Cabinet endorse the view that the council proceeds with Option Three as set out in section 7.1 of the report, namely progressing with the project, recognising the financial viability challenges and seeking to: · Contain costs within the current estimate; · Increase capital funding for the scheme; and/or · Identify opportunities to reduce costs further where they are not significantly detrimental to the key objectives of the project. 2. Cabinet recorded that any decision to proceed will be considered as a Key Decision taken by the Executive Leader in accordance with Annex 1.6 of the Constitution, recognising that this will have no impact on the approved capital programme for 2022/23.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Jamie Izzard – Director (Communities) Sarah Parfitt - Director (Corporate Services)
Subject: Cascades Leisure Centre Project Update
Purpose and summary of report: To provide Cabinet with an update of the Cascades Leisure Centre project and proposed next steps. Recommendations: 1. Cabinet is asked to endorse the view that the council proceeds with Option Three as set out in section 7.1 of this report, namely progressing with the project, recognising the financial viability challenges and seeking to: Contain costs within the current estimate; Increase capital funding for the scheme; and/or Identify opportunities to reduce costs further where they are not significantly detrimental to the key objectives of the project.
2. Cabinet are asked to record that any decision to proceed will be considered as a Key Decision taken by the Executive Leader in accordance with Annex 1.6 of the Constitution, recognising that this will have no impact on the approved capital programme for 2022/23.
Key Implications: Item Implications Legal The approval and commissioning of building works is an executive function for which the Cabinet have responsibility once the budget has been approved by the Council. Such a delegation is within the gift of the Cabinet, however, within the 31 January 2022 report it was outlined that Cabinet must be content that the level of member input into the project from hereon will be limited and thus they are satisfied there will be an adequate level of checks and balances, and accountability. Selected senior officers have delegated authority to carry out all necessary steps to deliver a completed leisure centre within approved budgets without further consideration by the cabinet. This includes the procurement of Early Contractor Involvement (ECI), following a competitive procurement process through the Pagabo ‘Major Works’ Framework. Finance and Value for The financial considerations for the council are set out within the Money 31 January 2022 Cabinet Report and the subsequent latest financial evaluation is included in this update report.
To demonstrate value for money a competitive procurement process will be undertaken through the Pagabo ‘Major Works’ Framework. Contractors on this Framework and the reserve list will be invited to tender. The successful candidate will be invited to enter a Pre-Construction Services Agreement (PCSA) with the Council. This assumes a two-stage process: pre-construction services ahead of a construction contract. The candidate that provides the PCSA scope will not necessarily be appointed for the second stage, construction contract – as the Council will reserve the right to re-engage the market should budget parameters be breached.
Corporate Plan Our ambition to deliver this new state-of-the-art building at pace, in line with the project vision and sustainability objectives and the Corporate Plan commitments.
Key Corporate Plan commitments include:
Deliver an ambitious and diverse programme of building Design a quality and affordable leisure offer Carbon neutral borough Positively promote sustainable development
Climate Change A decision to undertake this project will have a direct impact on the delivery of the council’s Climate Change Strategy. This will contribute to Priority 1: GBC – the organisation and, specifically, the progression of plans to replace the largest energy-using operational assets of the council. In 2020-21 the council produced carbon emissions totalling 1,760.3 tCO2e. Of this, 255.4 tCO2e (15%) could be attributed to Cascades Leisure Centre.
1. Introduction and Background
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.