Greater Manchester Combined Authority approved this item on Friday 12 February 2021. Below is the council's own wording, with the papers it was decided on.
That the allocation of £18.2m of Brownfield Housing Fund monies to fund Local Authority priority projects that were submitted to MHCLG as part of the Brownfield Hosing Fund bidding process be approved in principle, subject to satisfactory due diligence being undertaken to confirm the deliverability of the projects. 2. That the allocation of £16.01m of funding to those projects set out in Annex 1 of the report where satisfactory due diligence has already been undertaken be approved. 3. That authority be delegated to the GMCA Treasurer acting in conjunction with the GMCA Monitoring Officer to agree the final terms of all the necessary agreements.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
This report requests that Leaders’ approve allocations of Brownfield Housing Fund monies to those projects identified within the report.
RECOMMENDATIONS: It is recommended that Leaders’:
1. Approve, in principle, the allocation of £18.2m of Brownfield Housing Fund monies to fund Local Authority priority projects that were submitted to MHCLG as part of the Brownfield Hosing Fund bidding process, subject to satisfactory due diligence being undertaken to confirm the deliverability of the projects;
2. Approve the allocation of £16.01m of funding to those projects set out in Annex 1 where satisfactory due diligence has already been undertaken; and
3. Delegate authority to the GMCA Treasurer acting in conjunction with the GMCA Monitoring Officer to agree the final terms of all the necessary agreements
Equalities Implications: The Brownfield Housing Fund is aimed at unlocking stalled, brownfield sites across GM. Sites which have been recommended to receive grant funding within this paper represent sites across the GM Districts. Housing which will be delivered as a result of the grant funding will align with those specific housing needs and priorities for that District and as a result will not have any adverse implications from an equality perspective. Climate Change Impact Assessment and Mitigation Measures:
As part of the emerging prioritisation approach for “Tranche 2” of the BHF, the aspirations of the carbon neutral agenda will be addressed.
Risk Management: The grants will be conditional upon a satisfactory outcome of due diligence and ongoing monitoring confirmation that the schemes are being delivered satisfactorily. In view of the nature of the MHCLG grant funding agreements for BHF and the likely approach that any conditions will be mirrored in agreements between the GMCA and scheme promoters, there will be limited risk retained by the GMCA.
Legal Considerations: A detailed grant agreement and other associated legal documentation will be completed for each scheme ahead of the first grant payment. State Aid will be considered further for each individual scheme allocation with any allocation being state aid compliant.
Financial Consequences – Revenue: Any revenue costs are anticipated to be absorbed into the existing Delivery Team budget or subsequent revenue allocation (circa £1.94m) received from MHCLG.
Financial Consequences – Capital: Capital expenditure is funded from the GMCA Brownfield Housing Fund. Funds have since been received from MHCLG and will be distributed to sites based on a prioritisation process, there are therefore no capital consequences for the GMCA. Monitoring and reporting assurance will form part of the existing Single Pot Assurance Framework. The GMCA Accounting Officer will be required to confirm that investment is being used for the purposes agreed under the respective fund to deliver to fund’s objectives.
Number of attachments to the report: 0
Comments/recommendations from Overview & Scrutiny Committee None.
Background papers
[TBC – Previous Brownfield Housing Fund Papers to GMCA] TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in YES the GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which NO means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? TfGMC Overview & Scrutiny Committee
1. INTRODUCTION & BACKGROUND
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.