That the progress made in delivering Electric Vehicle Charging Infrastructure in Greater Manchester be noted. 2. That the continuing need for public sector intervention in charging infrastructure to overcome barriers to Electric Vehicle ownership be noted. 3. That the next steps, as set out in the report, to support the further expansion of the system be approved and that the draft EVCI Strategy be submitted to a meeting of the GMCA this summer.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Subject: Electric Vehicle Charging Infrastructure (EVCI) Update
Report of: Andy Burnham, Mayor of Greater Manchester, Portfolio Lead for Transport and Eamonn Boylan, Chief Executive Officer, GMCA & TfGM.
PURPOSE OF REPORT: To set out the progress made in delivering Electric Vehicle Charging Infrastructure (EVCI) in Greater Manchester. .
RECOMMENDATIONS: The GMCA is requested to:
1. Note the progress made in delivering EVCI in Greater Manchester;
2. Note the continuing need for public sector intervention in charging infrastructure to overcome barriers to EV ownership; and
3. Approve the next steps set out in the report to support the further expansion of the system, and request officers to bring back a draft EVCI Strategy to a meeting of the GMCA this summer.
CONTACT OFFICERS: Simon Warburton [email removed]
Megan Black [email removed] Equalities Implications: Locations of new infrastructure will be the subject of equalities assessments.
Climate Change Impact Assessment and Mitigation Measures – Successful roll-out will have a very positive carbon impact and is a key element of the GM Environment Plan.
Risk Management: TfGM standard practices on risk management have been applied to the EV Programme of work.
Legal Considerations: N/A
Financial Consequences – Revenue: No direct implications in report.
Financial Consequences – Capital: No direct implications in report. Capital implications relating to investing in EV infrastructure across Greater Manchester are considered during business case making.
Number of attachments to the report: None
Comments/recommendations from Overview & Scrutiny Committee N/A
BACKGROUND PAPERS: GMCA Report to Friday 29 November 2019 meeting on Greater Manchester EV system
TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in No the GMCA Constitution
EXEMPTION FROM CALL IN Are there any aspects in this report which N/A means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee 1. INTRODUCTION/BACKGROUND
1.1Electric Vehicle (EV) charging infrastructure is key driver of Greater Manchester (GM)’s ambitions for the environment. EV charging is a core enabler of GM’s ambition to be a carbon-neutral city region by 2038, and the proposals in the Greater Manchester Outline Business Case to tackle Nitrogen Dioxide Exceedances at the Roadside (GM Clean Air Plan) are underpinned by encouraging GM businesses to switch to low and zero emissions vehicles. As part of the public conversation last year on the GM Clean Air Plan proposals, the availability of charging points was cited as a key barrier for businesses and individuals in switching to an EV.
1.2The delivery and operation of Greater Manchester’s publicly funded Electric Vehicle Charging Infrastructure is co-ordinated by TfGM, so that EV can integrate its delivery with wider strategic GM responsibilities such as sustainable journeys, carbon reduction and Clean Air.
1.3In order to support a rapid transition to EVs across Greater Manchester (GM) it will be important to have the right charging infrastructure in the optimal locations to help meet our clean air and low carbon targets, support the 2040 Strategy ambitions and deliver the “Right Mix”.
1.4Greater Manchester has approximately 360 publicly accessible charge points operated and maintained by a number of operators. This includes 126 publicly funded Electric Vehicle Charging points, part of the Be.EV electric vehicle charging network. The Be.EV is currently free to use until the launch of a Pay as You Go model.
1.5Circa 30,000 sessions occurred between 1 September 2020 (post Be.Ev transition) and 31 January 2021. To give a monthly example, in January 2021, there were 5184 sessions from 941 unique drivers. Over this month, there were 1.37 sessions per unit per day.
2. ELECTRIC VEHICLE REGISTRATIONS IN GM
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.