Gravesham Borough Council
Cabinet, Monday 3 November 2025 at 7.30pm

Gravesend Town Centre Improvements Programme

Approved Executive 3 papers

AI summaryGravesham Cabinet approves receipt and spending of £3m from the Local Regeneration Fund and £490,000 from the Lower Thames Crossing for Gravesend Town Centre improvements, with delegated authority to the Director.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet approved funding and delegated project detail to Director
Money£3m and £490,000From Local Regeneration Fund and Lower Thames Crossing
What happens nextDirector to develop project detailWith Leader, Monitoring Officer and Section 151 Officer
Who it affectsGravesend Town CentreProgramme of town centre interventions

What was decided

Cabinet approved the receipt and expenditure of £3m from the Local Regeneration Fund, formally the Levelling Up Fund, and £490,000 from the Lower Thames Crossing for a programme of interventions in Gravesend Town Centre.

Delegated authority was given to the Director (Communities and Inclusive Growth) to progress project-level detail and all legal, financial and practical arrangements, in consultation with the Leader, Monitoring Officer and Section 151 Officer.

Why

The decision is supported by a Stage 2 Feasibility Study for Town Centre Public Realm and a Town Centre Action Plan, listed as appendices to the report. Report 6.1, 6.2

The report records the decision as making a positive contribution to promoting equality, supporting the Levelling Up agenda by reducing economic and social disparities across geographical locations. Report P9

What happens next

The Director (Communities and Inclusive Growth) will develop the project-level detail and all legal, financial and practical arrangements.

Individual project risk registers will be maintained via the monitoring and evaluation process, and programme risks will be monitored at board level. Report P7

Designing out crime and secure by design principles will be considered in all town centre improvements and initiatives. Report P9

The money

  • £3m Receipt and expenditure from the Local Regeneration Fund (formally the Levelling Up Fund) for Gravesend Town Centre interventions
  • £490,000 From the Lower Thames Crossing for Gravesend Town Centre interventions

Implications

  • Financial: Approval of receipt and expenditure of £3m from the Local Regeneration Fund and £490,000 from the Lower Thames Crossing.
  • Equalities: Decision supports the Levelling Up agenda by promoting equality and reducing economic and social disparities across geographical locations. Report P9
  • Risk: Individual project risk registers will be maintained via the monitoring and evaluation process, and programme risks will be monitored at board level. Report P7
  • Legal: Designing out crime and secure by design principles will be considered in all town centre improvements and initiatives. Report P9
  • Staffing: Project-level detail and arrangements will be progressed by the Director (Communities and Inclusive Growth) with delegated authority.

Who and where

  • Users of Gravesend Town Centre
  • Gravesham borough residents and businesses

Plain English for the jargon

  • Local Regeneration Fund: Funding stream formally known as the Levelling Up Fund, as named in the decision.
  • Section 151 Officer: Council officer with statutory responsibility for financial administration.
  • DPIA: Data Protection Impact Assessment, required at the start of major projects involving personal data.
  • M&E process: Monitoring and evaluation process used to maintain individual project risk registers.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item54

Resolved

To approve the receipt and expenditure of £3m from the Local Regeneration Fund (formally the Levelling Up Fund) and £490,000 from the Lower Thames Crossing to deliver a programme of interventions in Gravesend Town Centre. Delegated authority is given to the Director (Communities & Inclusive Growth) to progress the development of the project-level detail and all legal, financial and practical arrangements in consultation with the Leader, Monitoring Officer and Section 151 Officer.
Word for word from the decision Gravesham published for this meeting. Source: democracy.gravesham.gov.uk

Follow this further

Built from Gravesham's papers

What the report saysPro

Report to Cabinet

Classification: Public Key Decision: Yes

Gravesham Borough Council

Report to: Cabinet

Date: 3 November 2025

Reporting officer: Naznin Chowdhury, Head of Major Projects & Programmes

Subject: Gravesend Town Centre Improvements Programme

Purpose and summary of report: This report seeks approval for a number of projects within Gravesend Town Centre that aim to make it a greener, safer and healthier place to work, live, shop, eat and play. The proposals are fully funded by grants from HM Government’s Local Regeneration Fund (formerly referred to as the Levelling Up Fund) of £20m and Lower Thames Crossing (LTC) funding of £490,000. £17m of the £20m LRF funding is already allocated to the redevelopment of Cascades Leisure Centre, an update on which is included at section 1 below. This report therefore seeks approvals related to the remaining £3m of that funding and the LTC contribution.

