That the 2022/23 actual outturn capital expenditure of £442.6m, compared to the forecast position presented to GMCA on 10 February 2023 of £462.1m, be noted. That an amendment to an error on appendix 1 to the report will be circulated to GMCA members and published on the GMCA website.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
This report is to inform members of the Greater Manchester Combined Authority of the capital outturn for 2022/2023.
Recommendations
The GMCA is requested to:
1. Note the 2022/23 actual outturn capital expenditure of £442.6m compared to the forecast position presented to GMCA on 10 February 2023 of £462.1m. Contact Officers
Name: Steve Warrener, Managing Director, Transport for Greater Manchester
Telephone: [phone removed]
E-mail: [email removed]
Equalities Impact, Carbon and Sustainability Assessment:
There are no specific equalities impact, carbon and sustainability issues contained within this report.
Risk management
An assessment of major budget risks faced by the authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary.
Legal Considerations
There are no specific legal implications contained within the report. Financial Consequences – Revenue
There are no specific revenue considerations contained within the report.
Financial Consequences – Capital
The report reports the actual capital expenditure for 2022/23.
Number of attachments to the report: None
Background Papers GMCA Capital Programme 2021/22 – 2024/25 - 11 February 2022 GMCA 2022/23 Capital Update – Quarter 1 – 29 July 2022 GMCA 2022/23 Capital Update – Quarter 2 – 28 Oct 2022 GMCA 2022/23 Capital Update – Quarter 3 – 10 February 2023 Transport Capital Programme – 26 May 2023 Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
GM Transport Committee
Overview and Scrutiny Committee 1. Introduction/Background 1.1 The Greater Manchester Combined Authority (GMCA) approved the 2022/23 capital programme at its meeting on 11 February 2022. Updated forecast positions have been provided on a quarterly basis during 2022/23.
1.2GMCA’s capital programme includes Greater Manchester Fire and Rescue Services, Economic Development and Regeneration programmes, Waste and Resources Service and the continuation of the programme of activity currently being delivered by GMCA, Transport for Greater Manchester (TfGM) and Local Authorities including the following elements:
a) The Greater Manchester Transport Fund (‘GMTF’);
b) Metrolink Trafford Park Line Extension;
c) Clean Air Schemes including Early Measures Investment Fund (EMIF), Clean Bus Initiatives, Office for Zero emissions Vehicles (OZEV), Electric Vehicles (EV), Taxi, EV Taxi Infrastructure, Clean Air Zones (CAZ), Financial Support Schemes (FSS) and DEFRA Air Quality Monitoring with expenditure met in full from government grant;
d) City Regions Sustainable Transport Settlement (CRSTS) funded schemes;
e) Other capital projects and programmes including Transforming Cities Fund 1, Active Travel, Cycle City Ambition Grant (CCAG 2), Rail – Access for All, Cycle Safety, Bus Franchising and Zero Emission Buses Regional Areas (ZEBRA);
f) Transport Growth Deal Major Schemes;
g) Minor Works (including schemes funded by Integrated Transport Capital Block and Growth Deal);
h) Capital Highways Maintenance, Traffic Signals and Full Fibre;
i) Investments including Growing Places, Regional Growth Fund and Housing Investment Fund;
j) Economic Development and Regeneration Growth Deal Schemes;
k) Fire and Rescue Service Schemes; and
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.