Greater Manchester Transport Committee noted this item on Friday 18 September 2020. Below is the council's own wording, with the papers it was decided on.
That the report be noted. 2. That face covering compliance had been recorded as between 80-90% with some variance on lines and times of day and that targeted intervention had been undertaken to address areas of poorer compliance. 3. That it be noted that Government’s Light Rail Funding offer had been extended until the 26 October 2020 which covers operating costs only, and there were ongoing discussions with DfT regarding future funding packages. 4. That it be noted that capacity had begun to become an issue on some peak time services under the current social distancing guidance. However, in additions to the use of doubles across the network, recent TfGM communications campaigns had been designed to encourage people to travel outside peak times where possible. 5. That it be noted that further ticket options to ensure value and flexibility were being considered by TfGM.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
o Metrolink Quarterly Performance Report – 21 February 2020
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which N/A means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee N/A N/A 1. INTRODUCTION/BACKGROUND
1.1Metrolink is the largest urban light rail network in the UK. It provides a fast, frequent service which is fully accessible to all, running 7 days a week, 364 days of the year.
1.2The Metrolink network is owned by TfGM and is operated on TfGM’s behalf through a contract with KeolisAmey Metrolink (KAM).
1.3The network uses high-floor trams with raised platform stops and had reached patronage of over 45 million passengers each year, pre COVID-19.
1.4There are currently 120 trams serviced from two depots with 108 required to operate the current weekday daytime service.
1.5Trams serve 99 stops covering routes totalling just over 100 Km. Metrolink is the most accessible of the public transport networks in Greater Manchester, providing step free access to all stops.
2 PERFORMANCE SUMMARY
2.1The Metrolink Quarterly Performance Report provides a performance summary for the rolling 12-month period through to 25 July 2020.
2.2As expected, Metrolink patronage has been significantly affected by the COVID-19 pandemic reducing patronage down to just 5% of normal levels by Easter. Patronage growth has been steadily increasing since changes in Government guidelines and we are now carrying approx. 40% of pre COVID-19 patronage.
2.398.9% of scheduled miles were operated during the 12 months to July 2020 against a performance target of 99.4%. In the last quarter performance has remained above the target during the operation of bespoke COVID-19 services introduced.
2.4Recorded incidents of crime and anti-social behaviour on the network decreased during the COVID-19 lockdown. Levels have begun to climb since the lockdown has begun to ease and people begin to use public transport again.
2.5The number of recorded customer contacts and complaints also reduced during the lockdown due to the very low numbers of customers using the network, following government advice not to travel on public transport.
2.6Despite challenging circumstances, the Trafford Park line opened on 22 March. The service currently operates between Cornbrook and the intu Trafford Centre, the planned extension of the service across the city centre remains under review. 2.7 The delivery of the first of 27 new trams have been delayed until October 2020 as a result of of the COVID-19 pandemic and its impact on the supply chain in northern Italy and elsewhere.
2.8PATRONAGE
2.9Patronage measures the number of trips that are being made on the network.
2.10Inevitably, COVID-19 has significantly impacted patronage on the Metrolink network as can be seen in the chart below.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Transport Committee at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Minutes of the Sub Committee MeetingsThat the minutes of the Metrolink & Rail Sub Committee held on 3 March 2023 be noted. 2. That the minutes of the Bus ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.