The report also updates members on the wider approach to revitalising Gravesend Town Centre. Recommendations: 1. Approve receipt and expenditure of £3m from the Local Regeneration Fund (formally the Levelling Up Fund) and £490,000 from the Lower Thames Crossing to deliver a programme of interventions that help make Gravesend Town Centre a greener, safer and healthier place to work, live, shop, eat and play.

2. Delegate authority to the Director (Communities & Inclusive Growth) to progress the development of the project-level detail and all legal, financial and practical arrangements in consultation with the Leader, Monitoring Officer and Section 151 Officer, taking all necessary practical, financial and legal actions, including entering into the relevant formal legal agreements required.

Key Implications: Item Implications Legal All legal and contractual arrangements will be agreed at an individual project level, including adhering with appropriate procurement requirements. Finance and Value for The proposals outlined are fully funded through external grant, Money with LUF funding already included in the capital programme. Approval to add LTC grant of £0.49m to the capital programme will be sought following Cabinet consideration of this report. Corporate Plan Corporate plan objectives 1: #oneborough, 2: #onecommunity

Climate Change Undertaking these projects that make up the improvement programme will have a direct impact on the delivery of the council’s Climate Change Strategy. Specifically, this will assist in progressing plans to improve the council’s operational assets.

1. Introduction

Town Centre Revitalisation

1.1Gravesend Town Centre is a well-loved, historic and architecturally stunning riverside town. The high-speed rail link has brought unrivalled connectivity, and it has a thriving cultural scene, with many innovative small businesses making the town their home.

1.2Gravesend does however face familiar challenges, not least a national decline in retail demand that has meant that diversification of uses is key to revitalisation. Successful work has been underway to bring in alternative uses across the town, from Escape Rooms to Pilates studios, street food halls to art galleries.

1.3Officers have also worked with the Cabinet and other key stakeholders to understand how different parts of the town can support different uses and users, such as the emerging independent retail offer on the High Street, the role of key regeneration sites, and the continued need for a strong ‘essential’ retail offer along New Road and the adjacent shopping centres.

(Cabinet away day presentation slide, 2024)

1.4The proposals outlined in this report were developed through three stakeholder engagement sessions held in November 2024, March and July 2025. Invitees included the Portfolio Holder, the local MP, local business owners and other key stakeholders within the town centre.

2 1.5 Members will recall a Cabinet Awayday in 2024 where an outline plan for revitalising Gravesend Town Centre was agreed. The Plan focused on the following six key areas:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
RIBA Stage 2 ReportAppendix 1 11 MB Download
PDF
Town Centre Detailed Action Plan 2025-26Appendix 2 334 KB Download
PDF
Gravesend Town Centre Improvements ProgrammeReport 1.6 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 6 attended
JB
Cllr John BurdenChair, present
SM
Cllr Shane Mochrie-CoxVice-Chair, present
RA
Cllr Rajinder AtwalCommittee Member, apologies
DC
Cllr Deborah CroxtonCommittee Member, present
EM
Cllr Emma MorleyCommittee Member, present
KO
Cllr Karina O'MalleyCommittee Member, present

On this subject at Gravesham

Search all
  1. Gravesend Town Centre Improvements ProgrammeThis decision
  2. Gravesend Town Centre and Riverside Regeneration (PART A)Agreed
  3. Gravesend Town Centre and Riverside Regeneration (PART B)Agreed
  4. Balancing The Budget - Gravesend Town Centre OptionsDecided
  5. Revitalisation of Gravesend Town Centre Scrutiny Review - Oral Update following consideration at CabinetDecided
  6. Revitalisation of Gravesend Town Centre Scrutiny Review - Moving ForwardAgreed

More from Gravesham Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Refuse Vehicle ProcurementTo procure three refuse collection vehicles (one new vehicle and two new chassis with replacement body vehicles) to s... Refused Open
28 Sep 2026 Change to Order of BusinessIt was agreed that the order of business, during the meeting, be amended accordingly. Agreed Open
28 Sep 2026 Cygnet Leisure Centre - Wet Side ImprovementsDecision, outlining the intention to part fund the refurbishment, was published on 14 July 2026 GCLL had provided a p... Noted Open
28 Sep 2026 Gravesham Borough Council's response to 'The Shift'· The Council will work with the Shift Committee & young people to explore, design & develop an interim community spa... Decided Open
28 Sep 2026 LGA Corporate Peer Challenge - Progress Review Follow-up· That the content of the LGA Corporate Peer Challenge Progress Review report be noted · That the process for publish... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies