Electric Vehicle Charging Infrastructure (EVCI) Update

Noted Committee 1 paper

Greater Manchester Combined Authority noted this item on Friday 26 March 2021. Below is the council's own wording, with the papers it was decided on.

Item19B

Resolved

That the progress made in delivering Electric Vehicle Charging Infrastructure in Greater Manchester be noted. 2. That the continuing need for public sector intervention in charging infrastructure to overcome barriers to Electric Vehicle ownership be noted. 3. That the next steps, as set out in the report, to support the further expansion of the system be approved and that the draft EVCI Strategy be submitted to a meeting of the GMCA this summer.
Word for word from the decision Greater Manchester Combined Authority published for this meeting. Source: democracy.greatermanchester-ca.gov.uk

Follow this further

Built from Greater Manchester Combined Authority's papers

What the report saysPro

Report to Greater Manchester Combined Authority

GREATER MANCHESTER COMBINED AUTHORITY

Date: 26 March 2021

Subject: Electric Vehicle Charging Infrastructure (EVCI) Update

Report of: Andy Burnham, Mayor of Greater Manchester, Portfolio Lead for Transport and Eamonn Boylan, Chief Executive Officer, GMCA & TfGM.

PURPOSE OF REPORT: To set out the progress made in delivering Electric Vehicle Charging Infrastructure (EVCI) in Greater Manchester. .

RECOMMENDATIONS: The GMCA is requested to:

1. Note the progress made in delivering EVCI in Greater Manchester;

2. Note the continuing need for public sector intervention in charging infrastructure to overcome barriers to EV ownership; and

3. Approve the next steps set out in the report to support the further expansion of the system, and request officers to bring back a draft EVCI Strategy to a meeting of the GMCA this summer.

CONTACT OFFICERS: Simon Warburton [email removed]

Megan Black [email removed] Equalities Implications: Locations of new infrastructure will be the subject of equalities assessments.

Climate Change Impact Assessment and Mitigation Measures – Successful roll-out will have a very positive carbon impact and is a key element of the GM Environment Plan.

Risk Management: TfGM standard practices on risk management have been applied to the EV Programme of work.

Legal Considerations: N/A

Financial Consequences – Revenue: No direct implications in report.

Financial Consequences – Capital: No direct implications in report. Capital implications relating to investing in EV infrastructure across Greater Manchester are considered during business case making.

Number of attachments to the report: None

Comments/recommendations from Overview & Scrutiny Committee N/A

BACKGROUND PAPERS: GMCA Report to Friday 29 November 2019 meeting on Greater Manchester EV system

TRACKING/PROCESS Does this report relate to a major strategic decision, as set out in No the GMCA Constitution

EXEMPTION FROM CALL IN Are there any aspects in this report which N/A means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? GM Transport Committee Overview & Scrutiny Committee 1. INTRODUCTION/BACKGROUND

1.1Electric Vehicle (EV) charging infrastructure is key driver of Greater Manchester (GM)’s ambitions for the environment. EV charging is a core enabler of GM’s ambition to be a carbon-neutral city region by 2038, and the proposals in the Greater Manchester Outline Business Case to tackle Nitrogen Dioxide Exceedances at the Roadside (GM Clean Air Plan) are underpinned by encouraging GM businesses to switch to low and zero emissions vehicles. As part of the public conversation last year on the GM Clean Air Plan proposals, the availability of charging points was cited as a key barrier for businesses and individuals in switching to an EV.

1.2The delivery and operation of Greater Manchester’s publicly funded Electric Vehicle Charging Infrastructure is co-ordinated by TfGM, so that EV can integrate its delivery with wider strategic GM responsibilities such as sustainable journeys, carbon reduction and Clean Air.

1.3In order to support a rapid transition to EVs across Greater Manchester (GM) it will be important to have the right charging infrastructure in the optimal locations to help meet our clean air and low carbon targets, support the 2040 Strategy ambitions and deliver the “Right Mix”.

1.4Greater Manchester has approximately 360 publicly accessible charge points operated and maintained by a number of operators. This includes 126 publicly funded Electric Vehicle Charging points, part of the Be.EV electric vehicle charging network. The Be.EV is currently free to use until the launch of a Pay as You Go model.

1.5Circa 30,000 sessions occurred between 1 September 2020 (post Be.Ev transition) and 31 January 2021. To give a monthly example, in January 2021, there were 5184 sessions from 941 unique drivers. Over this month, there were 1.37 sessions per unit per day.

