Resolved that application 20160721 be DELEGATED to the Planning Manager, Development Management, in consultation with the Chair, for the issue of outline planning PERMISSION subject to: (a) minor amendments to the planning conditions to take account of the concerns of the Regulatory Board (Planning); (b) Reasons and informatives as set out in the report; and (c) to the completion of the legal agreement under s106 of the Town and Country Planning Act 1990 to secure a financial contribution of £50,000 to be used either by the County Council, as the Local Highway Authority, towards sustainable transport measures in the vicinity of the site, or for the Borough Council to make the money available to Highways England as a pooled contribution to work to improve the free flow of traffic at the A2/Wrotham Road junction, as such as agreement to be completed within 6 months of the date of the meeting of the Board, unless an alternative period is agreed in consultation with the Chair and the Shadow Chair of the Board.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
SUMMARY REPORT Application Ref: 20160721 Site Address: Land At Coldharbour Road Northfleet Gravesend Kent DA11 8AB
Outline application with all matters reserved for the erection of offices, Application workshops and light industrial units with associated car parking, Description: servicing and landscaping, with alterations to the vehicular access.
Applicant: Capital Space Ltd
Agent: Paul Keywood, Turley
Ward: Painters Ash and adjoining Coldharbour and Woodlands Wards
Parish: Non-Parish Area
Decision due date: 04 July 2018
Publicity expiry date: 11 May 2018
Decision Level: Planning Regulatory Board - 16 May 2018
At the request of Cllr Sara Langdale due to concerns of excessive traffic Reason for referral: and scale of development
Outline Planning Permission be GRANTED subject to planning Recommendation: conditions and the applicants entering into a s106 legal agreement
This proposal is an outline application with all matters reserved for subsequent submission and being for the erection of offices, workshops and light industrial units with associated car parking, servicing and landscaping, with alterations to the vehicular access. The application is a very similar proposal to the outline applications made by the same applicants as in 2007 and 2010 but which were never implemented and consequently the permissions expired.
The current outline application which when it was originally submitted in late July 2016 sought permission for up to 6,016 sq. m of offices, workshops and light industrial units, thus some 965 sq. m of floorspace more than was originally permitted for this site.
This was revised in March 2018 following a number of amendments to the original documents reducing the overall quantum of floorspace to up to 5,051 sq. m of offices, workshops and light industrial units, and being for flexible Use Class B1 (a) and B1 (c) uses (general office and light industrial).
In addition to the amendment reducing the overall quantum of floorspace the April 2018 amendments include the offer of a £50,000 financial contribution to be secured under a s106 legal agreement to be used for either sustainable transport measures in the vicinity of the site or for the money to be made available to Highways England as a pooled contribution to works at the junction of the A227 Wrotham Road with the A2; and a commitment to a site wide Travel Plan to encourage more sustainable modes of travel.
The development as now proposed is policy compliant. Policy CS21 of the Gravesham Local Plan Core Strategy shows that the application site (land south of Coldharbour Road) is allocated for employment. Paragraph 4.8.14 states: This will provide office and light industrial development in the form of an enterprise centre/incubation space of approximately 5,050 sq. m gross with pedestrian links to surrounding developments which provide facilities for workers and visitors.
It is also compliant with Policy CS07 (Economy, Employment and Skills).
Notably there is support to the development from the GBC Economic Development Manager and who advises that office and industrial demand information supplied in January 2018 by Locate in Kent the counties Inward Investment Agency shows high demand levels for such space that the Borough currently cannot accommodate as it does not have enough supply.
There have been only very limited local neighbour objections to the proposals.
In respect of the strategic highway impacts of the development an earlier holding objection to the original development proposals from Highways England relating to the impact of traffic on the A2 junctions has been withdrawn and they recommend that conditions be attached to any permission and a legal agreement be entered into to secure funding to sustainable transport measures or a pooled contribution to works to the A2 junction.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.