It was agreed: Director (Housing) in consultation with the S151 Officer and Lead Member be given delegated authority to conduct the procurement process and award a contract for the remediation of brownfield land at Milton Place, funded by grant funding.
Word for word from the decision Gravesham published for this meeting.Source: democracy.gravesham.gov.uk
Reporting officer: Daniel Killian, Director (Housing)
Subject: Contractor Procurement – Brownfield Land Release Fund
Purpose and summary of report: This report seeks Cabinet approval to procure and award a contract for remediation of brownfield land at Milton Place, in preparation for future development. The total remediation cost is estimated to be £1.6m, funded by the Brownfield Land Release Fund grant funding that was awarded to Gravesham late last year. Procurement will be conducted using a relevant framework in accordance with Gravesham's Procurement Strategy. Recommendations: 1. Director (Housing) in consultation with the S151 Officer and Lead Member be given delegated authority to conduct the procurement process and award a contract for the remediation of brownfield land at Milton Place, funded by grant funding.
Key Implications: Item Implications Legal A contract will be secured through pre-tendered frameworks which have been procured in accordance with domestic and European legislation Finance and Value for Procuring through a framework is the most cost-effective way of Money undertaking procurement and ensures value for money both in the tendering process and awarding of contract. Balancing the Budget a. Does this report form part of the balancing the budget delivery plan? No
b. If yes to question a, when will the projected savings be recognised in the budget? n/a c. If no to question a, should it form part of the plan? No
Corporate Plan This report relates to Corporate Objective 02 - #ONECOMMUNITY Climate Change Following remediation of the brownfield site, the works to be undertaken contribute to the Council’s Climate Change Strategy by:
(a) Reducing carbon emissions in new build housing due to current Building Regulation carbon emission targets (b) Reduction in energy consumption and fuel bills for our tenants (c) Providing warmer energy efficient homes for our tenants (d) Use of renewable heating and hot water systems, (Air source heat pumps and solar PV panels)
1. Milton Place
1.1The potential for development at Milton Place was first discussed by Cabinet in January 2018, where the Director (Housing & Regeneration) updated members on discussions with the Ebbsfleet Development Corporation (EDC) in relation to land they owned in the borough, that adjoined council owned land and had the potential for development. At this meeting, members supported the recommendation to allow officers to continue the work with the EDC to explore future development.
1.2Specifically in relation to Milton Place, the report referenced two options, the first was for Gravesham to work jointly with the EDC to bring forward a development scheme, the second was for Gravesham to purchase the land owned by the EDC to develop it alone.
1.3Cabinet considered a further report in September 2018. The report updated members on the work that had been undertaken to date, including information on the development appraisal completed by a specialist demonstrating the development potential, and recommended working jointly with the EDC to secure planning permission for a scheme and then either market the scheme to a developer or for Gravesham to progress and develop the scheme alone.
1.4Between the report in 2018 and a further update in March 2021, ongoing viability work took place, but due to resourcing issues and a change in direction for the EDC, the work did not progress as originally planned. At this point, Cabinet took the decision to purchase the parcel of land owned by the EDC to ensure a housing scheme was eventually built out.
1.5In May 2022, the Director (Housing) proposed to Cabinet the formation of an Investment Partnership (IP) with a housebuilder to help bring forward larger schemes within the Borough that the Council wished to pursue, and recommended using the Milton Place site as a pilot project once the IP was established.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.