Resolved
that the be approved and published on the Council’s website.
Cabinet approved this item on Monday 9 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
that the be approved and published on the Council’s website.
1.1In response to the national housing crisis, the Government published the Housing White Paper ‘Fixing our broken market’ in February 2017. The White Paper set out the Government’s plans to reform the housing market and boost the supply of new homes in England. The proposed measures covered planning for the right homes in the right places, how to build homes faster and how to diversify the housing market.
1.2Importantly, it proposed to hold local authorities to account for the number of new homes delivered through the introduction of a new Housing Delivery Test. The test would show whether the number of homes being built is below the required number of homes needed in that area. The test would provide a mechanism for establishing the reasons why there has been under delivery and providing a mechanism for setting out how this under delivery can be addressed. 1.3 The Government reinforced its objective to significantly boost the supply of new homes and making local planning authorities more accountable for delivery in their areas by publishing:
a revised National Planning Policy Framework (NPPF) (July 2018),
the Housing Delivery Test Measurement Rule Book (July 2018),
updated Planning Practice Guidance (PPG) (September 2018), and
the Housing Delivery Test: 2018 Measurement Technical note (February 2019).
1.4The methodology for calculating the Housing Delivery Test is set out in the Housing Delivery Test Measurement Rule Book. It measures the number of net homes delivered against the number of homes required over a rolling three-year period.
2. Housing Delivery Test
2.1The methodology for calculating the Housing Delivery Test is set out in the Housing Delivery Test Measurement Rule Book. At present, our housing delivery is measured by reviewing how many homes have been built out, over the preceding three financial year periods (2015-2018) against the housing target in the adopted Local Plan Core Strategy.
2.2If Local Authorities do not pass the Housing Delivery Test there are the following sanctions:
The ‘presumption in favour of sustainable development must be applied to planning applications if the test result is less than 45% in 2019, increasing to 75% from 2020 onwards, this means that proposed developments should be granted planning permission unless:
I. policies within the NPPF that protect areas or assets of particular importance provide a strong reason for restricting the overall scale, type or distribution of development or
II. the adverse impacts of the development "significantly and demonstrably" outweigh their benefits
A requirement to add a 20% buffer to the Council’s 5-year land supply of deliverable housing sites if delivery falls below 85% (this is to improve the prospect of achieving the planned supply); and
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
20190909 Appendix 2 Gravesham Housing Delivery Action PlanAppendix | 798 KB | Download |
PDF |
Housing Delivery Action PlanReport | 109 KB | DownloadRead as text |
Follow Cabinet at Gravesham and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Nov 2026 | Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... | Refused | Open |
| 28 Sep 2026 | Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. | Agreed | Open |
| 28 Sep 2026 | Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... | Noted | Open |
| 28 Sep 2026 | Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... | Decided | Open |
| 28 Sep 2026 | LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.