the 2018-19 Register. The existing risks are:
On-going financial viability of the Council Changes in national priorities and legislative change Organisational capacity/ resilience Housing Revenue Account Services 100% Business Rates Retention Scheme
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
2. Risk Analysis (Risk identification Document) Appendix 2Appendix | 217 KB | Download |
PDF |
3. Draft Corporate Risk Register 2018-19 Appendix 3Appendix | 160 KB | Download |
PDF |
Corporate Risk Register 2018-19Report | 106 KB | DownloadRead as text |
Follow Finance and Audit Committee at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | The Audit Plan for Gravesham Borough Council - Year ending 21 March 2026It was agreed this be taken back to Grant Thornton to advise on how assurances could be provided for this asset. Asse... | Agreed | Open |
| 25 Feb 2026 | Statement of Accounts 2024/25 and Letter of RepresentationResolved that Members: considered the Statement of Accounts for 2024/25 and agreed that the Chair of the Finance and ... | Agreed | Open |
| 25 Feb 2026 | Review of Accounting Policies for 2025/26Resolved that Members endorsed the use of the Accounting Policies as outlined at Appendix One to this report, subject... | Decided | Open |
| 25 Feb 2026 | IA Charter ReviewResolved that Members approved the Charter presented at appendix two. | Approved | Open |
| 25 Feb 2026 | Internal Audit Plan 2026/27 (Q1-Q2)Resolved that Members approved the Internal Audit Plan 2026-27 (Q1-Q2) presented at appendix two. | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.