That the 2021/22 provisional outturn capital expenditure of £499.275 million compared to the forecast position, presented to the GMCA on 11 February 2022 of £379.917 million, which was a variance of £19.358 million in spend compared to forecast, be noted.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
The GMCA is requested to note the 2021/22 provisional outturn capital expenditure of £499.275 million compared to the forecast position presented to the GMCA on 11 February 2022 of £479.917 million which is a variance of £19.358m reduction in spend compared to forecast.
Name: Steve Warrener, Finance and Corporate Services Director, Transport for Greater Manchester Telephone: [phone removed] E-mail: [email removed] Equalities Impact, Carbon and Sustainability Assessment:
No decisions are included in this report.
Risk management
An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – there are no specific risks identified with the 2021/22 provisional outturn position.
Legal Considerations
There are no specific legal implications with regards to the 2021/22 budget update.
Financial Consequences – Revenue
There are no specific revenue implications contained in this report.
Financial Consequences – Capital
The report sets out the capital expenditure for 2021/22
Number of attachments to the report: 0
Comments/recommendations from Overview & Scrutiny Committee
N/a
Background papers
GMCA Capital Programme 2020/21 – 2023/24 - 12 February 2021 GMCA Capital Update 2021/22 – Quarter 1 – 10 September 2021 GMCA Capital Update 2021/22 – Quarter 2 – 26 November 2021 GMCA Capital Update 2021/22 – Quarter 3 – 11 February 2022
Tracking/ Process
Does this report relate to a major strategic decision, as set out in the GMCA Constitution
No
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency? No GM Transport Committee
N/a
Overview and Scrutiny Committee
N/a 1. INTRODUCTION AND BACKGROUND
1.1The Greater Manchester Combined Authority (GMCA) approved the 2021/22 Capital Programme at its meeting on 12 February 2021. Updated forecast outturns were provided on a quarterly basis during 2021/22.
1.2GMCA’s capital programme includes Greater Manchester Fire and Rescue Services, Economic Development and Regeneration programmes, Waste & Resources Service and the continuation of the programme of activity currently being delivered by Transport for Greater Manchester (TfGM) and Local Authorities including the following elements:
a) The Greater Manchester Transport Fund (‘GMTF’); b) Metrolink Trafford Park Line Extension; c) Clean Air Schemes including Early Measures Investment Fund (EMIF), Clean Bus Initiatives, Office for Zero emissions Vehicles (OZEV), Electric Vehicles (EV), Taxi, Clean Air Plan (CAP), EV Taxi Infrastructure, Clean Air Zones (CAZ) and Financial Support Schemes (FSS); d) Other capital projects and programmes including Transforming Cities 1 and 2, Active Travel, Cycle City Ambition Grant (CCAG 2), Rail – Access for All, Cycle Safety, and Bus Franchising; e) Transport Growth Deal Major Schemes; f) Minor Works (including schemes funded by Integrated Transport Capital Block and Growth Deal); g) Capital Highways Maintenance, Traffic Signals and Full Fibre; h) Investments including Growing Places, Regional Growth Fund and Housing Investment Fund; i) Economic Development and Regeneration Growth Deal Schemes; j) Fire and Rescue Service Schemes; and k) Waste and Resources Schemes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.