Cabinet, Tuesday 3 January 2023 at 7.30pm

Emerging Local Plan - Local Development Scheme

Decided Executive 3 papers

Cabinet decided this item on Tuesday 3 January 2023. Below is the council's own wording, with the papers it was decided on.

Item55

Resolved

that the Assistant Director (Planning), in consultation with the Cabinet member for the Strategic Environment Portfolio, be delegated authority to publish a revised Local Development Scheme.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Classification: Private Key Decision: No

Gravesham Borough Council

Report to: Cabinet

Date: 3 January 2023

Reporting officer: Wendy Lane – Assistant Director (Planning)

Subject: Emerging Local Plan - Local Development Scheme

Purpose and summary of report:  To provide Cabinet with an update on the emerging Local Plan Timetable now that the ongoing delays caused by the highways modelling, which are attributable to external organisations, are known.  To seek approval for publishing a revised Local Development Scheme.

Recommendations: Cabinet members are asked to give the Assistant Director (Planning) in consultation with the Cabinet member for the Strategic Environment Portfolio delegated authority to publish a revised Local Development Scheme, in line with Appendix 2.

Key Implications:

Item Implications

Legal Section 15 of the Planning and Compulsory Purchase Act 2004, as amended, requires the Council as a Local Planning Authority (LPA) to prepare and maintain a LDS. The current LDS was brought into effect on 8 October 2019.

Finance and Value for The Council maintains a Planning Policy Reserve for Money commissioning work related to the Local Plan, with separate revenue budgets covering day to day expenditure on staff. The Planning Policy Reserve and revenue budgets will need to be reviewed in light of the amended Local Development Scheme.

Corporate Plan The emerging Local Plan feeds into Strategic Objectives 1,2, 3 and 4

Climate Change There are no direct implications arising from the recommendations contained within this report. However, a key component of the emerging Local Plan includes addressing sustainability and climate change – with policies included to assist with this.

1 1. Introduction

1.1The Council currently has an adopted Local Plan Core Strategy covering the whole borough (including the part of Ebbsfleet Development Corporation that falls within Gravesham). This was adopted by the Council in September 2014. Several policies of the Adopted Gravesham Local Plan First Review were saved following approval by the Secretary of State via a Direction issued 2007. Together with the Gravesham Local Plan Policies Map (adopted in September 2014), they form components of the Development Plan, for which Gravesham Borough Council has direct responsibility as part of our Plan Making role.

1.2Following the adoption of the Core Strategy officers turned their attention to reviewing the Local Plan Core Strategy, as well as progressing work on the Site Allocations and Development Management Policies Document. The latter document being the second part of the Council’s Local Plan, which would allocate additional sites for development, designates sites / land for specific uses and would set out the detailed Development Management policies.

1.3The Council’s project plan for bringing forward the emerging Local Plan is set out in the Council’s Local Development Scheme, with the most recent Local Development Scheme being adopted by Cabinet in October 2019.

2. Local Development Scheme

2.1The Planning and Compulsory Purchase Act 2004 (as amended) places a statutory duty on the Council to maintain an up-to-date Local Development Scheme. The current (October 2019) Local Development Scheme is attached to this report at Appendix 1.

2.2The Local Plan Core Strategy and Proposals Map need to be updated to reflect changing circumstances both locally and a result of changes to Government policy. With the remaining Saved Policies from the Gravesham Local Plan First Review in need of being replaced in their entirety.

2.3Key dates from the currently adopted Local Development Scheme for the remaining tasks associated with the emerging Local Plan are set out in the table below.

Stage October 2019 LDS

Public Consultation Regulation 19 (statutory 6 September-October weeks) 2020

Submission for independent examination February 2021 (regulation 22)

Examination July 2021

Receipt of Inspector’s Report November 2021

Full Council followed by adoption and publication December 2021

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gravesham_Local_Development_SchemeAppendix 1 381 KB Download
PDF
Revised Local Plan TimetableAppendix 2 147 KB Download
PDF
Emerging Local Plan: Local Development SchemeReport 257 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Gravesham

Search all
  1. Emerging Local Plan - Local Development SchemeThis decision
  2. Development Management Policies in the emerging Local Development Framework (LDF)Noted

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies