Armoury Drive Development - Contract Award

Refused Executive 1 paper

Cabinet refused this item on Monday 4 October 2021. Below is the council's own wording, with the papers it was decided on.

Item41

Resolved

Resolved that Cabinet gave delegated authority to the Director (Housing), in consultation with the Cabinet Member for Housing Services and Section 151 Officer, to award a build contract to the successful contractor following a selection process via the Kent Business Portal for the construction of six new Council homes consisting of 4 x 2 bed maisonettes and2 x 1 bed bungalows with the provision of associated parking, cycle/refuse storage and landscaping.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Classification: Public Key Decision: Yes

Gravesham Borough Council

Report to: Cabinet

Date: 04 October 2021

Reporting officer: Daniel Killian, Director (Housing)

Subject: Armoury Drive Development - Contract Award

Purpose and summary of report: To seek authority to award a build contract for the development of six new Council homes on land at Armoury Drive. Recommendations: 1. That authority be delegated to the Director (Housing), in consultation with the Cabinet Member for Housing Services and Section 151 Officer, to award a build contract to the successful contractor following a selection process via the Kent Business Portal for the construction of six new Council homes consisting of 4 x 2 bed maisonettes and 2 x 1 bed bungalows with the provision of associated parking, cycle/refuse storage and landscaping.

1. Land at Armoury Drive (former St John’s Ambulance Depot)

1.1A planning application for the above development was submitted by the Council and presented to Planning Committee on 16 December 2020. The application 20200561 was recommended for permission subject to conditions. Full permission was subsequently granted on 23 December 2020.

2. Procurement

2.1Potter Raper Limited (PRL) is appointed as the Council’s Employers Agent, and in consultation with Council officers, they prepared the tender documentation based on the drawings submitted to the Planning Committee along with the Council’s agreed Employer’s Requirements, for submission to the Kent Business Portal to which the Council has membership.

2.2Seven tender documents were received via the Kent Business Portal. In consultation with officers from Housing Strategy and Development and Finance, Potter Raper evaluated all tenders and provided a tender report for the Design and Build of 4 x 2 bed maisonettes and 2 x 1 bed bungalows. 2.3 Following the post-tender evaluation, Potter Raper Limited has recommended that the Longley Group be awarded the build contract for the scheme. Details of the costs can be found at Appendix 2 which is in the private part of this agenda.

3. Viability & Funding

3.1Officers from the Finance Department have assessed the viability of the scheme based on an Affordable Rent tenure using current Local Housing Allowance rates which gives a payback period of approximately 19 years.

3.2As from April 2012, the Ministry for Housing, Communities and Local Government announced that it would allow a local housing authority to retain some Right to Buy (RTB) receipts, provided that it could demonstrate that it had spent a sufficient amount on replacement affordable housing. Gravesham Borough Council signed the agreement with MHCLG in the first quarter of 2012 thereby confirming a commitment to delivering affordable housing.

3.3In return the authority agreed that 30% of the RTB receipts will be used to fund replacement stock and any unused receipts would be returned (after a period of three years from initial receipt) to the Secretary of State with interest at 4% above base rate.

3.4Following a government consultation in 2018, the rules around using RTB receipts were reformed with the reforms coming into effect in April this year. These reforms included increasing the cap on the cost of a replacement home that can be met from RTB receipts from 30% to 40% for both Social and Affordable Rent homes. The period for which receipts could be retained also changed, and increased from three years to five years.

3.5The balance of funds (60%) must be met from either the HRA’s existing resources or using external borrowing. The HRA’s resources are limited and therefore it is likely that the Council will secure external borrowing to fund most of the remaining cost of the scheme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Armoury Drive Development: Contract AwardReport 87 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Armoury Drive Development - Contract AwardThis decision
  2. Armoury Drive, Gravesend - Residents ParkingDecided

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies