Greater Manchester Combined Authority approved this item on Friday 27 November 2020. Below is the council's own wording, with the papers it was decided on.
That the proposed alignment of the Key Route Network with the Major Road Network, as published by the Department for Transport , be approved. 2. That the proposed additions to the Key Route Network (Appendix 1), extending the Key Route Network by 29.7km be approved.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
To review the current Greater Manchester (GM) Key Route Network (KRN) to ensure full alignment with the Department for Transport recently introduced Major Road Network (MRN).
Recommendations
The GMCA is requested to:
1. Agree the proposal to align the KRN with the MRN as published by the Department for Transport.
2. Approve the proposed additions to the KRN referenced in paragraph 3.5 and shown in Appendix 1, which will extend the KRN by 29.7km.
CONTACT OFFICERS:
Peter Boulton Head of Highways 0161 244 1411
Kevin Hargreaves Key Route Network Manager 0161 244 1955 Mike Purcell Key Route Network Asset Manager 0161 244 1121
Equalities Implications: N/A at this stage.
Climate Change Impact Assessment and Mitigation Measures – N/A
Risk Management: There are no additional risk implications identified from this review.
Legal Considerations: N/A
Financial Consequences – Revenue: As TfGM are not directly responsible for the maintenance of the KRN, there will be no additional financial implications at this time.
There will be however an additional 29.7km of KRN network to steward and monitor. Procedures and processes are already in place for monitoring the current KRN, therefore the additional 29.7km (+4.7%) will be incorporated within KRN network management as BAU.
Financial Consequences – Capital: N/A
Number of attachments to the report: Appendix 1 indicating the additional KRN locations on a GM map.
Comments/recommendations from Overview & Scrutiny Committee
Background papers
27 February 2015, Highways Reform – Proposed Key Route Network, report to GMCA.
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which No exemption means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee 1. INTRODUCTION
1.1The current KRN encompasses 626km of road network, equating to 7% of all local authority managed roads in Greater Manchester. Importantly, the KRN comprises 49% of all A and B roads but carries 63% of the traffic on these roads and 67% during the peaks. The KRN supports the critical mass of trips of high economic importance, including commuting, business and logistics movements.
1.2The KRN has been developed to include the following;
Highway links to key centres and strategic employment sites within and outside of the Greater Manchester boundary; Bus priority corridors and high frequency bus routes; All highway links serving the Strategic Road Network (SRN, also referred to as the motorway network); and Manchester Ship Canal crossings.
1.3The highway network is of varying standard and comprises both single and dual carriageway sections of road. For example, the A666 St Peter’s Way in Bolton and the A580 East Lancashire Road are both high capacity dual carriageway roads carrying significant volumes of longer distance traffic. The majority of the KRN however is constructed to a lower standard, including sections of single carriageway road with one lane in each direction.
1.4The network is to be reviewed at intervals in response to changes to the highway network and development patterns, with a full review at least every five years.
2 CASE FOR CHANGE
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.