That members support the proposals for Cascades Leisure Centre, as set out in the report; and 2. Delegated authority is given to the Director (Communities) in consultation with the Leader and Director (Corporate Services in the role of S151 officer) and the Monitoring Officer; to take all necessary practical, financial and legal actions required to deliver the leisure centre within agreed budgets (inclusive of but not limited to entering into the relevant formal legal agreements required to engage consultant support, agree and commence the procurement process, evaluate and appoint successful contractors, approve the design, commence construction and certify the acceptance of completion of works.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Melanie Norris, Director (Community Services) Sarah Parfitt, Director (Corporate Services)
Subject: Cascades Leisure Centre
Purpose and summary of report: To provide Members with an overview of the project that is proposed for redevelopment of Cascades Leisure Centre. To seek Member approval for the progression of the proposals outlined within this report.
Recommendations: Members are requested to: 1. Support the proposals for Cascades Leisure Centre, as set out within this report. 2. Grant delegated authority to the Director (Communities) in consultation with the Leader, the Director (Corporate Services) (in the role of S151 officer) and the Monitoring Officer; to take all necessary practical, financial and legal actions required to deliver the leisure centre within agreed budgets, (inclusive of but not limited to entering into the relevant formal legal agreements required to engage consultant support, agree and commence the procurement process, evaluate and appoint successful contractor(s), approve the design, commence construction and certify the acceptance of completion of works).
1. Introduction and Background
1.1The Council commissioned Knight, Kavanagh, & Page (KKP) to undertake a feasibility study of the Council owned leisure centres, currently located at Cascades Leisure Centre and Cygnet Leisure Centre. The key focus of the study was to refresh the Council’s Indoor Leisure Strategy and to redefine its needs and options for investment in its facility portfolio.
1.2The updated work needed to take account of a changed landscape from the original strategy completed in 2016. These changes include the developments of the Lower Thames Crossing, potential developments undertaken in Ebbsfleet Development Corporation and the proposed Garden City, as well as the potential impact of Covid- 19 on the leisure industry. The updated study work was completed over two phases;
Phase One – a refresh of the 2016 Indoor Strategy and, based on the refreshed strategy findings; Phase Two - a feasibility study to investigate whether/how to replace one or both facilities, in a process which incorporates evaluation of capital and revenue costs, as well as a management options appraisal to assist the Council in deciding on the optimal way forward.
2. Cascades Leisure Centre – strategic case for redevelopment
2.1The main conclusions of the feasibility study can be summarised as follows;
2.1.1 There is commitment by Gravesham Borough Council to addressing health inequalities in the Borough, and to invest in new leisure provision as a means towards delivering on this commitment. The Corporate Plan has identified that it is important in ensuring that residents are ‘safe, healthy and active.’ Section two of the plan; ‘Place’ lays out the council’s commitments towards this:
Design a quality and affordable leisure offer –improved facilities and creative sports programmes to tackle local health inequalities
Improve resident wellbeing – provide and preserve a suite of high quality play areas and promote opportunities for active lives
Manage a programme of proactive healthy living interventions – work with partners to support and safeguard vulnerable residents.
2.1.2 The needs assessment shows that, as per the previous 2016 GBC indoor assessment and strategy, Cascades and Cygnet Leisure centres are ageing and have issues in respect of their building quality. Whilst being well located in respect of their accessibility to Gravesham residents, they do not provide a modern, flexible offer to the community.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.