2. ELECTRIC VEHICLE REGISTRATIONS IN GM

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Electric Vehicle Charging Infrastructure (EVCI) UpdateReport 439 KB DownloadRead as text

At this meeting

Whole meeting
1ApologiesNoted 2Chairs Announcements and Urgent BusinessNoted 3Declarations of InterestDecided 4Minutes of the GMCA meetings held 12 February & 23 March 2021Approved 5Minutes of the Overview & Scrutiny Committee meetings held in March 2021Noted 6Minutes of the GM Local Enterprise Partnership held on 18 March 2021Noted 7Minutes of the GM Transport Committee held 19 February 2021Noted 8Update on Greater Manchester Independent Inequalities CommissionNoted 9Greater Manchester's Equality PanelsNoted 10Living with Covid Resilience Plan - Quarter 2 Progress UpdateNoted 11A Bed Every Night 2021/22Approved 12GM Devolved Adult Education Budget (AEB) Year 1 update and next StepsNoted 13Covid-19 Contingency support measures for GM Work & Skills ProgrammesNoted 14Troubled Families FundingAgreed 15Greater Manchester Culture Recovery Plan 2021Noted 16Monthly Economic UpdateNoted 17Preparations for the UN Climate Change Conference (COP26)Noted 18Green Homes Grant Local Authority Delivery Scheme Phase 2Agreed 19Transport Strategy Delivery UpdatesNoted 19AActive Travel UpdateNoted
19BElectric Vehicle Charging Infrastructure (EVCI) UpdateThis decision
19CCity Centre Transport StrategyNoted 20Mayor's Challenge Fund Financial ApprovalsAgreed 21Local Growth Deal (1, 2 and 3) - Six monthly Progress UpdateNoted 22Metrolink Phase 3 Monitoring & EvaluationNoted 23Greater Manchester Good Landlord SchemeApproved 24Greater Manchester Brownfield Housing Fund - Tranche 2Agreed 25Greater Manchester Local Enterprise Partnership Membership ReviewApproved 26Growth Co Business Plan 2021/22Noted 27Greater Manchester Housing Investment Loans UpdateNoted 28Greater Manchester Housing Investment Loans ApprovalsApproved 29GM Investment Framework, Conditional Project Approval and temporary delegationApproved 30A Review of Remuneration for the Elected Mayor of the Greater Manchester Combined Authority (GMCA) and the Independent Members/Person appointed to the GMCA Audit and Standards CommitteesApproved 31Exclusion of Press & PublicDecided 32Growth Co Business Plan 2021/22Private 33Greater Manchester Housing Investment Loans ApprovalsPrivate 34GM Investment Framework, Conditional Project ApprovalPrivate

Who was there

0 of 13 attended
DD
Diane DaleyCouncil Staff, expected
SH
Stacey HeywoodCouncil Staff, expected
EO
Councillor Eamonn O'BrienCommittee Member, expected
GM
GM Mayor Andy BurnhamChair, expected
DG
Councillor David GreenhalghCommittee Member, expected
BW
Councillor Brenda WarringtonVice-Chair, expected
RL
Councillor Richard LeeseVice-Chair, expected
SF
Councillor Sean FieldingCommittee Member, expected
AB
Councillor Allen BrettCommittee Member, expected
CM
City Mayor Paul DennettCommittee Member, expected
AW
Councillor Andrew WesternCommittee Member, expected
DM
Councillor David MolyneuxCommittee Member, expected

All 13 on the meeting page

On this subject at Greater Manchester Combined Authority

Search all
  1. Electric Vehicle Charging Infrastructure (EVCI) UpdateThis decision
  2. Electric Vehicle Charging PricingDecided
  3. Electric Vehicle Charging TariffApproved
  4. Electric vehicle charging tariffNoted
  5. Electric Vehicles Charging Infrastructure Delivery (key Decision)Noted
  6. Greater Manchester Electric Vehicle Charging TariffNoted

More from Greater Manchester Combined Authority Greater Manchester Combined Authority

All decisions
MeetingDecisionOutcome
25 Sep 2026 ApologiesThat apologies be received from Councillor Eleanor Wills (Tameside), with Councillor Andrew Mclaren attending as subs... Decided Open
25 Sep 2026 Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities... Decided Open
25 Sep 2026 Declarations of InterestThat it be noted that no declarations of interest were received. Noted Open
25 Sep 2026 GMCA Minutes - 10 July 2026That the minutes of the GMCA meeting held on 10 July 2026 be approved. Approved Open
25 Sep 2026 Bee Network Committee - 25 June 2026That the proceedings of the Bee Network Committee held on 25 June 2026 be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies