The Director (Housing) in consultation with the S151 Officer and Lead Member be given delegated authority to conduct the procurement process and award the contracts for DSO Building Management using procurement frameworks by way of mini tender and direct award as outlined in the report.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
1.1As a landlord, Gravesham Borough Council has a statutory duty to ensure its housing stock is properly maintained, that equipment is serviced and that any responsive repairs are completed within a timely manner and it is essential that external service providers are in place to assist with the delivery of required works.
1.2The Councils current Procurement Strategy actively encourages the use of frameworks, which consist of a list of pre-approved suppliers for effective procurement arrangements via min-tender or direct award to deliver high quality services to our tenants.
1.3The Joint Contracts Tribunal (JCT) suite of contracts are used between the employer and contractor to agree terms and conditions, control payment, disputes, insurance and extent of works, thus reducing the risk to any project.
2. Current Position
2.1The following Major & Planned Works contracts procured via the South East Consortium (SEC) are due to expire on 31 March 2023:
2.1.1 Cyclical Decorating (Axis Europe)
2.1.2 Roofing Replacements (Breyer Group)
2.1.3 Wet Rooms & Level Access (Pilon)
2.2The following Compliance & Projects contracts procured via the South East Consortium (SEC) are due to expire on 31 March 2023
2.2.1 Mobility Lifts (Apex Lifts)
2.2.2 Water Hygiene (H20 Nationwide Ltd)
2.2.3 Asbestos Surveys (Riverside)
2.2.4 Asbestos Removals (PA Group)
2.3To meet the carbon reduction and energy efficiency HRA related commitments in the corporate Climate Delivery Action Plan and Housing Operations Carbon
2 Action Plan, the council requires two new contracts in place to deliver the relevant improvement measures to its housing stock:
2.3.1 Energy Efficiency Measures (Whole House Retrofit) - includes loft, cavity, external wall insulation and Solar PV)
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.