that Cabinet endorses the proposed Energy Procurement Strategy for the council; and 2. that Cabinet agrees to procure the council’s energy requirements from the current Public Buying Organisation (LASER) and delegates authority to the Director (Corporate Services), in consultation with the Monitoring Officer and Head of Property & Regulatory Services, to take all necessary practical, financial and legal actions required to secure the necessary arrangements from October 2024.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Sarah Parfitt, Director (Corporate Services)
Subject: Future Energy Procurement
Purpose and summary of report: To inform Cabinet on proposals for the procurement of the council’s energy requirements from October 2024.
Recommendations: 1. Cabinet endorses the proposed Energy Procurement Strategy for the council. 2. Cabinet agrees to procure the council’s energy requirements from the current Public Buying Organisation (LASER) and delegates authority to the Director (Corporate Services), in consultation with the Monitoring Officer and Head of Property & Regulatory Services, to take all necessary practical, financial and legal actions required to secure the necessary arrangements from October 2024.
Key Implications: Item Implications Legal The Energy Purchasing Framework proposed has been established to comply with the requirements of the Public Contracts Regulations of 2015, as amended (PCR2015). Kent County Council remains the Contracting Authority for all LASER contracts. This permits a public body to access LASER’s frameworks and services without the need to run a separate procurement process to do so. Finance and Value for LASER’s current flexible frameworks have been assessed as Money reducing the council’s energy spend by £206.8k per annum over the current term. Access to LASER’s purchasing power is expected to provide access to competitive best-value market energy prices and also deliver social value benefits. Corporate Plan The decision to procure will support the following Corporate Plan commitments: #1 People – Carbon Neutral Borough #3 Progress – Sound financial management #3 Progress – Successfully manage key business risks Climate Change The Climate Change Strategy 2022-2030 delivery plan specifies securing the procurement of renewable energy when the current supply contract end (area of action 1.4). The LASER flexible framework will open up various routes to assist with this aim. 1. Introduction
1.1The council is currently procuring its gas and electricity requirements from the LASER Energy Buying Group, an organisation established by Kent County Council in 1989 to collaboratively procure energy on behalf of the public sector. LASER is a Public Buying Organisation (PBO). Kent County Council remains the Contracting Authority and Central Purchasing Body (CPB) for gas and electricity framework contracts operated by LASER.
1.2These supplies meet the energy requirements of the council’s corporate properties including the Civic Centre and Brookvale Depot, council operated street lighting and communal requirements of housing assets. Council spend on electricity and gas for the past two years and the budgeted spend for the current year are shown in the table below.
2023/24 2021/22 2022/23 Electricity Original Outturn Outturn Budget Civic Centre/Brookvale Depot 160,510 327,500 367,090 Other General Fund Sites 72,590 159,270 154,490 HRA Sites 24,910 67,640 66,010 Total 258,010 554,410 587,590 2023/24 2021/22 2022/23 Gas Original Outturn Outturn Budget Civic Centre/Brookvale Depot 23,640 55,070 17,990 Other General Fund Sites 65,750 129,690 98,020 HRA Sites 51,650 107,630 113,970 Total 141,040 292,390 229,980
1.3With the current contract expiring on 30 September 2024, procurement of the new contract needs to start imminently in order to have a new contract in place by 30 September 2023 (both electricity and gas are purchased up to one year in advance).
1.4This report sets out the energy procurement strategy that has been set in place when considering procurement options for the council, alongside the proposed route to procurement to ensure that the council secures value for money with its preferred provider to meet its energy requirements from October 2024.
2 2. Energy Market Update and Economic Context
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.