GMCA Capital Programme 2020/21-2023/24

Approved Committee 1 paper

Greater Manchester Combined Authority approved this item on Friday 12 February 2021. Below is the council's own wording, with the papers it was decided on.

Item6F

Resolved

That the revisions to the 2020/21 capital forecast, as set out in Appendix A and detailed within the repor,t be approved. 2. That the capital programme budget for 2021/22 and the forward commitments, as detailed in the report and in Appendix A, be approved. 3. That it be noted that the capital programme was financed from a combination of grants, external contributions and long term borrowings. 4. That it be noted that provision has been made in the revenue budget for the associated financing costs of borrowing. 5. That the addition to the capital programme of the second Transforming Cities Fund (TCF2) as per the prioritised programme be approved and it be noted that the prioritised TCF 2 programme budgeted capital expenditure for 2021/22 is £2.6 million, as set out in section 6 of the report. 6. That the addition to the capital programme of the ‘OZEV EV (Office for Zero Emission Vehicles Electric Vehicle) Taxi project’ (as part of the Greater Manchester Clean Air Programme) be approved, with a current forecast expenditure of £0.1 million in 2020/21 and £2.0 million budgeted expenditure for 2021/22, as set out in section 9 of the report. 7. That the addition to the capital programme of the Access for All programme (part of the Department for Transport’s Access for All programme for rail stations) be approved, with a current forecast expenditure of £0.1 million in 2020/21 and £1.1 million budgeted expenditure for 2021/22, as set out in section 10 of the report. 8. That authority be delegated to the Chief Executive Officer, GMCA & TfGM, where necessary, to vary individual scheme allocations for the Growth Deal programmes, in order to optimise Growth Deal grant expenditure by 31 March 2021. 9. That it be noted that the capital programme would continue to be reviewed, with any new schemes which have not yet received specific approval being the subject of future reports.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

Purpose of report

To present an update in relation to the Greater Manchester Combined Authority capital expenditure programme for Transport and Economic and Regeneration functions.

Recommendations

GMCA is requested toL

1. Approve the revisions to the 2020/21 capital forecast as set out in Appendix A and detailed within the report. 2. Approve the capital programme budget for 2021/22 and the forward commitments as detailed in the report and in Appendix A. 3. Note that the capital programme is financed from a combination of grants, external contributions and long term borrowings. 4. Note that provision has been made in the revenue budget for the associated financing costs of borrowing. 5. Approve the addition to the capital programme of the second Transforming Cities Fund (TCF2) as per the prioritised programme. The prioritised TCF 2 programme budgeted capital expenditure for 2021/22 is £2.6 million as set out in section 6 of this report. 6. Approve the addition to the capital programme of the ‘OZEV EV (Office for Zero Emission Vehicles Electric Vehicle) Taxi project’ (as part of the Greater Manchester Clean Air Programme) with a current forecast expenditure of £0.1 million in 2020/21 and £2.0 million budgeted expenditure for 2021/22, as set out in section 9 of this report. 7. Approve the addition to the capital programme of the Access for All programme (part of the Department for Transport’s Access for All programme for rail stations) with a current forecast expenditure of £0.1 million in 2020/21 and £1.1 million budgeted expenditure for 2021/22, as set out in section 10 of this report. 8. Grant delegated authority to the Chief Executives to, where necessary, vary individual scheme allocations for the Growth Deal programmes, in order to optimise Growth Deal grant expenditure by 31 March 2021. 9. Note that the capital programme will continue to be reviewed, with any new schemes which have not yet received specific approval being the subject of future reports.

CONTACT OFFICERS:

Name: Steve Wilson, Treasurer to GMCA Telephone: 0161 778 7004 E-Mail: [email protected]

Name: Steve Warrener, Finance and Corporate Services Director, Transport for Greater Manchester Telephone: 0161 244 1025 E-mail: [email removed]

Risk Management – An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action will be taken as necessary.

Legal Considerations – There are no specific legal implications contained within the report

Financial Consequences – Revenue – There are no specific revenue considerations contained within the report, however the revenue budget contains resources to meet the capital costs of the authority. Changes in the capital programme can affect the budget to meet these costs.

Financial Consequences – Capital – The report sets out the forecast expenditure for 2020/21, 2021/22 and future years.

Equalities Implications - There are no specific equality implications contained within the report, however the capital programme approved by the GMCA reflects the priorities for Greater Manchester.

Background papers

 Report to Greater Manchester Combined Authority: ‘GMCA Capital Programme 2019/20 – 2022/23’: 14 February 2020.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
GMCA Capital Programme 2020/21-2023/24Report 669 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 11 attended
EO
Councillor Eamonn O'BrienCommittee Member, expected
GM
GM Mayor Andy BurnhamChair, expected
DG
Councillor David GreenhalghCommittee Member, expected
BW
Councillor Brenda WarringtonVice-Chair, expected
RL
Councillor Richard LeeseVice-Chair, expected
SF
Councillor Sean FieldingCommittee Member, expected
AB
Councillor Allen BrettCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
AW
Councillor Andrew WesternCommittee Member, expected
DM
Councillor David MolyneuxCommittee Member, expected
EW
Councillor Elise WilsonCommittee Member, expected

On this subject at Greater Manchester Combined Authority

Search all
  1. GMCA Capital Programme 2020/21-2023/24This decision
  2. 2026/27 GMCA Capital StrategyApproved
  3. GMCA Revenue and Capital Budgets 2026/27 OverviewNoted
  4. GMCA Capital Programme 2025/26 - 2028/29Noted
  5. GMCA Capital Outturn 2024/25Noted
  6. 2025/26 GMCA Capital StrategyApproved

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies