Greater Manchester Combined Authority noted this item on Friday 27 September 2024. Below is the council's own wording, with the papers it was decided on.
That the update from the DfT Outline Business Case review and associated risks highlighted be noted. 2. That the proposals for securing the land interests required to deliver the scheme as set out within this report be noted. 3. That TfGM securing the required land interests in accordance with the agreed programme budgets be approved. 4. That the submission of a planning application for the scheme and the preparation of the CPO and supporting documentation including issuing Land Interest Questionnaires to affected landowners be approved. 5. That the entering into of any ancillary agreements required to achieve the scheme objectives be approved. 6. That the importance of ensuring all railway stations on the 8 rail lines, identified for integration within the wider Bee Network, be fully accessible be endorsed.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
Failure to progress planning application and land negotiations at this time will lead to delay to delivery of the scheme within the committed timeframes and funding envelope.
Whilst negotiations with affected landowners are progressing well, a CPO and supporting documentation should be prepared in parallel to provide the back-up needed should we fail to acquire by agreement. If we can secure those land interests by way of Options, we can discontinue with the CPO process. Further engagement with landowners is planned for the end of August. The landowners will be informed that we are progressing a CPO but only as a last resort and we will then make the offers for the acquisition of the rights by agreement.
Legal Considerations
The use of CPO powers must be as a last resort. An acquiring authority must be able to demonstrate that they have done all they can to acquire the land by negotiation. It is therefore important for TfGM to now make offers to acquire the land interests required for the Scheme.
TfGM’s CPO powers are contained within the general powers of Passenger Transport Executives within s10 of the Transport Act 1968 and if required will be relied upon to secure the creation of the station only. The powers cannot be utilised for the wider masterplan elements of the Project, specifically the public access to Wigan Centre over land owned by Wigan Council and the Public House.
Financial Consequences – Revenue
Financial Consequences – Capital
The costs of securing the land required is by way of grant funding as referred to in paragraph 1.5 of this report
Number of attachments to the report: 0
Comments/recommendations from Overview & Scrutiny Committee
N/A
Background Papers None Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution?
Yes
Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
No
Bee Network Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor David MolyneuxCommittee Member, expected
BC
Councillor Bev CraigCommittee Member, expected
Hear about the next one first
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.