Greater Manchester Transport Committee noted this item on Friday 18 September 2020. Below is the council's own wording, with the papers it was decided on.
That the report be noted. 2. That it be noted that Northern would respond directly to Cllr Peter Robinson with relation to works planned for Newton and Godley stations on the Hadfield Line, and information included in a future report. 3. That congratulations be extended to Hindley train station who recently received a highly commended award at the National Rail awards.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
This report provides an update on local rail stations matters within Greater Manchester.
Recommendations
Members are asked to note the contents of this report.
CONTACT OFFICERS:
Simon Elliott Head of Rail Programme [phone removed] [email removed] Equalities Implications: n/a Climate Change Impact Assessment and Mitigation Measures – n/a Risk Management: n/a Legal Considerations: n/a Financial Consequences – Revenue: n/a Financial Consequences – Capital: n/a
Number of attachments to the report: n/a
BACKGROUND PAPERS: n/a
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which n/a means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
1.1This report aims to provide an overview to Members on local rail station matters since 23 March, 2020 and any impacts as a result of the Coronavirus pandemic.
1.2The report is structured under subject headings aligned with the following key areas of focus for TfGM in relation to rail station items, including:
Access for All funding and mid-tier programme Mills Hill park and ride scheme Rail Station Improvement Schemes (RSIS) Rail Station Alliance Community Rail
2. ACCESS FOR ALL FUNDING AND MID-TIER PROGRAMME
2.1It is recognised that extensive work is needed to address accessibility issues and the provision of the necessary facilities to encourage travel by train by passengers with disabilities and mobility restraints.
2.2Across Greater Manchester approximately 40% of rail stations are stepped access and a further 14% with steep ramps.
2.3Although the responsibility for addressing this issue lies with Network Rail and the train operating companies, historically GMCA has also invested in improvements in this area.
2.4In April 2019, DfT announced the outcome of the Access for All programme, which will, subject to feasibility design, award funding to 73 stations to receive accessibility improvements. In Greater Manchester, Daisy Hill and Irlam were successful. TfGM is working closely with Network Rail and Northern to progress these projects. All work at Daisy Hill and Irlam is to be completed by the end of March 2024. TfGM have agreed with Network Rail and Northern to procure the delivery of Governance for Railway Investment Projects (GRIP) Stages 3-5. The procurement of the work has been impacted by COVID and will be completed later this year.
2.5Following joint working with the rail industry, TfGM and Network Rail secured additional funding for Walkden as part of the March 2020 budget announcements. Work is now underway to include this in the above work programme. Although Daisy Hill and Irlam will be managed by TfGM, following discussions with Network Rail, it has been agreed that they will progress the delivery of GRIP Stages 3-5. This is due to several operational challenges with this scheme and mine workings in the area, Network Rail are best placed to take this scheme forward. 2.6 Additional to the main Access for All programme, in July 2019, DfT announced the Access for All Mid-Tier programme. This fund will provide £20 million nationally focused on stations where accessibility improvements can be delivered with a fixed contribution up to £1 million of government support. This funding is in addition to the Access for All Programme detailed above. The fund is targeted at smaller scale access improvements and TfGM has submitted a single nomination covering a number of smaller improvements at around 22 stations. The types of improvements proposed include:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Peter RobinsonCommittee Member, present
SA
Councillor Stephen AdsheadCommittee Member, present
Hear about the next one first
Follow Greater Manchester Transport Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Sub Committee MeetingsThat the minutes of the Metrolink & Rail Sub Committee held on 3 March 2023 be noted. 2. That the minutes of the Bus ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.