Greater Manchester Combined Authority approved this item on Friday 27 September 2024. Below is the council's own wording, with the papers it was decided on.
That the current 2024/25 forecast of £636.3m compared to the 2024/25 budget of £685.2m and approve changes to the capital programme as set out in the report be noted. 2. That the addition of £3.8m to the 2024/25 GMCA Capital Programme from an extension to the fourth round of the Active Travel Fund (ATF4) award as outlined in section 2.6.1 be approved. 3. That the addition to the capital programme of £16.2m of Local Electric Vehicle Infrastructure (LEVI) funding to deliver local, on-street charging infrastructure across Greater Manchester and to accelerate the commercialisation of, and investment in, the local charging infrastructure sector be approved. 4. That the addition to the capital programme of £4.8m of Investment Zone grant funding to support the development of high-potential clusters identified as Investment Zones with a focus on developing Advanced Manufacturing & Materials be approved.
Word for word from the decision Greater Manchester Combined Authority published for this meeting.Source: democracy.greatermanchester-ca.gov.uk
Follow this further
Built from Greater Manchester Combined Authority's papers
An assessment of major budget risks faced by the Authority are carried out quarterly as part of the reporting process – at the present time a significant proportion of the capital budget is funded through grant. In order to mitigate the risk of monetary claw back the full programme is carefully monitored against the grant conditions and further action would be taken as necessary.
Legal Considerations
There are no specific legal implications contained within the report.
Financial Consequences – Revenue
There are no specific revenue considerations contained within the report.
Financial Consequences – Capital
The report sets out the forecast capital expenditure for 2024/25.
Number of attachments to the report: None
Background Papers GMCA Capital Programme 2023/24 – 2026/2027– 9 February 2024
Transport Capital Programme Report – 21 March 2024 (BNC)
Transport Infrastructure Pipeline Update Report – 27 June 2024 (BNC)
Transport Infrastructure Pipeline Update Report - 25 July 2024 (BNC)
Tracking/ Process Does this report relate to a major strategic decision, as set out in the GMCA Constitution? Exemption from call in
Are there any aspects in this report which means it should be considered to be exempt from call in by the relevant Scrutiny Committee on the grounds of urgency?
Bee Network Committee
N/A
Overview and Scrutiny Committee
N/A 1. Introduction/Background
1.1The Greater Manchester Combined Authority approved the 2024/25 capital programme at its meeting on 9 February 2024. This report provides the first in a series of updates throughout 2024/25.
1.2The Authority’s capital programme includes Greater Manchester Fire and Rescue Services (GMFRS), Economic Development & Regeneration programmes, Waste & Resources Service and the continuation of the programme of activity currently being delivered by the Authority, Transport for Greater Manchester (TfGM) and GM Local Authorities (LA) including the following elements:
a) The Greater Manchester Transport Fund (GMTF);
b) Metrolink Trafford Park Line Extension;
c) Clean Air funded schemes;
d) City Region Sustainable Transport Settlement (CRSTS) funded schemes;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Greater Manchester Combined Authority at Greater Manchester Combined Authority and we tell you when its next papers are published, before the meeting rather than after it.
Chairs Announcements and Urgent BusinessThat the following Portfolio Leaders were announced: Portfolio Leader Portfolio Leader Safer and Stronger Communities...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.