That the report be noted. 2. That the latest position against the approved investments from the retained business rates reserve be noted. 3. That the proposed seven additional schemes at a cost of £15.9m be approved. 4. That the return of the residual funding of £16.7 to the 10 Greater Manchester Authorities on the proposed basis be approved, final details to be confirmed between the GMCA Treasurer and the District Treasurers. 5. That the proposals for ongoing monitoring of business rates investments be noted and that the use of any further slippage be submitted to the GMCA for approval with priority placed on supporting businesses and district’s financial positions. 6. That further information on the proposed scheme by Unified Architecture be provided to Councillor Richard Leese in order to give further assurance as to its potential delivery.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
The purpose of this paper is to update the Combined Authority on the latest position against the retained business rates pilot scheme
The report considers the impact of COVID 19 on the plans for the scheme and provides members with an updated analysis of the current funding, the approved programmes and the final list of proposed investments from the scheme.
The paper highlights the remaining uncommitted funds and proposes these are re-distributed to the 10 GM authorities.
Recommendations
The GMCA is asked to:
To note and comment on the contents of the report. To note the latest position against the approved investments from the retained business rates reserve To approve the proposed seven additional schemes at a cost of £15.9m To approve the return of the residual funding of £16.7 to the 10 GM Authorities on the proposed basis to be confirmed between the GMCA treasurer and the District Treasurers To note the proposals for ongoing monitoring of business rates investments and that the use of any further slippage is brought back to the CA for approval with a priority placed on supporting businesses and district’s financial positions
CONTACT OFFICERS: Name: Steve Wilson, Treasurer to GMCA Telephone: 0161 778 7004 E-Mail: [email protected] 1 TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in the No GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which No means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
Risk Management Legal Considerations Financial Consequences – Revenue – these are set out within the report Financial Consequences – Capital - n o n e
BACKGROUND PAPERS: COVID 19 Finance update September GMCA
2 Update on Retained Business Rates
Background
1.1In previous updates to the Combined Authority we have analysed the impact of the COVID 19 pandemic on the funding available to GM through the retained business rates pilot scheme and the impact that might have on the proposed use of that funding.
1.2The pandemic has the following impacts on the scheme:
i) Anticipated receipts of £35m for 2020/21 are not now expected to be delivered, with latest forecast by districts suggesting no additional receipts should now be assumed. ii) The impact of COVID 19 may mean the original investment plans are no longer relevant and must therefore be reviewed. iii) The financial impact of COVID 19 at a GM and district level mean all planned expenditure should be reviewed and only committed if essential. iv) Any uncommitted residual funding from business rates could be used to support the current financial challenge faced by districts.
1.3Following discussions at previous meetings officers, in conjunction with portfolio holders, have reviewed the remaining commitments and potential bids against the retained business rates funding.
1.4If we now assume no additional funding for 2020/21, which is the final year of the current scheme, the total funding carried forward into 2020/21 of £63,527k is the total now available for commitments in this year and beyond.
1.5The February 2020 CA meeting approved a number of new commitments against this funding which, added to the previous commitments agreed by the CA meant a total of £32,046k of the remaining funding had been approved for spend.
1.6In addition to the approved schemes the February meeting of the CA also received details about potential further commitments of £44,395k.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.